1165 N SOMERA ROAD 90077

Certificate Information: 1165 N SOMERA ROAD 90077

Application / Permit
19010-20000-03452
Plan Check / Job No.
B19VN13052
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 2-STORY TYPE V-A SFD W/ TYPE I-A BASEMENT & GARAGE (NFPA-13D FIRE SPRINKLERS THROUGHOUT)
Permit Issued
Issued on 6/29/2021
Issuing Office
Valley
Current Status
CofO Issued on 1/17/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/5/2019 APPLICANT
Assigned to Plan Check Engineer 9/5/2019 NILOOFAR MEHRAIN
Green Plans Picked Up 9/12/2019 APPLICANT
Corrections Issued 9/19/2019 NILOOFAR MEHRAIN
Quality Review Completed 9/19/2019 GUANG MIN TUNG
Building Plans Picked Up 10/10/2019 APPLICANT
Applicant returned to address corrections 10/24/2019 NILOOFAR MEHRAIN
Applicant returned to address corrections 3/23/2020 NILOOFAR MEHRAIN
Applicant returned to address corrections 11/19/2020 NILOOFAR MEHRAIN
Applicant returned to address corrections 1/7/2021 NILOOFAR MEHRAIN
Applicant returned to address corrections 1/26/2021 NILOOFAR MEHRAIN
Applicant returned to address corrections 4/22/2021 NILOOFAR MEHRAIN
Applicant returned to address corrections 5/18/2021 NILOOFAR MEHRAIN
Applicant returned to address corrections 6/1/2021 NILOOFAR MEHRAIN
Plan Check Approved 6/3/2021 NILOOFAR MEHRAIN
Issued 6/29/2021 APPLICANT
CofO in Progress 1/14/2026 CHRISTOPHER WILSON
Permit Finaled 1/17/2026 RICHARD STEINBACH
CofO Issued 1/17/2026 RICHARD STEINBACH
Permit Finaled 1/17/2026 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 10/22/2019 ADRIAN CASTRO
BHO/Hillside ordinance Cleared 10/22/2019 ADRIAN CASTRO
BHO/Hillside ordinance Cleared 10/22/2019 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 10/22/2019 ADRIAN CASTRO
Permit Cleared 10/22/2019 ADRIAN CASTRO
Sewer availability Cleared 10/22/2019 ADRIAN CASTRO
BHO/Hillside ordinance Cleared 9/2/2020 RAYMOND MUGAMBWA
GPI Written Notices Cleared 1/7/2021 NILOOFAR MEHRAIN
Grading Pre-Inspection Cleared 1/7/2021 NILOOFAR MEHRAIN
Green Code Cleared 1/28/2021 MICHAEL AYERS
Low Impact Development Cleared 2/23/2021 MARTIN FRAGOSO
Miscellaneous Cleared 2/23/2021 MAHELET GEBEYHU
Roof/Waste drainage to street Cleared 2/23/2021 MAHELET GEBEYHU
Hydrant and Access approval Cleared 2/24/2021 JEREMY CARTER
Trees in Parkway Cleared 3/10/2021 ADRIAN SANCHEZ
Haul Route Cleared 5/18/2021 NILOOFAR MEHRAIN
Excavation more than 5-ft deep Cleared 6/14/2021 CALOSHA APPROVED

Contact Information

Contractor Owner-Builder       ,
Engineer Almalla,, Dean; Lic. No.: C58024 15053 VENTURA BLVD STE 205      SHERMAN OAKS, CA 91403
Engineer Jitechian,, Ara; Lic. No.: C54893 9433 VIA PATRICIA      BURBANK, CA 91504
Geologist Miller,, Steven Burl; Lic. No.: EG1303 23890 COPPERHILL DRIVE #111      VALENCIA, CA 91354

