22819 W LEONORA DR 91367
Certificate Information: 22819 W LEONORA DR 91367
- Application / Permit
- 19010-20000-03108
- Plan Check / Job No.
- B19VN12083
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Recreation Room
- Work Description
- NEW (37'-2" x 19'-2") DETACHED REC. ROOM WITH A HALF BATHROOM PER ENGINEER
- Permit Issued
- Issued on 8/8/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/12/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/22/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 7/22/2019 | PINANK PATEL |
| Corrections Issued | 7/22/2019 | PINANK PATEL |
| Plan Check Approved | 8/8/2019 | JEROME MAGAT PALMA |
| Issued | 8/8/2019 | LADBS |
| CofO in Progress | 2/12/2020 | DONALD SUNSERI |
| Permit Finaled | 2/12/2020 | DONALD SUNSERI |
| CofO Issued | 2/12/2020 | DONALD SUNSERI |
| Permit Finaled | 2/12/2020 | DONALD SUNSERI |
Permit Application Clearance Information
| Low Impact Development | Cleared | 7/31/2019 | MITESH PATEL |
| Eng Process Fee Ord 176,300 | Cleared | 8/5/2019 | LEE GUILBEAUX |
| GPI Written Notices | Cleared | 8/5/2019 | PINANK PATEL |
| Grading Pre-Inspection | Cleared | 8/5/2019 | PINANK PATEL |
| Hydrant and Access approval | Cleared | 8/5/2019 | GEORGE SUCHAND |
| Roof/Waste drainage to street | Cleared | 8/5/2019 | MARKOS PEREZ-BRAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Basma,, Ali J; Lic. No.: C53080 | 21500 WYANDOTTE ST 106 CANOGA PARK, CA 91303 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/13/2019 | Not Ready for Inspection | RYAN MCGILL |
| Footing/Foundation/Slab | 9/27/2019 | Approved | RYAN MCGILL |
| PLUMBING-Rough | 9/27/2019 | Approved | RYAN MCGILL |
| Sewer | 9/27/2019 | Approved | RYAN MCGILL |
| Underground Mechanical | 9/27/2019 | Approved | RYAN MCGILL |
| ELECTRICAL-Rough | 10/4/2019 | Approved | RYAN MCGILL |
| Floor/Roof Diaphrgm/Shear Wall | 10/4/2019 | Partial Approval | RYAN MCGILL |
| Insulation | 10/4/2019 | Partial Approval | RYAN MCGILL |
| Pre-Inspection | 10/18/2019 | Not Ready for Inspection | JOHN KIDWELL |
| BUILDING-Rough-Frame | 10/31/2019 | Not Ready for Inspection | JOHN KIDWELL |
| Green Building Rough | 10/31/2019 | Not Ready for Inspection | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 10/31/2019 | SGSOV Not Ready | DONALD SUNSERI |
| Verify Sprinkler Sign Off | 10/31/2019 | Not Ready for Inspection | JOHN KIDWELL |
| Pre-Inspection | 11/5/2019 | Approved | DONALD SUNSERI |
| Special/Order Compliance | 11/5/2019 | Partial Inspection | MICHAEL SMITH |
| Special/Order Compliance | 11/13/2019 | Corrections Issued | JOHN KIDWELL |
| BUILDING-Rough-Frame | 2/4/2020 | Approved | DONALD SUNSERI |
| ELECTRICAL-Rough | 2/4/2020 | Approved | DONALD SUNSERI |
| Green Building Rough | 2/4/2020 | Approved | DONALD SUNSERI |
| Special/Order Compliance | 2/4/2020 | Partial Inspection | MICHAEL SMITH |
| ELECTRICAL-Final | 2/11/2020 | Approved | DONALD SUNSERI |
| Final | 2/11/2020 | OK to Issue CofO | DONALD SUNSERI |
| Green Building Final | 2/11/2020 | Approved | DONALD SUNSERI |
| PLUMBING-Final | 2/11/2020 | Approved | DONALD SUNSERI |
| SGSOV-Seismic Gas S/O Valve | 2/11/2020 | SGSOV Approved | DONALD SUNSERI |
| Special/Order Compliance | 2/11/2020 | Partial Inspection | MICHAEL SMITH |