7433 N BECKFORD AVE 91335

Certificate Information: 7433 N BECKFORD AVE 91335

Application / Permit
19010-20000-03282
Plan Check / Job No.
B19VN12787
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW (36' X 40'-0") IRREGULAR SHAPED ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 11/17/2021
Issuing Office
Current Status
CofO in Progress on 7/10/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/31/2019 APPLICANT
Assigned to Plan Check Engineer 8/15/2019 RAPHAEL ROSAS
Green Plans Picked Up 8/16/2019 APPLICANT
Corrections Issued 8/17/2019 RAPHAEL ROSAS
Quality Review Completed 8/20/2019 CHON CHIO KUO
Building Plans Picked Up 8/23/2019 APPLICANT
Plan Check Approved 1/13/2020 RAPHAEL ROSAS
Issued 11/17/2021 APPLICANT
CofO in Progress 7/10/2026 JUAN ALVARADO

Permit Application Clearance Information

Address approval Cleared 9/4/2019 ELENA LOPEZ
Eng Process Fee Ord 176,300 Cleared 9/4/2019 ELENA LOPEZ
Permit Cleared 9/4/2019 ELENA LOPEZ
Sewer availability Cleared 9/4/2019 ELENA LOPEZ
Green Code Cleared 10/8/2019 AARON COSTA
Hydrant and Access approval Cleared 1/7/2020 GILBERT URREA
Low Impact Development Cleared 1/7/2020 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 1/9/2020 EMIL KYUPELYAN

Contact Information

Contractor Owner-Builder       ,
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/14/2025 Approved TROY SANDERS
Floor/Roof Diaphrgm/Shear Wall 3/10/2025 Conditional Approval JUAN ALVARADO
PLUMBING-Rough 3/10/2025 Approved JUAN ALVARADO
Underground Mechanical 3/10/2025 Not Ready for Inspection JUAN ALVARADO
Floor/Roof Diaphrgm/Shear Wall 3/27/2025 Approved JUAN ALVARADO
Deputy Wood Construction 4/17/2025 Conditional Approval ROBERT GOLD
BUILDING-Rough-Frame 4/23/2025 Not Ready for Inspection JUAN ALVARADO
Deck 4/23/2025 Partial Inspection JUAN ALVARADO
Excavation/Setback/Form/Re-Bar 4/23/2025 Approved JUAN ALVARADO
Floor/Roof Diaphrgm/Shear Wall 4/23/2025 Approved JUAN ALVARADO
Green Building Rough 4/23/2025 Not Ready for Inspection JUAN ALVARADO
Masonry Wall/Backfill 4/23/2025 Partial Inspection JUAN ALVARADO
Structural Steel Frame 4/23/2025 Not Ready for Inspection JUAN ALVARADO
Verify Sprinkler Sign Off 4/23/2025 Not Ready for Inspection JUAN ALVARADO
Wood Frame 4/23/2025 Not Ready for Inspection JUAN ALVARADO
ELECTRICAL-Rough 9/25/2025 Approved JUAN ALVARADO
HVAC-Rough 9/25/2025 Approved JUAN ALVARADO
Interior/Exterior Lathing 9/25/2025 Approved JUAN ALVARADO
PLUMBING-Rough 9/25/2025 Approved JUAN ALVARADO
BUILDING-Rough-Frame 10/7/2025 Approved JUAN ALVARADO
Floor/Roof Diaphrgm/Shear Wall 10/7/2025 Approved JUAN ALVARADO
Green Building Rough 10/7/2025 Approved JUAN ALVARADO
Verify Sprinkler Sign Off 10/7/2025 Approved JUAN ALVARADO
Shower Pan 10/10/2025 Approved KRISTEN CAUSEY
Insulation 10/15/2025 Approved JUAN ALVARADO
Drywall Nailing 10/22/2025 Approved JUAN ALVARADO
Interior/Exterior Lathing 10/22/2025 Approved JUAN ALVARADO
Underground Mechanical 12/15/2025 Approved JUAN ALVARADO
ELECTRICAL-Final 6/5/2026 Corrections Issued JUAN ALVARADO
ELECTRICAL-Final 6/10/2026 Approved JUAN ALVARADO
Final 6/17/2026 Corrections Issued JUAN ALVARADO
Green Building Final 6/17/2026 Approved JUAN ALVARADO
SGSOV-Seismic Gas S/O Valve 6/17/2026 SGSOV Approved JUAN ALVARADO
Service/Power Release 6/17/2026 Not Ready for Inspection JUAN ALVARADO
Smoke Detectors 6/17/2026 Approved JUAN ALVARADO
Final 7/9/2026 OK to Issue CofO JUAN ALVARADO
HVAC-Final 7/9/2026 Approved JUAN ALVARADO
PLUMBING-Final 7/9/2026 Approved JUAN ALVARADO
Service/Power Release 7/9/2026 Approved JUAN ALVARADO