4330 N LEMP AVE 91604

Certificate Information: 4330 N LEMP AVE 91604

Application / Permit
19010-20000-03507
Plan Check / Job No.
B19VN13236
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 24'-0" x 29'-0" One-Story Acessory Dwelling Unit per CA Govt. Code 65852.2(e)(1)(B) and applicable part of LAMC 12.22 A.33 (c)-(d), (g).
Permit Issued
Issued on 11/21/2022
Issuing Office
Valley
Current Status
CofO Issued on 3/6/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/8/2019 APPLICANT
Assigned to Plan Check Engineer 9/5/2019 OMID HEDAYAT
Corrections Issued 9/10/2019 OMID HEDAYAT
Quality Review Completed 9/10/2019 STEVEN KIM
Building Plans Picked Up 9/13/2019 APPLICANT
Green Plans Picked Up 9/13/2019 APPLICANT
Applicant returned to address corrections 2/18/2022 OMID HEDAYAT
Applicant returned to address corrections 8/19/2022 OMID HEDAYAT
Plan Check Approved 8/19/2022 OMID HEDAYAT
Issued 11/21/2022 APPLICANT
CofO in Progress 2/11/2025 CHRISTOPHER ROJAS
Permit Finaled 3/6/2025 RUBEN SALAS
CofO Issued 3/6/2025 RUBEN SALAS
Permit Finaled 3/6/2025 RUBEN SALAS

Permit Application Clearance Information

Construction near power lines Cleared 10/24/2019 RIDWAN HARDY
Address approval Cleared 11/21/2019 ELAINE LEI
Eng Process Fee Ord 176,300 Cleared 11/21/2019 ELAINE LEI
Roof/Waste drainage to street Cleared 11/21/2019 ELAINE LEI
Sewer availability Cleared 11/21/2019 ELAINE LEI
Hydrant and Access approval Cleared 11/25/2019 GEORGE SUCHAND
ZI Cleared 11/25/2019 MARITZA PRZEKOP
Construction within easement Cleared 4/17/2021 WALTER RAMIREZ
Low Impact Development Cleared 10/15/2021 MARTIN FRAGOSO
Green Code Cleared 2/18/2022 DAVID MATSON

Contact Information

Contractor Owner-Builder       ,
Engineer Hamilton,, John O; Lic. No.: C53284 P O BOX 866      HAWTHORNE, CA 90251

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/9/2022 Partial Approval JACK KARGODORIAN
Excavation/Setback/Form/Re-Bar 5/4/2023 Corrections Issued MICHEL ABAJAN
Footing/Foundation/Slab 5/4/2023 Not Ready for Inspection MICHEL ABAJAN
PLUMBING-Rough 5/4/2023 Partial Approval MICHEL ABAJAN
Excavation/Setback/Form/Re-Bar 5/10/2023 Approved JACK KARGODORIAN
Deputy Wood Construction 6/5/2023 Conditional Approval MICHAEL SMITH
Wood Frame 6/6/2023 Partial Approval JACK KARGODORIAN
BUILDING-Rough-Frame 7/12/2023 Partial Approval JACK KARGODORIAN
ELECTRICAL-Rough 7/12/2023 Approved JACK KARGODORIAN
Green Building Rough 7/12/2023 Approved JACK KARGODORIAN
PLUMBING-Rough 7/12/2023 Not Ready for Inspection JACK KARGODORIAN
Verify Sprinkler Sign Off 7/12/2023 Approved JACK KARGODORIAN
BUILDING-Rough-Frame 8/3/2023 Approved JACK KARGODORIAN
Green Building Rough 8/3/2023 Approved JACK KARGODORIAN
HVAC-Rough 8/3/2023 Approved JACK KARGODORIAN
PLUMBING-Rough 8/3/2023 Approved JACK KARGODORIAN
Insulation 12/19/2023 Approved KIRK SANDERS
Interior/Exterior Lathing 12/19/2023 Partial Approval KIRK SANDERS
Drywall Nailing 3/4/2024 Approved ROBERTO PALACIOS-LOPEZ
Shower Pan 4/15/2024 Approved CHRISTOPHER ROJAS
Sewer 10/3/2024 Approved CHRISTOPHER ROJAS
Underground Mechanical 10/3/2024 Approved CHRISTOPHER ROJAS
Gas Test 10/17/2024 Corrections Issued CHRISTOPHER ROJAS
ELECTRICAL-Final 1/15/2025 Partial Inspection CHRISTOPHER ROJAS
Final 1/15/2025 Corrections Issued CHRISTOPHER ROJAS
Footing/Foundation/Slab 1/15/2025 Approved CHRISTOPHER ROJAS
Gas Test 1/15/2025 Approved CHRISTOPHER ROJAS
Green Building Final 1/15/2025 Partial Inspection CHRISTOPHER ROJAS
HVAC-Final 1/15/2025 Partial Inspection CHRISTOPHER ROJAS
PLUMBING-Final 1/15/2025 Partial Inspection CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 1/15/2025 SGSOV Not Ready CHRISTOPHER ROJAS
Service/Power Release 1/15/2025 Partial Inspection CHRISTOPHER ROJAS
Smoke Detectors 1/15/2025 Partial Inspection CHRISTOPHER ROJAS
Final 1/28/2025 Corrections Issued MISAEL ESPARZA
Green Building Final 1/28/2025 Not Ready for Inspection MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 1/28/2025 SGSOV Not Ready MISAEL ESPARZA
Service/Power Release 1/28/2025 Not Ready for Inspection MISAEL ESPARZA
Smoke Detectors 1/28/2025 Corrections Issued MISAEL ESPARZA
Final 1/30/2025 Partial Inspection CHRISTOPHER ROJAS
Green Building Final 1/30/2025 Approved CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 1/30/2025 SGSOV Not Ready CHRISTOPHER ROJAS
Service/Power Release 1/30/2025 Partial Inspection CHRISTOPHER ROJAS
Smoke Detectors 1/30/2025 Approved CHRISTOPHER ROJAS
Final 2/10/2025 OK to Issue CofO CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 2/10/2025 SGSOV Approved CHRISTOPHER ROJAS
Service/Power Release 2/10/2025 Approved CHRISTOPHER ROJAS