18633 W VANOWEN ST 91335
Certificate Information: 18633 W VANOWEN ST 91335
- Application / Permit
- 19010-20000-03497
- Plan Check / Job No.
- B19VN13192
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSE 30'X62'-6" TWO STORY SFD WITH 3 CAR ATTACHED GARAGE _ BUILDING SHALL BE FULLY SPRINKLER THROUGH OUT WITH NFPA 13D [SEE COMMENTS].
- Permit Issued
- Issued on 7/10/2020
- Issuing Office
- Current Status
- CofO Issued on 3/23/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/7/2019 | APPLICANT |
| Green Plans Picked Up | 8/28/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/5/2019 | DAWN MC NULTY |
| Corrections Issued | 9/23/2019 | DAWN MC NULTY |
| Quality Review Completed | 9/25/2019 | CHON CHIO KUO |
| Building Plans Picked Up | 9/26/2019 | APPLICANT |
| Plan Check Approved | 5/18/2020 | DAWN MC NULTY |
| Issued | 7/10/2020 | APPLICANT |
| CofO in Progress | 3/18/2021 | VINCENT HANLEY |
| Permit Finaled | 3/23/2021 | MICHAEL SMITH |
| CofO Issued | 3/23/2021 | MICHAEL SMITH |
| Permit Finaled | 3/23/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Trees in Parkway | Cleared | 11/13/2019 | ADRIAN SANCHEZ |
| Address approval | Cleared | 11/14/2019 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 11/14/2019 | ADRIAN CASTRO |
| Green Code | Cleared | 11/14/2019 | AARON COSTA |
| Roof/Waste drainage to street | Cleared | 11/14/2019 | ADRIAN CASTRO |
| Sewer availability | Cleared | 11/14/2019 | ADRIAN CASTRO |
| Frnt yard landscape/Water mgmt | Cleared | 11/21/2019 | HERMINIGILDO AGUSTIN |
| ZI | Cleared | 11/21/2019 | HERMINIGILDO AGUSTIN |
| Hydrant and Access approval | Cleared | 12/4/2019 | GEORGE SUCHAND |
| Permit | Cleared | 12/4/2019 | APEKSHYA BAJRACHARYA |
| Sewer availability | Cleared | 3/12/2020 | JOHN LIN |
| ZI | Cleared | 4/7/2020 | HERMINIGILDO AGUSTIN |
| Low Impact Development | Cleared | 5/19/2020 | MITESH PATEL |
Contact Information
| Contractor | Pnr Builders Inc; Lic. No.: 1028148-B | 21226 VENTURA BLVD #250 WOODLAND HILLS, CA 91364 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 7/14/2020 | Not Ready for Inspection | EMIL ALEXANDRIAN |
| PLUMBING-Rough | 7/15/2020 | Partial Approval | VINCENT HANLEY |
| Excavation/Setback/Form/Re-Bar | 7/22/2020 | Approved | VINCENT HANLEY |
| Special/Order Compliance | 8/6/2020 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 8/18/2020 | Partial Approval | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 9/28/2020 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 10/2/2020 | Not Ready for Inspection | VINCENT HANLEY |
| BUILDING-Rough-Frame | 10/14/2020 | Partial Approval | VINCENT HANLEY |
| ELECTRICAL-Rough | 10/14/2020 | Approved | VINCENT HANLEY |
| Green Building Rough | 10/14/2020 | Approved | VINCENT HANLEY |
| HVAC-Rough | 10/14/2020 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 10/14/2020 | Not Ready for Inspection | VINCENT HANLEY |
| PLUMBING-Rough | 10/14/2020 | Approved | VINCENT HANLEY |
| Verify Sprinkler Sign Off | 10/14/2020 | Not Ready for Inspection | VINCENT HANLEY |
| Drywall Nailing | 10/23/2020 | Approved | RONALD COWAN |
| Interior/Exterior Lathing | 10/23/2020 | Approved | RONALD COWAN |
| Shower Pan | 10/29/2020 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 11/5/2020 | Approved | VINCENT HANLEY |
| Shower Pan | 11/5/2020 | Approved | VINCENT HANLEY |
| Underground Mechanical | 12/11/2020 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 2/26/2021 | Partial Approval | VINCENT HANLEY |
| Final | 2/26/2021 | Corrections Issued | VINCENT HANLEY |
| Footing/Foundation/Slab | 2/26/2021 | Approved | VINCENT HANLEY |
| Green Building Final | 2/26/2021 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 2/26/2021 | SGSOV Not Ready | VINCENT HANLEY |
| Service/Power Release | 2/26/2021 | Not Ready for Inspection | VINCENT HANLEY |
| Smoke Detectors | 2/26/2021 | Approved | VINCENT HANLEY |
| Verify Sprinkler Sign Off | 2/26/2021 | Not Ready for Inspection | VINCENT HANLEY |
| BUILDING-Rough-Frame | 3/4/2021 | Approved | VINCENT HANLEY |
| Final | 3/4/2021 | Corrections Issued | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 3/4/2021 | SGSOV Approved | VINCENT HANLEY |
| Service/Power Release | 3/4/2021 | Not Ready for Inspection | VINCENT HANLEY |
| Verify Sprinkler Sign Off | 3/4/2021 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 3/18/2021 | Approved | VINCENT HANLEY |
| Final | 3/18/2021 | OK to Issue CofO | VINCENT HANLEY |
| HVAC-Final | 3/18/2021 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 3/18/2021 | Approved | VINCENT HANLEY |
| Service/Power Release | 3/18/2021 | Approved | VINCENT HANLEY |