22819 W LEONORA DR 91367

Certificate Information: 22819 W LEONORA DR 91367

Application / Permit
19010-20000-03108
Plan Check / Job No.
B19VN12083
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
NEW (37'-2" x 19'-2") DETACHED REC. ROOM WITH A HALF BATHROOM PER ENGINEER
Permit Issued
Issued on 8/8/2019
Issuing Office
Valley
Current Status
CofO Issued on 2/12/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/22/2019 APPLICANT
Assigned to Plan Check Engineer 7/22/2019 PINANK PATEL
Corrections Issued 7/22/2019 PINANK PATEL
Plan Check Approved 8/8/2019 JEROME MAGAT PALMA
Issued 8/8/2019 LADBS
CofO in Progress 2/12/2020 DONALD SUNSERI
Permit Finaled 2/12/2020 DONALD SUNSERI
CofO Issued 2/12/2020 DONALD SUNSERI
Permit Finaled 2/12/2020 DONALD SUNSERI

Permit Application Clearance Information

Low Impact Development Cleared 7/31/2019 MITESH PATEL
Eng Process Fee Ord 176,300 Cleared 8/5/2019 LEE GUILBEAUX
GPI Written Notices Cleared 8/5/2019 PINANK PATEL
Grading Pre-Inspection Cleared 8/5/2019 PINANK PATEL
Hydrant and Access approval Cleared 8/5/2019 GEORGE SUCHAND
Roof/Waste drainage to street Cleared 8/5/2019 MARKOS PEREZ-BRAN

Contact Information

Contractor Owner-Builder       ,
Engineer Basma,, Ali J; Lic. No.: C53080 21500 WYANDOTTE ST 106      CANOGA PARK, CA 91303

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/13/2019 Not Ready for Inspection RYAN MCGILL
Footing/Foundation/Slab 9/27/2019 Approved RYAN MCGILL
PLUMBING-Rough 9/27/2019 Approved RYAN MCGILL
Sewer 9/27/2019 Approved RYAN MCGILL
Underground Mechanical 9/27/2019 Approved RYAN MCGILL
ELECTRICAL-Rough 10/4/2019 Approved RYAN MCGILL
Floor/Roof Diaphrgm/Shear Wall 10/4/2019 Partial Approval RYAN MCGILL
Insulation 10/4/2019 Partial Approval RYAN MCGILL
Pre-Inspection 10/18/2019 Not Ready for Inspection JOHN KIDWELL
BUILDING-Rough-Frame 10/31/2019 Not Ready for Inspection JOHN KIDWELL
Green Building Rough 10/31/2019 Not Ready for Inspection JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 10/31/2019 SGSOV Not Ready DONALD SUNSERI
Verify Sprinkler Sign Off 10/31/2019 Not Ready for Inspection JOHN KIDWELL
Pre-Inspection 11/5/2019 Approved DONALD SUNSERI
Special/Order Compliance 11/5/2019 Partial Inspection MICHAEL SMITH
Special/Order Compliance 11/13/2019 Corrections Issued JOHN KIDWELL
BUILDING-Rough-Frame 2/4/2020 Approved DONALD SUNSERI
ELECTRICAL-Rough 2/4/2020 Approved DONALD SUNSERI
Green Building Rough 2/4/2020 Approved DONALD SUNSERI
Special/Order Compliance 2/4/2020 Partial Inspection MICHAEL SMITH
ELECTRICAL-Final 2/11/2020 Approved DONALD SUNSERI
Final 2/11/2020 OK to Issue CofO DONALD SUNSERI
Green Building Final 2/11/2020 Approved DONALD SUNSERI
PLUMBING-Final 2/11/2020 Approved DONALD SUNSERI
SGSOV-Seismic Gas S/O Valve 2/11/2020 SGSOV Approved DONALD SUNSERI
Special/Order Compliance 2/11/2020 Partial Inspection MICHAEL SMITH