11426-11428 W OXNARD ST 91606

Certificate Information: 11426-11428 W OXNARD ST 91606

Application / Permit
19010-20000-03266
Plan Check / Job No.
B19VN12745
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
(N) 81" X 25'-6" 2-STORY DUPLEX WITH 2 UNITS ON 2ND-FLOOR & ATTACHED GARAGE ON 1ST-FLOOR. FIRE SPRINKLER REQUIRED NFPA-13D. TYPE-VA CONSTRUCTION. "COMPLY WITH DEPARTMENT ORDER EFFECTIVE DATE 09/04/2018."
Permit Issued
Issued on 8/25/2020
Issuing Office
Valley
Current Status
Issued on 8/25/2020
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/31/2019 APPLICANT
Assigned to Plan Check Engineer 8/15/2019 ABDUL CHEGENI
Corrections Issued 8/19/2019 ABDUL CHEGENI
Quality Review Completed 8/20/2019 STEVEN KIM
Building Plans Picked Up 8/22/2019 APPLICANT
Applicant returned to address corrections 10/1/2019 ABDUL CHEGENI
Applicant returned to address corrections 10/28/2019 ABDUL CHEGENI
Green Plans Picked Up 11/25/2019 APPLICANT
Applicant returned to address corrections 6/16/2020 SERGIO MUNIZ
Applicant returned to address corrections 7/10/2020 SERGIO MUNIZ
Plan Check Approved 8/3/2020 SERGIO MUNIZ
Issued 8/25/2020 APPLICANT

Permit Application Clearance Information

Address approval Cleared 12/2/2019 ADRIAN CASTRO
Address approval Cleared 12/2/2019 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 12/2/2019 ADRIAN CASTRO
Sewer availability Cleared 12/2/2019 ADRIAN CASTRO
"Q" conditions Cleared 12/11/2019 JASON CHAN
CPC Cleared 12/11/2019 JASON CHAN
Permit Cleared 4/14/2020 MARKOS PEREZ-BRAN
Green Code Cleared 5/14/2020 AARON COSTA
Low Impact Development Cleared 5/19/2020 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 5/28/2020 ADRIAN CASTRO
Housing rent stabilization Cleared 6/1/2020 MICHAEL SOTO
Hydrant and Access approval Cleared 6/17/2020 MATTHEW CRAIG
Highway dedication Cleared 6/24/2020 JOHN TRIANTAFYLLOS

Contact Information

Contractor Hye Art Glass; Lic. No.: 1006188-B 8101 ORION AVE UNIT 16      VAN NUYS, CA 91406
Engineer Yenjai,, Seree; Lic. No.: C73151 3249 SHADYLAWN DRIVE      DUARTE, CA 91010

