11050 N SWEETWATER CT 91311

Certificate Information: 11050 N SWEETWATER CT 91311

Application / Permit
19010-20000-03194
Plan Check / Job No.
B19VN12375
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSE (N) 2 STORY SFD W/ ATT GARAGE_ PER STD PLAN # 645_PLAN 7 (BUILDING SHALL BE FULLY SPRINKLER THROUGH OUT WITH NFPA 13D)
Permit Issued
Issued on 10/21/2019
Issuing Office
Valley
Current Status
CofO Issued on 6/29/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/29/2019 APPLICANT
Green Plans Picked Up 8/6/2019 APPLICANT
Assigned to Plan Check Engineer 8/15/2019 DAWN MC NULTY
Corrections Issued 8/19/2019 DAWN MC NULTY
Quality Review Completed 8/21/2019 CHON CHIO KUO
Building Plans Picked Up 8/27/2019 APPLICANT
Applicant returned to address corrections 10/17/2019 DAWN MC NULTY
Plan Check Approved 10/21/2019 DAWN MC NULTY
Issued 10/21/2019 LADBS
CofO in Progress 6/21/2021 SEAN WIRCH
CofO Issued 6/29/2021 MICHAEL SMITH
Permit Finaled 6/29/2021 MICHAEL SMITH

Permit Application Clearance Information

Low Impact Development Cleared 9/17/2019 AMMAR ELTAWIL
Address approval Cleared 9/18/2019 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 9/18/2019 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 9/18/2019 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 9/18/2019 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 9/18/2019 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 9/18/2019 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 9/18/2019 LEE GUILBEAUX
Flood clearance Cleared 9/18/2019 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 9/18/2019 LEE GUILBEAUX
Sewer availability Cleared 9/18/2019 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 9/18/2019 LEE GUILBEAUX
Public Works-Open Permits Cleared 9/18/2019 LEE GUILBEAUX
Hydrant and Access approval Cleared 9/25/2019 ROBERT DUFF
"Q" conditions Cleared 10/7/2019 NOAH MCCOY
CPC Cleared 10/7/2019 NOAH MCCOY
Miscellaneous Cleared 10/7/2019 NOAH MCCOY
Miscellaneous Cleared 10/7/2019 NOAH MCCOY
Miscellaneous Cleared 10/7/2019 NOAH MCCOY
Miscellaneous Cleared 10/7/2019 NOAH MCCOY
Private street Cleared 10/7/2019 NOAH MCCOY
Tract Map conditions Cleared 10/7/2019 NOAH MCCOY
ZA Case Cleared 10/7/2019 NOAH MCCOY
Green Code Cleared 10/16/2019 MICHAEL AYERS

Contact Information

Architect Gorrill, Ernest Bernard; Lic. No.: C13407 419 E BAY ST      COSTA MESA, CA 92627
Contractor Shapell Homes Inc; Lic. No.: 1001034-B 250 GIBRALTAR RD   ATTN: GATES/LEGAL    HORSHAM, PA 19044
Engineer Christian, Dale Alan; Lic. No.: S2705 1744 W KATELLA AVENUE SUITE 107      ORANGE, CA 92867
Engineer Waddell, Ian Robertson; Lic. No.: C41219 519 10TH ST      HUNTINGTON BEACH, CA 92648

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 9/15/2020 Partial Approval SEAN WIRCH
Footing/Foundation/Slab 9/29/2020 Approved SEAN WIRCH
Deputy Reinf. Concrete 10/1/2020 Approved SEAN WIRCH
Sewer 10/8/2020 Approved SEAN WIRCH
Sewer 10/22/2020 Not Ready for Inspection SEAN WIRCH
Floor/Roof Diaphrgm/Shear Wall 11/4/2020 Partial Approval SEAN WIRCH
Floor/Roof Diaphrgm/Shear Wall 11/25/2020 Partial Approval DONALD SUNSERI
ELECTRICAL-Rough 1/6/2021 Approved DONALD SUNSERI
Floor/Roof Diaphrgm/Shear Wall 1/6/2021 Not Ready for Inspection DONALD SUNSERI
HVAC-Rough 1/6/2021 Approved DONALD SUNSERI
PLUMBING-Rough 1/6/2021 Approved DONALD SUNSERI
Floor/Roof Diaphrgm/Shear Wall 1/8/2021 Partial Approval SEAN WIRCH
BUILDING-Rough-Frame 1/15/2021 Corrections Issued SEAN WIRCH
Green Building Rough 1/15/2021 Not Ready for Inspection SEAN WIRCH
MERV13>=Rough 1/15/2021 Not Ready for Inspection SEAN WIRCH
Verify Sprinkler Sign Off 1/15/2021 Not Ready for Inspection SEAN WIRCH
BUILDING-Rough-Frame 1/22/2021 Corrections Issued SEAN WIRCH
Green Building Rough 1/22/2021 Not Ready for Inspection SEAN WIRCH
MERV13>=Rough 1/22/2021 Not Ready for Inspection SEAN WIRCH
Underground Mechanical 1/22/2021 Approved SEAN WIRCH
Verify Sprinkler Sign Off 1/22/2021 Approved SEAN WIRCH
BUILDING-Rough-Frame 1/25/2021 Partial Approval SEAN WIRCH
Green Building Rough 1/25/2021 Approved SEAN WIRCH
MERV13>=Rough 1/25/2021 Approved SEAN WIRCH
Drywall Nailing 2/3/2021 Approved SEAN WIRCH
Interior/Exterior Lathing 2/3/2021 Partial Approval SEAN WIRCH
Interior/Exterior Lathing 3/11/2021 Partial Approval SEAN WIRCH
Gas Test 3/25/2021 Approved SEAN WIRCH
Service/Power Release 4/19/2021 Approved SEAN WIRCH
Gas Test 4/20/2021 Not Ready for Inspection SEAN WIRCH
Gas Test 5/3/2021 Approved JOSEPH SAGEN
SGSOV-Seismic Gas S/O Valve 5/3/2021 SGSOV Approved JOSEPH SAGEN
ELECTRICAL-Final 5/26/2021 Approved JOSEPH SAGEN
HVAC-Final 5/26/2021 Approved JOSEPH SAGEN
BUILDING-Rough-Frame 6/4/2021 Approved SEAN WIRCH
Final 6/4/2021 Not Ready for Inspection JOSEPH SAGEN
Green Building Final 6/4/2021 Approved JOSEPH SAGEN
MERV13>=Final 6/4/2021 Approved JOSEPH SAGEN
PLUMBING-Final 6/4/2021 Approved JOSEPH SAGEN
Smoke Detectors 6/4/2021 Approved JOSEPH SAGEN
Final 6/11/2021 Not Ready for Inspection JOSEPH SAGEN
Final 6/18/2021 OK to Issue CofO SEAN WIRCH
Green Building Final 6/18/2021 Approved SEAN WIRCH
Smoke Detectors 6/18/2021 Approved SEAN WIRCH