19750 W ENADIA WAY 91306

Certificate Information: 19750 W ENADIA WAY 91306

Application / Permit
19010-20000-03166
Plan Check / Job No.
B19VN12292
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 34'2"X54'4" ACCESSORY DWELLING UNIT PER AB 494 & SB 229
Permit Issued
Issued on 3/4/2020
Issuing Office
Valley
Current Status
CofO Issued on 2/12/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/24/2019 APPLICANT
Green Plans Picked Up 8/6/2019 APPLICANT
Assigned to Plan Check Engineer 8/8/2019 MARVEL DELACRUZ
Corrections Issued 8/10/2019 MARVEL DELACRUZ
Quality Review Completed 8/19/2019 OMID HEDAYAT
Building Plans Picked Up 8/19/2019 APPLICANT
Applicant returned to address corrections 10/10/2019 MARVEL DELACRUZ
Applicant returned to address corrections 12/27/2019 MARVEL DELACRUZ
Applicant returned to address corrections 1/22/2020 MARVEL DELACRUZ
Applicant returned to address corrections 3/2/2020 MARVEL DELACRUZ
Plan Check Approved 3/3/2020 MARVEL DELACRUZ
Issued 3/4/2020 LADBS
CofO in Progress 2/10/2021 HENRY KIM
Permit Finaled 2/12/2021 JOHN JANSON
CofO Issued 2/12/2021 JOHN JANSON
Permit Finaled 2/12/2021 JOHN JANSON

Permit Application Clearance Information

Green Code Cleared 8/14/2019 AARON COSTA
Construction near power lines Cleared 11/21/2019 RIDWAN HARDY
ZI Cleared 12/10/2019 STEVEN WECHSLER
Address approval Cleared 12/27/2019 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 12/27/2019 GUILLERMO PETRA
Sewer availability Cleared 12/27/2019 GUILLERMO PETRA
Low Impact Development Cleared 1/7/2020 AMMAR ELTAWIL
Hydrant and Access approval Cleared 1/10/2020 GEORGE SUCHAND
Roof/Waste drainage to street Cleared 1/16/2020 GUILLERMO PETRA

Contact Information

Contractor Owner-Builder       ,
Engineer Yenjai,, Seree; Lic. No.: C73151 3249 SHADYLAWN DRIVE      DUARTE, CA 91010

Inspector Information

ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/15/2020 Approved HENRY KIM
PLUMBING-Rough 4/21/2020 Partial Approval HENRY KIM
Footing/Foundation/Slab 4/23/2020 Approved HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 6/4/2020 Approved HENRY KIM
Sewer 6/11/2020 Partial Approval HENRY KIM
PLUMBING-Rough 6/19/2020 Approved HENRY KIM
Sewer 6/19/2020 Approved HENRY KIM
Underground Mechanical 6/19/2020 Partial Approval HENRY KIM
ELECTRICAL-Rough 6/22/2020 Approved HENRY KIM
HVAC-Rough 6/24/2020 Approved HENRY KIM
BUILDING-Rough-Frame 6/26/2020 Approved HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 6/26/2020 Approved HENRY KIM
Green Building Rough 6/26/2020 Approved HENRY KIM
Verify Sprinkler Sign Off 6/26/2020 Approved HENRY KIM
Gas Test 7/7/2020 Partial Approval HENRY KIM
Insulation 7/7/2020 Approved HENRY KIM
Drywall Nailing 7/21/2020 Approved HENRY KIM
Interior/Exterior Lathing 7/21/2020 Approved HENRY KIM
Underground Mechanical 7/21/2020 Corrections Issued HENRY KIM
Interior/Exterior Lathing 8/14/2020 Approved HENRY KIM
Shower Pan 8/14/2020 Corrections Issued HENRY KIM
Shower Pan 8/18/2020 Approved HENRY KIM
ELECTRICAL-Final 11/25/2020 Corrections Issued HENRY KIM
Final 11/25/2020 Corrections Issued HENRY KIM
Gas Test 11/25/2020 Approved HENRY KIM
Green Building Final 11/25/2020 Approved HENRY KIM
HVAC-Final 11/25/2020 Corrections Issued HENRY KIM
PLUMBING-Final 11/25/2020 Corrections Issued HENRY KIM
SGSOV-Seismic Gas S/O Valve 11/25/2020 SGSOV Approved HENRY KIM
Smoke Detectors 11/25/2020 Corrections Issued HENRY KIM
ELECTRICAL-Final 12/18/2020 Corrections Issued HENRY KIM
Final 12/18/2020 Corrections Issued HENRY KIM
HVAC-Final 12/18/2020 Corrections Issued HENRY KIM
PLUMBING-Final 12/18/2020 Approved HENRY KIM
Smoke Detectors 12/18/2020 Approved HENRY KIM
ELECTRICAL-Final 2/5/2021 Corrections Issued HENRY KIM
Final 2/5/2021 Corrections Issued HENRY KIM
HVAC-Final 2/5/2021 Corrections Issued HENRY KIM
ELECTRICAL-Final 2/10/2021 Approved HENRY KIM
Final 2/10/2021 OK to Issue CofO HENRY KIM
HVAC-Final 2/10/2021 Approved HENRY KIM