4330 N LEMP AVE 91604
Certificate Information: 4330 N LEMP AVE 91604
- Application / Permit
- 19010-20000-03507
- Plan Check / Job No.
- B19VN13236
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 24'-0" x 29'-0" One-Story Acessory Dwelling Unit per CA Govt. Code 65852.2(e)(1)(B) and applicable part of LAMC 12.22 A.33 (c)-(d), (g).
- Permit Issued
- Issued on 11/21/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/6/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/8/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/5/2019 | OMID HEDAYAT |
| Corrections Issued | 9/10/2019 | OMID HEDAYAT |
| Quality Review Completed | 9/10/2019 | STEVEN KIM |
| Building Plans Picked Up | 9/13/2019 | APPLICANT |
| Green Plans Picked Up | 9/13/2019 | APPLICANT |
| Applicant returned to address corrections | 2/18/2022 | OMID HEDAYAT |
| Applicant returned to address corrections | 8/19/2022 | OMID HEDAYAT |
| Plan Check Approved | 8/19/2022 | OMID HEDAYAT |
| Issued | 11/21/2022 | APPLICANT |
| CofO in Progress | 2/11/2025 | CHRISTOPHER ROJAS |
| Permit Finaled | 3/6/2025 | RUBEN SALAS |
| CofO Issued | 3/6/2025 | RUBEN SALAS |
| Permit Finaled | 3/6/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Construction near power lines | Cleared | 10/24/2019 | RIDWAN HARDY |
| Address approval | Cleared | 11/21/2019 | ELAINE LEI |
| Eng Process Fee Ord 176,300 | Cleared | 11/21/2019 | ELAINE LEI |
| Roof/Waste drainage to street | Cleared | 11/21/2019 | ELAINE LEI |
| Sewer availability | Cleared | 11/21/2019 | ELAINE LEI |
| Hydrant and Access approval | Cleared | 11/25/2019 | GEORGE SUCHAND |
| ZI | Cleared | 11/25/2019 | MARITZA PRZEKOP |
| Construction within easement | Cleared | 4/17/2021 | WALTER RAMIREZ |
| Low Impact Development | Cleared | 10/15/2021 | MARTIN FRAGOSO |
| Green Code | Cleared | 2/18/2022 | DAVID MATSON |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Hamilton,, John O; Lic. No.: C53284 | P O BOX 866 HAWTHORNE, CA 90251 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/9/2022 | Partial Approval | JACK KARGODORIAN |
| Excavation/Setback/Form/Re-Bar | 5/4/2023 | Corrections Issued | MICHEL ABAJAN |
| Footing/Foundation/Slab | 5/4/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| PLUMBING-Rough | 5/4/2023 | Partial Approval | MICHEL ABAJAN |
| Excavation/Setback/Form/Re-Bar | 5/10/2023 | Approved | JACK KARGODORIAN |
| Deputy Wood Construction | 6/5/2023 | Conditional Approval | MICHAEL SMITH |
| Wood Frame | 6/6/2023 | Partial Approval | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 7/12/2023 | Partial Approval | JACK KARGODORIAN |
| ELECTRICAL-Rough | 7/12/2023 | Approved | JACK KARGODORIAN |
| Green Building Rough | 7/12/2023 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 7/12/2023 | Not Ready for Inspection | JACK KARGODORIAN |
| Verify Sprinkler Sign Off | 7/12/2023 | Approved | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 8/3/2023 | Approved | JACK KARGODORIAN |
| Green Building Rough | 8/3/2023 | Approved | JACK KARGODORIAN |
| HVAC-Rough | 8/3/2023 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 8/3/2023 | Approved | JACK KARGODORIAN |
| Insulation | 12/19/2023 | Approved | KIRK SANDERS |
| Interior/Exterior Lathing | 12/19/2023 | Partial Approval | KIRK SANDERS |
| Drywall Nailing | 3/4/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Shower Pan | 4/15/2024 | Approved | CHRISTOPHER ROJAS |
| Sewer | 10/3/2024 | Approved | CHRISTOPHER ROJAS |
| Underground Mechanical | 10/3/2024 | Approved | CHRISTOPHER ROJAS |
| Gas Test | 10/17/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 1/15/2025 | Partial Inspection | CHRISTOPHER ROJAS |
| Final | 1/15/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Footing/Foundation/Slab | 1/15/2025 | Approved | CHRISTOPHER ROJAS |
| Gas Test | 1/15/2025 | Approved | CHRISTOPHER ROJAS |
| Green Building Final | 1/15/2025 | Partial Inspection | CHRISTOPHER ROJAS |
| HVAC-Final | 1/15/2025 | Partial Inspection | CHRISTOPHER ROJAS |
| PLUMBING-Final | 1/15/2025 | Partial Inspection | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 1/15/2025 | SGSOV Not Ready | CHRISTOPHER ROJAS |
| Service/Power Release | 1/15/2025 | Partial Inspection | CHRISTOPHER ROJAS |
| Smoke Detectors | 1/15/2025 | Partial Inspection | CHRISTOPHER ROJAS |
| Final | 1/28/2025 | Corrections Issued | MISAEL ESPARZA |
| Green Building Final | 1/28/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 1/28/2025 | SGSOV Not Ready | MISAEL ESPARZA |
| Service/Power Release | 1/28/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Smoke Detectors | 1/28/2025 | Corrections Issued | MISAEL ESPARZA |
| Final | 1/30/2025 | Partial Inspection | CHRISTOPHER ROJAS |
| Green Building Final | 1/30/2025 | Approved | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 1/30/2025 | SGSOV Not Ready | CHRISTOPHER ROJAS |
| Service/Power Release | 1/30/2025 | Partial Inspection | CHRISTOPHER ROJAS |
| Smoke Detectors | 1/30/2025 | Approved | CHRISTOPHER ROJAS |
| Final | 2/10/2025 | OK to Issue CofO | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 2/10/2025 | SGSOV Approved | CHRISTOPHER ROJAS |
| Service/Power Release | 2/10/2025 | Approved | CHRISTOPHER ROJAS |