Inspector Information

RYAN SALAZAR, (310) 914-3862 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/23/2021 Partial Approval CHRISTOPHER WILSON
Piling/Pier/Caisson 5/20/2022 Not Ready for Inspection CHRISTOPHER WILSON
Deputy Reinf. Concrete 6/16/2022 Conditional Approval CHRISTOPHER WILSON
Pre-Inspection 7/25/2022 Approved CHRISTOPHER WILSON
Deputy Drilled-In Anchors 8/17/2022 Conditional Approval CHRISTOPHER WILSON
Deputy Drilled-In Anchors 9/19/2022 Conditional Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 9/23/2022 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 5/1/2023 Corrections Issued CHRISTOPHER WILSON
Piling/Pier/Caisson 5/1/2023 Not Ready for Inspection CHRISTOPHER WILSON
Deputy Reinf. Concrete 5/2/2023 Conditional Approval MICHAEL PELHAM
Excavation/Setback/Form/Re-Bar 5/2/2023 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 5/3/2023 Conditional Approval MICHAEL PELHAM
Deputy Reinf. Concrete 5/12/2023 Conditional Approval MICHAEL PELHAM
Piling/Pier/Caisson 5/15/2023 Partial Approval CHRISTOPHER WILSON
Underground Mechanical 8/3/2023 Corrections Issued CHRISTOPHER WILSON
PLUMBING-Rough 8/7/2023 Partial Approval CHRISTOPHER WILSON
Piling/Pier/Caisson 8/15/2023 Corrections Issued CHRISTOPHER WILSON
Deputy Reinf. Concrete 8/16/2023 Conditional Approval CHRISTOPHER WILSON
Piling/Pier/Caisson 8/16/2023 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 8/31/2023 Partial Approval CHRISTOPHER WILSON
Piling/Pier/Caisson 10/23/2023 Corrections Issued CHRISTOPHER WILSON
Deputy Drilled-In Anchors 10/26/2023 Conditional Approval CHRISTOPHER WILSON
Piling/Pier/Caisson 10/27/2023 Partial Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 11/9/2023 Partial Approval CHRISTOPHER WILSON
Structural Steel Frame 11/9/2023 Not Ready for Inspection CHRISTOPHER WILSON
Footing/Foundation/Slab 11/15/2023 Corrections Issued CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 11/16/2023 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 11/29/2023 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 12/1/2023 Conditional Approval MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 12/27/2023 Corrections Issued CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 12/28/2023 Partial Approval CHRISTOPHER WILSON
Deputy Drilled-In Anchors 1/4/2024 Conditional Approval MICHAEL PELHAM
Footing/Foundation/Slab 1/8/2024 Partial Approval CHRISTOPHER WILSON
Deputy Drilled-In Anchors 1/12/2024 Conditional Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 1/17/2024 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 1/17/2024 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 1/17/2024 Partial Approval CHRISTOPHER WILSON
Piling/Pier/Caisson 1/17/2024 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 1/19/2024 Conditional Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 1/23/2024 Corrections Issued STEPHANIE SWANSON
Deputy Other (see comments) 1/30/2024 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 1/30/2024 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 1/30/2024 Partial Approval CHRISTOPHER WILSON
Piling/Pier/Caisson 1/30/2024 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 3/8/2024 Partial Approval CHRISTOPHER WILSON
Deputy Drilled-In Anchors 5/31/2024 Conditional Approval MICHAEL PELHAM
ELECTRICAL-Rough 7/19/2024 Not Ready for Inspection SEAN HAUPT
