18633 1/2 W VANOWEN ST 91335

Certificate Information: 18633 1/2 W VANOWEN ST 91335

Application / Permit
19010-20000-03499
Plan Check / Job No.
B19VN13192
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSE 27'X45' ONE STORY ACCESSORY DWELLING UNIT WITH ATTACHED 13'X21' ONE CAR GARAGE_BUILDING SHALL BE FULLY SPRINKLER THROUGH OUT WITH NFPA 13D [SEE COMMENTS].
Permit Issued
Issued on 7/10/2020
Issuing Office
Current Status
CofO Issued on 3/23/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/7/2019 APPLICANT
Green Plans Picked Up 8/28/2019 APPLICANT
Assigned to Plan Check Engineer 9/5/2019 DAWN MC NULTY
Corrections Issued 9/23/2019 DAWN MC NULTY
Quality Review Completed 9/25/2019 CHON CHIO KUO
Building Plans Picked Up 9/26/2019 APPLICANT
Plan Check Approved 5/18/2020 DAWN MC NULTY
Issued 7/10/2020 APPLICANT
CofO in Progress 3/18/2021 VINCENT HANLEY
Permit Finaled 3/23/2021 MICHAEL SMITH
CofO Issued 3/23/2021 MICHAEL SMITH
Permit Finaled 3/23/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 11/14/2019 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 11/14/2019 ADRIAN CASTRO
Green Code Cleared 11/14/2019 DAWN MC NULTY
Roof/Waste drainage to street Cleared 11/14/2019 ADRIAN CASTRO
Sewer availability Cleared 11/14/2019 ADRIAN CASTRO
Certificate of Compliance Cleared 11/18/2019 MARC WOERSCHING
Frnt yard landscape/Water mgmt Cleared 11/21/2019 HERMINIGILDO AGUSTIN
ZI Cleared 11/21/2019 HERMINIGILDO AGUSTIN
Hydrant and Access approval Cleared 12/4/2019 GEORGE SUCHAND
Permit Cleared 12/4/2019 APEKSHYA BAJRACHARYA
Sewer availability Cleared 3/12/2020 JOHN LIN
ZI Cleared 4/7/2020 HERMINIGILDO AGUSTIN
Low Impact Development Cleared 5/19/2020 MITESH PATEL
Trees in Parkway Cleared 6/2/2020 JOHN KIM
Hold Cleared 7/20/2020 JASON SHEETS

Contact Information

Contractor Pnr Builders Inc; Lic. No.: 1028148-B 21226 VENTURA BLVD #250      WOODLAND HILLS, CA 91364

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/22/2020 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 7/31/2020 Partial Approval VINCENT HANLEY
PLUMBING-Rough 8/5/2020 Order to Comply Issued VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 8/7/2020 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 9/28/2020 Approved VINCENT HANLEY
BUILDING-Rough-Frame 10/14/2020 Partial Approval VINCENT HANLEY
ELECTRICAL-Rough 10/14/2020 Approved VINCENT HANLEY
Green Building Rough 10/14/2020 Approved VINCENT HANLEY
HVAC-Rough 10/14/2020 Approved VINCENT HANLEY
PLUMBING-Rough 10/14/2020 Approved VINCENT HANLEY
Verify Sprinkler Sign Off 10/14/2020 Not Ready for Inspection VINCENT HANLEY
Drywall Nailing 10/23/2020 Approved RONALD COWAN
Interior/Exterior Lathing 10/23/2020 Approved RONALD COWAN
Interior/Exterior Lathing 11/5/2020 Approved VINCENT HANLEY
Shower Pan 11/5/2020 Approved VINCENT HANLEY
Underground Mechanical 11/30/2020 Partial Approval VINCENT HANLEY
Underground Mechanical 12/11/2020 Approved VINCENT HANLEY
BUILDING-Rough-Frame 2/26/2021 Partial Approval VINCENT HANLEY
Final 2/26/2021 Corrections Issued VINCENT HANLEY
Footing/Foundation/Slab 2/26/2021 Approved VINCENT HANLEY
Green Building Final 2/26/2021 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 2/26/2021 SGSOV Not Ready VINCENT HANLEY
Service/Power Release 2/26/2021 Not Ready for Inspection VINCENT HANLEY
Smoke Detectors 2/26/2021 Approved VINCENT HANLEY
Verify Sprinkler Sign Off 2/26/2021 Not Ready for Inspection VINCENT HANLEY
BUILDING-Rough-Frame 3/4/2021 Approved VINCENT HANLEY
Final 3/4/2021 Corrections Issued VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 3/4/2021 SGSOV Approved VINCENT HANLEY
Service/Power Release 3/4/2021 Not Ready for Inspection VINCENT HANLEY
Verify Sprinkler Sign Off 3/4/2021 Approved VINCENT HANLEY
ELECTRICAL-Final 3/18/2021 Approved VINCENT HANLEY
Final 3/18/2021 OK to Issue CofO VINCENT HANLEY
HVAC-Final 3/18/2021 Approved VINCENT HANLEY
PLUMBING-Final 3/18/2021 Approved VINCENT HANLEY
Service/Power Release 3/18/2021 Approved VINCENT HANLEY