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/3/2020 Not Ready for Inspection THOMAS FINNILA
BUILDING-Rough-Frame 9/21/2020 Partial Approval THOMAS FINNILA
Green Building Rough 9/21/2020 Not Ready for Inspection THOMAS FINNILA
Verify Sprinkler Sign Off 9/21/2020 Not Ready for Inspection THOMAS FINNILA
BUILDING-Rough-Frame 10/5/2020 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Rough 10/20/2020 Not Ready for Inspection THOMAS FINNILA
Underground Mechanical 10/20/2020 Corrections Issued THOMAS FINNILA
BUILDING-Rough-Frame 11/10/2020 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Rough 11/10/2020 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Rough 11/10/2020 Not Ready for Inspection THOMAS FINNILA
BUILDING-Rough-Frame 12/3/2020 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Rough 12/3/2020 Not Ready for Inspection THOMAS FINNILA
HVAC-Rough 12/3/2020 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Rough 12/3/2020 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Rough 12/8/2020 Not Ready for Inspection THOMAS FINNILA
HVAC-Rough 12/8/2020 Corrections Issued THOMAS FINNILA
PLUMBING-Rough 12/8/2020 Not Ready for Inspection THOMAS FINNILA
BUILDING-Rough-Frame 12/10/2020 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Rough 12/15/2020 Partial Approval BEAU COLLINS
PLUMBING-Rough 12/15/2020 Partial Approval BEAU COLLINS
Floor/Roof Diaphrgm/Shear Wall 12/18/2020 Partial Approval BEAU COLLINS
HVAC-Rough 12/18/2020 Partial Approval BEAU COLLINS
BUILDING-Rough-Frame 1/26/2021 Corrections Issued THOMAS FINNILA
Green Building Rough 1/26/2021 Not Ready for Inspection THOMAS FINNILA
Verify Sprinkler Sign Off 1/26/2021 Approved THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 2/2/2021 Approved DANIEL DREW
Interior/Exterior Lathing 3/22/2021 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Rough 3/26/2021 Corrections Issued THOMAS FINNILA
HVAC-Rough 3/26/2021 Partial Approval THOMAS FINNILA
PLUMBING-Rough 3/26/2021 Corrections Issued THOMAS FINNILA
BUILDING-Rough-Frame 4/5/2021 Not Ready for Inspection JOHN HAYES
Green Building Rough 4/5/2021 Not Ready for Inspection JOHN HAYES
Insulation 4/5/2021 Corrections Issued JOHN HAYES
Insulation 4/12/2021 Conditional Approval THOMAS FINNILA
BUILDING-Rough-Frame 4/22/2021 Not Ready for Inspection THOMAS FINNILA
Drywall Nailing 4/22/2021 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Rough 4/22/2021 Corrections Issued THOMAS FINNILA
Green Building Rough 4/22/2021 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Rough 4/22/2021 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Rough 5/3/2021 Corrections Issued THOMAS FINNILA
Interior/Exterior Lathing 5/19/2021 Partial Approval THOMAS FINNILA
Interior/Exterior Lathing 5/26/2021 Partial Approval THOMAS FINNILA
Shower Pan 3/30/2022 Corrections Issued DAVID MATSON
Shower Pan 4/5/2022 Corrections Issued THOMAS FINNILA
Shower Pan 4/12/2022 Not Ready for Inspection GREGG CUMMINGS
Shower Pan 4/15/2022 Approved THOMAS FINNILA
Deputy Wood Construction 6/8/2022 Conditional Approval THOMAS FINNILA
ELECTRICAL-Final 11/15/2022 Not Ready for Inspection JACK KARGODORIAN
HVAC-Final 11/15/2022 Not Ready for Inspection JACK KARGODORIAN
PLUMBING-Final 11/15/2022 Not Ready for Inspection JACK KARGODORIAN
Service/Power Release 11/15/2022 Corrections Issued JACK KARGODORIAN
ELECTRICAL-Final 12/30/2022 Not Ready for Inspection JACK KARGODORIAN
HVAC-Final 12/30/2022 Not Ready for Inspection JACK KARGODORIAN
PLUMBING-Final 12/30/2022 Not Ready for Inspection JACK KARGODORIAN
Service/Power Release 12/30/2022 Corrections Issued JACK KARGODORIAN
ELECTRICAL-Final 1/30/2023 Approved JACK KARGODORIAN
HVAC-Final 1/30/2023 Approved JACK KARGODORIAN
PLUMBING-Final 1/30/2023 Approved JACK KARGODORIAN
Service/Power Release 1/30/2023 Corrections Issued JACK KARGODORIAN
BUILDING-Rough-Frame 4/14/2023 Approved JACK KARGODORIAN
Drywall Nailing 4/14/2023 Approved JACK KARGODORIAN
Final 4/14/2023 Not Ready for Inspection JACK KARGODORIAN
Footing/Foundation/Slab 4/14/2023 Approved JACK KARGODORIAN
Green Building Final 4/14/2023 Approved JACK KARGODORIAN
Green Building Rough 4/14/2023 Approved JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 4/14/2023 SGSOV Not Required JACK KARGODORIAN
Service/Power Release 4/14/2023 Approved JACK KARGODORIAN
Smoke Detectors 4/14/2023 Approved JACK KARGODORIAN
Final 11/21/2023 Partial Inspection JOHN COLEMAN