11618 N MANCHESTER WAY 91326
Certificate Information: 11618 N MANCHESTER WAY 91326
- Application / Permit
- 19010-20000-03448
- Plan Check / Job No.
- B19VN13044
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSE TWO STORY SFD WITH ATTACHED 3 CAR GARAGE_STANDARD PLAN # 643 _ PLAN 3CR (BUILDING SHALL BE FULLY SPRINKLER THROUGH OUT WITH NFPA 13D).
- Permit Issued
- Issued on 10/29/2019
- Issuing Office
- Valley
- Current Status
- CofO Corrected on 11/21/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/6/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 8/22/2019 | DAWN MC NULTY |
| Corrections Issued | 8/27/2019 | DAWN MC NULTY |
| Green Plans Picked Up | 8/27/2019 | APPLICANT |
| Quality Review Completed | 8/30/2019 | GUANG MIN TUNG |
| Building Plans Picked Up | 9/3/2019 | APPLICANT |
| Plan Check Approved | 10/29/2019 | DAWN MC NULTY |
| Issued | 10/29/2019 | LADBS |
| CofO in Progress | 8/1/2020 | SEAN WIRCH |
| CofO Issued-Status Void | 8/3/2020 | DONALD SUNSERI |
| Permit Finaled-Status Void | 8/3/2020 | DONALD SUNSERI |
| Re-Activate Permit | 11/21/2020 | DONALD SUNSERI |
| CofO Corrected | 11/21/2020 | DONALD SUNSERI |
| Permit Finaled | 11/21/2020 | DONALD SUNSERI |
Permit Application Clearance Information
| Low Impact Development | Cleared | 9/18/2019 | AMMAR ELTAWIL |
| Miscellaneous | Cleared | 10/8/2019 | NOAH MCCOY |
| Miscellaneous | Cleared | 10/8/2019 | NOAH MCCOY |
| Specific Plan | Cleared | 10/8/2019 | NOAH MCCOY |
| Tract Map conditions | Cleared | 10/8/2019 | NOAH MCCOY |
| ZA Case | Cleared | 10/8/2019 | NOAH MCCOY |
| ZA Case | Cleared | 10/8/2019 | NOAH MCCOY |
| Address approval | Cleared | 10/10/2019 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 10/10/2019 | LEE GUILBEAUX |
| Permit | Cleared | 10/10/2019 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 10/10/2019 | LEE GUILBEAUX |
| Sewer availability | Cleared | 10/10/2019 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 10/10/2019 | LEE GUILBEAUX |
| "T" removal | Cleared | 10/29/2019 | NOAH MCCOY |
| CPC | Cleared | 10/29/2019 | NOAH MCCOY |
| Green Code | Cleared | 10/29/2019 | MICHAEL AYERS |
| Hydrant and Access approval | Cleared | 10/29/2019 | GEORGE SUCHAND |
| Miscellaneous | Cleared | 10/29/2019 | NOAH MCCOY |
| Private street | Cleared | 10/29/2019 | NOAH MCCOY |
Contact Information
| Contractor | Shapell Homes Inc; Lic. No.: 1001034-B | 250 GIBRALTAR RD ATTN: GATES/LEGAL HORSHAM, PA 19044 |
| Engineer | Miller, Karen Lynn; Lic. No.: GE2257 | 5364 DORIS WY TORRANCE, CA 90505 |
| Engineer | Wong, Ramon Roman Ii; Lic. No.: S2345 | 1800 E. 16TH STREET SANTA ANA, CA 92701 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 11/20/2019 | Approved | BRUCE ROZAK |
| SWPPP-Const. Storm Water | 12/4/2019 | Completed | BRUCE ROZAK |
| Footing/Foundation/Slab | 1/9/2020 | Approved | DONALD SUNSERI |
| Deputy Reinf. Concrete | 1/10/2020 | Approved | DONALD SUNSERI |
| Sewer | 1/14/2020 | Approved | SEAN WIRCH |
| Floor/Roof Diaphrgm/Shear Wall | 1/22/2020 | Partial Approval | DONALD SUNSERI |
| Underground Mechanical | 1/28/2020 | Approved | DONALD SUNSERI |
| Floor/Roof Diaphrgm/Shear Wall | 2/10/2020 | Approved | SEAN WIRCH |
| ELECTRICAL-Rough | 2/18/2020 | Approved | SEAN WIRCH |
| HVAC-Rough | 2/18/2020 | Approved | SEAN WIRCH |
| PLUMBING-Rough | 2/18/2020 | Approved | SEAN WIRCH |
| Floor/Roof Diaphrgm/Shear Wall | 2/27/2020 | Partial Approval | DONALD SUNSERI |
| BUILDING-Rough-Frame | 2/28/2020 | Approved | DONALD SUNSERI |
| Floor/Roof Diaphrgm/Shear Wall | 2/28/2020 | Approved | DONALD SUNSERI |
| Green Building Rough | 2/28/2020 | Approved | DONALD SUNSERI |
| Verify Sprinkler Sign Off | 2/28/2020 | Approved | DONALD SUNSERI |
| Drywall Nailing | 3/6/2020 | Not Ready for Inspection | SEAN WIRCH |
| Interior/Exterior Lathing | 3/6/2020 | Approved | SEAN WIRCH |
| Interior/Exterior Lathing | 4/1/2020 | Approved | DONALD SUNSERI |
| Gas Test | 4/14/2020 | Approved | SEAN WIRCH |
| Service/Power Release | 4/16/2020 | Approved | SEAN WIRCH |
| SGSOV-Seismic Gas S/O Valve | 5/13/2020 | SGSOV Approved | SEAN WIRCH |
| ELECTRICAL-Final | 6/3/2020 | Approved | SEAN WIRCH |
| HVAC-Final | 6/15/2020 | Approved | SEAN WIRCH |
| PLUMBING-Final | 6/15/2020 | Approved | SEAN WIRCH |
| Drywall Nailing | 7/31/2020 | Approved | SEAN WIRCH |
| Final | 7/31/2020 | OK to Issue CofO | SEAN WIRCH |
| Green Building Final | 7/31/2020 | Approved | SEAN WIRCH |
| Smoke Detectors | 7/31/2020 | Approved | SEAN WIRCH |