5736 S RUTHELEN ST 90062

Certificate Information: 5736 S RUTHELEN ST 90062

Application / Permit
19010-20000-03141
Plan Check / Job No.
B19VN12209
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 27' X 32' DETACHED ACCESSORY DWELLING UNIT AS PER AB 494 AND SB 229 , ALL WORK PER WFPP
Permit Issued
Issued on 1/14/2020
Issuing Office
West Los Angeles
Current Status
CofO Issued on 10/13/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/23/2019 APPLICANT
Green Plans Picked Up 8/1/2019 APPLICANT
Assigned to Plan Check Engineer 8/8/2019 RARES BODEA
Corrections Issued 8/11/2019 RARES BODEA
Quality Review Completed 8/19/2019 OMID HEDAYAT
Building Plans Picked Up 8/21/2019 APPLICANT
Plan Check Approved 12/24/2019 RARES BODEA
Issued 1/14/2020 LADBS
CofO in Progress 10/7/2021 HORACE FULTZ
Permit Finaled 10/13/2021 DEROLD HAUFF
CofO Issued 10/13/2021 DEROLD HAUFF
Permit Finaled 10/13/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 11/1/2019 JOHN LIN
Eng Process Fee Ord 176,300 Cleared 11/1/2019 JOHN LIN
Sewer availability Cleared 11/1/2019 JOHN LIN
Hydrant and Access approval Cleared 12/6/2019 GEORGE SUCHAND
Green Code Cleared 12/12/2019 DAVID MATSON
Low Impact Development Cleared 12/17/2019 ORVAL HERNANDEZ-MARCIAL
Roof/Waste drainage to street Cleared 12/17/2019 EMIL KYUPELYAN

Contact Information

Contractor Ortiz Albanes Pablo S; Lic. No.: 1044042-B 714 1/2 WEST 46TH ST      LOS ANGELES, CA 90037

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/28/2020 Not Ready for Inspection ROBERT MCDOWELL
Underground Mechanical 2/28/2020 Approved ROBERT MCDOWELL
Excavation/Setback/Form/Re-Bar 3/9/2020 Approved ROBERT MCDOWELL
Footing/Foundation/Slab 3/9/2020 Approved ROBERT MCDOWELL
BUILDING-Rough-Frame 6/9/2020 Conditional Approval ROBERT MCDOWELL
ELECTRICAL-Rough 6/9/2020 Approved ROBERT MCDOWELL
Floor/Roof Diaphrgm/Shear Wall 6/9/2020 Approved ROBERT MCDOWELL
Green Building Rough 6/9/2020 Not Ready for Inspection ROBERT MCDOWELL
HVAC-Rough 6/9/2020 Approved ROBERT MCDOWELL
PLUMBING-Rough 6/9/2020 Approved ROBERT MCDOWELL
Verify Sprinkler Sign Off 6/9/2020 Not Ready for Inspection ROBERT MCDOWELL
Green Building Rough 6/19/2020 Approved SABAS ALONSO
Insulation 6/19/2020 Partial Approval SABAS ALONSO
Interior/Exterior Lathing 6/19/2020 Partial Approval SABAS ALONSO
BUILDING-Rough-Frame 6/29/2020 Conditional Approval SABAS ALONSO
Drywall Nailing 6/29/2020 Approved SABAS ALONSO
Insulation 6/29/2020 Approved SABAS ALONSO
Interior/Exterior Lathing 7/30/2020 Approved SABAS ALONSO
BUILDING-Rough-Frame 10/19/2020 Approved ROBERT MCDOWELL
ELECTRICAL-Final 10/19/2020 Approved ROBERT MCDOWELL
Final 10/19/2020 Corrections Issued ROBERT MCDOWELL
Green Building Final 10/19/2020 Approved ROBERT MCDOWELL
HVAC-Final 10/19/2020 Approved ROBERT MCDOWELL
PLUMBING-Final 10/19/2020 Approved ROBERT MCDOWELL
SGSOV-Seismic Gas S/O Valve 10/19/2020 SGSOV Approved ROBERT MCDOWELL
Service/Power Release 10/19/2020 Approved ROBERT MCDOWELL
Smoke Detectors 10/19/2020 Approved ROBERT MCDOWELL
Verify Sprinkler Sign Off 10/19/2020 Approved ROBERT MCDOWELL
Final 3/10/2021 Corrections Issued ROBERT MCDOWELL
Pre-Inspection 9/3/2021 Corrections Issued JESUS PINEDA
Special/Order Compliance 9/14/2021 Partial Inspection JESUS PINEDA
Final 9/21/2021 Conditional Approval SABAS ALONSO