13372 N BORDEN AVE 91342

Certificate Information: 13372 N BORDEN AVE 91342

Application / Permit
19010-20000-03505
Plan Check / Job No.
B19VN13223
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSE IRREG. 28'-6"X50'-6" ONE STORY ACCESSORY DWELLING UNIT WITH ATTACHED PORCH _ PER AB 494 AND SB 229_ ALL WORK TO COMPLY WITH WOOD FRAME PRESCRIPTIVE PROVISIONS [SEE COMMENTS].
Permit Issued
Issued on 1/22/2020
Issuing Office
Valley
Current Status
CofO Issued on 7/5/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/7/2019 APPLICANT
Assigned to Plan Check Engineer 9/5/2019 DAWN MC NULTY
Green Plans Picked Up 9/6/2019 APPLICANT
Corrections Issued 9/11/2019 DAWN MC NULTY
Quality Review Completed 9/12/2019 CHON CHIO KUO
Building Plans Picked Up 9/13/2019 APPLICANT
Applicant returned to address corrections 12/2/2019 DAWN MC NULTY
Plan Check Approved 12/18/2019 DAWN MC NULTY
Issued 1/22/2020 LADBS
CofO in Progress 3/21/2024 KEVIN BERBERYAN
No Progress 5/2/2024 KEVIN BERBERYAN
CofO in Progress 5/2/2024 KEVIN BERBERYAN
CofO in Progress 5/6/2024 KEVIN BERBERYAN
CofO in Progress 7/3/2024 ROBERT GOLD
Permit Finaled 7/5/2024 RUBEN SALAS
CofO Issued 7/5/2024 RUBEN SALAS
Permit Finaled 7/5/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 9/13/2019 ADRIAN CASTRO
CPC Cleared 9/13/2019 MARITZA PRZEKOP
Permit Cleared 9/13/2019 ADRIAN CASTRO
ZA Case Cleared 9/13/2019 MARITZA PRZEKOP
ZA Case Cleared 9/13/2019 MARITZA PRZEKOP
Hydrant and Access approval Cleared 10/15/2019 GEORGE SUCHAND
Eng Process Fee Ord 176,300 Cleared 10/18/2019 GUILLERMO PETRA
Sewer availability Cleared 10/18/2019 GUILLERMO PETRA
Trees in Parkway Cleared 10/23/2019 ADRIAN SANCHEZ
Green Code Cleared 12/4/2019 AARON COSTA
Low Impact Development Cleared 12/17/2019 RYAN HUDSON
Roof/Waste drainage to street Cleared 12/17/2019 ERIK BEASLEY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/10/2020 Approved MARK JOHNSON
Footing/Foundation/Slab 10/23/2020 Partial Approval MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 1/5/2021 Corrections Issued MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 1/14/2021 Not Ready for Inspection MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 1/20/2021 Partial Approval MISAEL ESPARZA
Interior/Exterior Lathing 6/28/2021 Approved MICHEL ABAJAN
Insulation 7/28/2021 Approved MICHEL ABAJAN
Drywall Nailing 8/26/2021 Approved MISAEL ESPARZA
Green Building Rough 8/26/2021 Approved MISAEL ESPARZA
Rough-Elec/Plmb/HVAC 8/26/2021 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 4/20/2022 Corrections Issued JOHN HAYES
Shower Pan 4/20/2022 Approved JOHN HAYES
Gas Test 6/23/2022 Approved HERBERT GIRON
BUILDING-Rough-Frame 2/9/2024 Approved JOHN COLEMAN
Final 2/9/2024 Corrections Issued JOHN COLEMAN
Footing/Foundation/Slab 2/9/2024 Approved JOHN COLEMAN
Green Building Final 2/9/2024 Not Ready for Inspection JOHN COLEMAN
SGSOV-Seismic Gas S/O Valve 2/9/2024 SGSOV Approved JOHN COLEMAN
Service/Power Release 2/9/2024 Partial Inspection JOHN COLEMAN
Smoke Detectors 2/9/2024 Approved JOHN COLEMAN
Verify Sprinkler Sign Off 2/9/2024 Approved JOHN COLEMAN
Final 3/20/2024 Partial Approval KEVIN BERBERYAN
Green Building Final 3/20/2024 Approved KEVIN BERBERYAN
Service/Power Release 3/20/2024 Approved KEVIN BERBERYAN
Final 5/6/2024 Corrections Issued KEVIN BERBERYAN
Final 7/3/2024 OK to Issue CofO KEVIN BERBERYAN