HVAC-Rough 7/22/2024 Corrections Issued CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 7/23/2024 Partial Approval CHRISTOPHER WILSON
Wood Frame 7/23/2024 Not Ready for Inspection CHRISTOPHER WILSON
Deputy Drilled-In Anchors 8/1/2024 Conditional Approval CHRISTOPHER WILSON
Deputy Steel/Welding 8/13/2024 Conditional Approval CARLOS MATAMOROS
HVAC-Rough 8/19/2024 Approved MICHAEL PELHAM
Deputy Steel/Welding 8/20/2024 Conditional Approval MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 8/26/2024 Approved SEAN HAUPT
Structural Steel Frame 9/12/2024 Corrections Issued CARLOS MATAMOROS
ELECTRICAL-Rough 9/26/2024 Corrections Issued CHRISTOPHER WILSON
Gas Test 9/26/2024 Corrections Issued CHRISTOPHER WILSON
PLUMBING-Rough 10/1/2024 Corrections Issued CHRISTOPHER WILSON
Structural Steel Frame 10/1/2024 Approved CHRISTOPHER WILSON
ELECTRICAL-Rough 10/15/2024 Corrections Issued CHRISTOPHER WILSON
Gas Test 10/29/2024 Not Ready for Inspection CHRISTOPHER WILSON
ELECTRICAL-Rough 10/31/2024 Not Ready for Inspection CHRISTOPHER WILSON
ELECTRICAL-Rough 11/4/2024 Corrections Issued BOBBY KEY
Gas Test 11/4/2024 Partial Approval CHRISTOPHER WILSON
Special/Order Compliance 11/4/2024 Partial Inspection CHRISTOPHER WILSON
BUILDING-Rough-Frame 11/6/2024 Approved CHRISTOPHER WILSON
ELECTRICAL-Rough 11/6/2024 Partial Approval CHRISTOPHER WILSON
Green Building Rough 11/6/2024 Approved CHRISTOPHER WILSON
HVAC-Rough 11/6/2024 Approved CHRISTOPHER WILSON
Verify Sprinkler Sign Off 11/6/2024 Approved CHRISTOPHER WILSON
Insulation 11/20/2024 Approved CHRISTOPHER WILSON
Interior/Exterior Lathing 11/20/2024 Partial Approval CHRISTOPHER WILSON
Interior/Exterior Lathing 12/5/2024 Approved REGINA MENDEZ
Shower Pan 12/5/2024 Approved REGINA MENDEZ
Drywall Nailing 12/16/2024 Approved CHRISTOPHER WILSON
Interior/Exterior Lathing 12/16/2024 Approved CHRISTOPHER WILSON
Gas Test 4/7/2025 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 4/7/2025 Partial Approval CHRISTOPHER WILSON
Underground Mechanical 4/7/2025 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 5/21/2025 Partial Inspection CHRISTOPHER WILSON
HVAC-Rough 5/21/2025 Approved CHRISTOPHER WILSON
Service/Power Release 5/23/2025 Partial Inspection CHRISTOPHER WILSON
Service/Power Release 5/30/2025 Not Ready for Inspection SEAN HAUPT
Service/Power Release 6/3/2025 Corrections Issued CHRISTOPHER WILSON
Final 6/16/2025 Corrections Issued CHRISTOPHER WILSON
Service/Power Release 6/16/2025 Approved CHRISTOPHER WILSON
Masonry Wall/Backfill 7/29/2025 Not Ready for Inspection CHRISTOPHER WILSON
Special/Order Compliance 9/4/2025 Corrections Issued CHRISTOPHER WILSON
HVAC-Final 10/9/2025 Corrections Issued CARLOS MATAMOROS
HVAC-Final 10/14/2025 Corrections Issued SEAN HAUPT
ELECTRICAL-Final 10/15/2025 Approved DANIEL VERA
HVAC-Final 10/20/2025 Approved CARLOS MATAMOROS
PLUMBING-Final 10/21/2025 Approved CARLOS MATAMOROS
Final 12/26/2025 Corrections Issued CHRISTOPHER WILSON
Footing/Foundation/Slab 12/26/2025 Approved CHRISTOPHER WILSON
Green Building Final 12/26/2025 Approved CHRISTOPHER WILSON
Reinforced Concrete Frame 12/26/2025 Approved CHRISTOPHER WILSON
SGSOV-Seismic Gas S/O Valve 12/26/2025 SGSOV Not Ready CHRISTOPHER WILSON
Smoke Detectors 12/26/2025 Approved CHRISTOPHER WILSON
Final 1/13/2026 OK to Issue CofO CHRISTOPHER WILSON
SGSOV-Seismic Gas S/O Valve 1/13/2026 SGSOV Approved CHRISTOPHER WILSON