10412-10414 N LEMONA AVE 91345

Certificate Information: 10412-10414 N LEMONA AVE 91345

Application / Permit
19010-20000-03245
Plan Check / Job No.
B19VN12630
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Add 19'-11" x 38'-11" second story Accessory Dwelling Unit per AB 494 & SB 229 to single family dwelling.
Permit Issued
Issued on 9/20/2019
Issuing Office
Valley
Current Status
CofO Issued on 6/19/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/30/2019 APPLICANT
Assigned to Plan Check Engineer 8/15/2019 ANGELICA DAVE
Green Plans Picked Up 8/15/2019 APPLICANT
Corrections Issued 8/20/2019 ANGELICA DAVE
Quality Review Completed 8/20/2019 CHON CHIO KUO
Building Plans Picked Up 8/21/2019 APPLICANT
Plan Check Approved 9/18/2019 ANGELICA MARTINEZ
Issued 9/20/2019 LADBS
CofO in Progress 5/27/2021 JENNIFER RABUCHIN
Permit Finaled 6/19/2021 MICHAEL SMITH
CofO Issued 6/19/2021 MICHAEL SMITH
Permit Finaled 6/19/2021 MICHAEL SMITH

Permit Application Clearance Information

Abandoned oil well Cleared 8/29/2019 GEORGE SUCHAND
Abandoned oil well approval Cleared 8/29/2019 GEORGE SUCHAND
Address approval Cleared 8/29/2019 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 9/10/2019 JAMES MORALEZ
Low Impact Development Cleared 9/10/2019 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 9/10/2019 JAMES MORALEZ
Sewer availability Cleared 9/10/2019 JAMES MORALEZ
Green Code Cleared 9/11/2019 DAVID MATSON

Contact Information

Contractor Owner-Builder       ,
Engineer Li,, Dacheng David; Lic. No.: C58075 3129 S HACIENDA BL STE 524      HACIENDA HEIGHTS, CA 91745

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/28/2019 Partial Approval JENNIFER RABUCHIN
Excavation/Setback/Form/Re-Bar 11/4/2019 Partial Approval JENNIFER RABUCHIN
Special/Order Compliance 11/6/2019 Partial Inspection JENNIFER RABUCHIN
BUILDING-Rough-Frame 11/18/2019 Partial Approval JENNIFER RABUCHIN
Green Building Rough 11/18/2019 Not Ready for Inspection JENNIFER RABUCHIN
BUILDING-Rough-Frame 12/24/2019 Partial Approval JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 12/24/2019 Partial Approval JENNIFER RABUCHIN
Green Building Rough 12/24/2019 Not Ready for Inspection JENNIFER RABUCHIN
BUILDING-Rough-Frame 2/4/2020 Corrections Issued JENNIFER RABUCHIN
BUILDING-Rough-Frame 3/2/2020 Corrections Issued JENNIFER RABUCHIN
Green Building Rough 3/2/2020 Not Ready for Inspection JENNIFER RABUCHIN
BUILDING-Rough-Frame 5/21/2020 Corrections Issued BEAU COLLINS
ELECTRICAL-Rough 5/21/2020 Not Ready for Inspection BEAU COLLINS
Green Building Rough 5/21/2020 Not Ready for Inspection BEAU COLLINS
PLUMBING-Rough 5/21/2020 Not Ready for Inspection BEAU COLLINS
BUILDING-Rough-Frame 6/16/2020 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 6/16/2020 Corrections Issued JENNIFER RABUCHIN
Gas Test 6/16/2020 Partial Approval JENNIFER RABUCHIN
HVAC-Rough 6/16/2020 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 6/16/2020 Corrections Issued JENNIFER RABUCHIN
HVAC-Rough 6/26/2020 Approved DANIEL DREW
Insulation 6/26/2020 Approved DANIEL DREW
Drywall Nailing 7/22/2020 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 7/22/2020 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 2/5/2021 Corrections Issued JENNIFER RABUCHIN
BUILDING-Rough-Frame 3/15/2021 Corrections Issued JENNIFER RABUCHIN
Final 3/15/2021 Corrections Issued JENNIFER RABUCHIN
Footing/Foundation/Slab 3/15/2021 Approved JENNIFER RABUCHIN
Gas Test 3/15/2021 Corrections Issued JENNIFER RABUCHIN
Green Building Final 3/15/2021 Corrections Issued JENNIFER RABUCHIN
Green Building Rough 3/15/2021 Approved JENNIFER RABUCHIN
HVAC-Final 3/15/2021 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 3/15/2021 SGSOV Not Ready JENNIFER RABUCHIN
Smoke Detectors 3/15/2021 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 5/19/2021 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 5/19/2021 Corrections Issued JENNIFER RABUCHIN
Final 5/19/2021 Corrections Issued JENNIFER RABUCHIN
Green Building Final 5/19/2021 Corrections Issued JENNIFER RABUCHIN
HVAC-Final 5/19/2021 Approved JENNIFER RABUCHIN
PLUMBING-Final 5/19/2021 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 5/19/2021 SGSOV Approved JENNIFER RABUCHIN
Special/Order Compliance 5/19/2021 Partial Inspection JENNIFER RABUCHIN
ELECTRICAL-Final 5/28/2021 Approved JENNIFER RABUCHIN
Final 5/28/2021 OK to Issue CofO JENNIFER RABUCHIN
Green Building Final 5/28/2021 Approved JENNIFER RABUCHIN