16706 W MAGNOLIA BLVD 91436
Certificate Information: 16706 W MAGNOLIA BLVD 91436
- Application / Permit
- 19010-20000-03091
- Plan Check / Job No.
- B19VN12016
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 43' X 79' SINGLE FAMILY DWELLING WITH ATTACHED GARAGE. NFPA - 13D FIRE SPRINKLER THRU-OUT.
- Permit Issued
- Issued on 5/28/2020
- Issuing Office
- Current Status
- CofO Issued on 8/3/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/19/2019 | APPLICANT |
| Green Plans Picked Up | 7/29/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 8/8/2019 | PINANK PATEL |
| Corrections Issued | 9/9/2019 | PINANK PATEL |
| Quality Review Completed | 9/10/2019 | OMID HEDAYAT |
| Building Plans Picked Up | 9/17/2019 | APPLICANT |
| Plan Check Approved | 5/21/2020 | PINANK PATEL |
| Issued | 5/28/2020 | APPLICANT |
| CofO in Progress | 7/29/2022 | VINCENT HANLEY |
| Permit Finaled | 8/3/2022 | JOHN JANSON |
| CofO Issued | 8/3/2022 | JOHN JANSON |
| Permit Finaled | 8/3/2022 | JOHN JANSON |
Permit Application Clearance Information
| Hold | Cleared | 9/6/2019 | CYNTHIA RYAN |
| Address approval | Cleared | 4/10/2020 | JOHN LIN |
| Eng Process Fee Ord 176,300 | Cleared | 4/10/2020 | JOHN TRIANTAFYLLOS |
| Permit | Cleared | 4/10/2020 | JOHN LIN |
| Sewer availability | Cleared | 4/10/2020 | JOHN TRIANTAFYLLOS |
| Hydrant and Access approval | Cleared | 4/16/2020 | GEORGE SUCHAND |
| Low Impact Development | Cleared | 4/28/2020 | MARTIN FRAGOSO |
| Green Code | Cleared | 5/6/2020 | AARON COSTA |
| Roof/Waste drainage to street | Cleared | 5/14/2020 | LEE GUILBEAUX |
Contact Information
| Architect | Schneider,, Brent T; Lic. No.: C21821 | 2282 TOWNSGATE ROAD SUITE 3 WESTLAKE VILLAGE, CA 91361 |
| Contractor | D & A Home Renovations; Lic. No.: 808672-B | 5021 ESCALON VIEW PARK, CA 90043 |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/26/2020 | Not Ready for Inspection | RONALD COWAN |
| Underground Mechanical | 10/20/2020 | Corrections Issued | RONALD COWAN |
| Underground Mechanical | 10/23/2020 | Partial Approval | RONALD COWAN |
| Footing/Foundation/Slab | 11/6/2020 | Partial Approval | RONALD COWAN |
| Deputy Reinf. Concrete | 11/9/2020 | Approved | RONALD COWAN |
| Footing/Foundation/Slab | 11/18/2020 | Conditional Approval | RONALD COWAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/2/2020 | Partial Approval | RONALD COWAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/14/2020 | Not Ready for Inspection | RONALD COWAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/16/2020 | Corrections Issued | RONALD COWAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/25/2021 | Not Ready for Inspection | DAVID SCANTLIN |
| Deputy Wood Construction | 1/28/2021 | Approved | RONALD COWAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/3/2021 | Approved | RONALD COWAN |
| Interior/Exterior Lathing | 2/23/2021 | Partial Approval | RONALD COWAN |
| ELECTRICAL-Rough | 4/15/2021 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 4/15/2021 | Approved | VINCENT HANLEY |
| Rough-Elec/Plmb/HVAC | 4/15/2021 | Off-Hour Fees Due | |
| Sewer | 4/15/2021 | Approved | VINCENT HANLEY |
| HVAC-Rough | 4/22/2021 | Approved | RONALD COWAN |
| BUILDING-Rough-Frame | 5/3/2021 | Approved | VINCENT HANLEY |
| Green Building Rough | 5/3/2021 | Approved | VINCENT HANLEY |
| MERV13>=Rough | 5/3/2021 | Approved | VINCENT HANLEY |
| Verify Sprinkler Sign Off | 5/3/2021 | Approved | VINCENT HANLEY |
| Insulation | 5/11/2021 | Approved | VINCENT HANLEY |
| Drywall Nailing | 5/20/2021 | Approved | RONALD COWAN |
| Shower Pan | 7/27/2021 | Approved | RYAN SALAZAR |
| Final | 7/26/2022 | Not Ready for Inspection | VINCENT HANLEY |
| Footing/Foundation/Slab | 7/26/2022 | Approved | VINCENT HANLEY |
| Green Building Final | 7/26/2022 | Approved | VINCENT HANLEY |
| MERV13>=Final | 7/26/2022 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 7/26/2022 | SGSOV Approved | VINCENT HANLEY |
| Service/Power Release | 7/26/2022 | Not Ready for Inspection | VINCENT HANLEY |
| Smoke Detectors | 7/26/2022 | Approved | VINCENT HANLEY |
| Final | 7/29/2022 | OK to Issue CofO | VINCENT HANLEY |
| Service/Power Release | 7/29/2022 | Approved | VINCENT HANLEY |