3765 N MOUND VIEW AVE 91604

Certificate Information: 3765 N MOUND VIEW AVE 91604

Application / Permit
19010-20000-03028
Plan Check / Job No.
B19VN11720
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW (67'-2"x 34'-0") TWO STORY SINGLE FAMILY DWELLING WITH BASEMENT AND ATTACHED 2-CAR GARAGE. WORK PER ENGINEER.
Permit Issued
Issued on 1/8/2020
Issuing Office
Valley
Current Status
CofO Issued on 6/12/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/16/2019 APPLICANT
Assigned to Plan Check Engineer 8/1/2019 TROY DEGUZMAN
Corrections Issued 8/6/2019 TROY DEGUZMAN
Quality Review Completed 8/9/2019 CHON CHIO KUO
Building Plans Picked Up 8/12/2019 APPLICANT
Green Plans Picked Up 8/12/2019 APPLICANT
Applicant returned to address corrections 9/26/2019 TROY DEGUZMAN
Plan Check Approved 11/4/2019 TROY DEGUZMAN
Issued 1/8/2020 LADBS
CofO in Progress 5/21/2021 ARAM AVEDISIAN
CofO Issued 6/12/2021 MICHAEL SMITH
Permit Finaled 6/12/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 8/23/2019 APEKSHYA BAJRACHARYA
Eng Process Fee Ord 176,300 Cleared 8/23/2019 APEKSHYA BAJRACHARYA
Sewer availability Cleared 8/23/2019 APEKSHYA BAJRACHARYA
Low Impact Development Cleared 8/27/2019 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 8/27/2019 JEANIE LAM
CPC Cleared 9/10/2019 RINA LARA
CPC Cleared 9/10/2019 RINA LARA
Green Code Cleared 9/12/2019 TROY DEGUZMAN
GPI Written Notices Cleared 9/26/2019 TROY DEGUZMAN
Grading Pre-Inspection Cleared 9/26/2019 TROY DEGUZMAN
Hydrant and Access approval Cleared 11/4/2019 OSCAR SALGADO JR

Contact Information

Contractor Owner-Builder       ,
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/14/2020 Partial Approval ARAM AVEDISIAN
Footing/Foundation/Slab 2/25/2020 Partial Approval ARAM AVEDISIAN
Footing/Foundation/Slab 3/4/2020 Partial Approval ARAM AVEDISIAN
Underground Mechanical 4/2/2020 Partial Approval ARAM AVEDISIAN
Excavation/Setback/Form/Re-Bar 4/24/2020 Partial Approval RAYMOND KEHOE
BUILDING-Rough-Frame 5/13/2020 Partial Inspection THOMAS FINNILA
Drywall Nailing 5/13/2020 Not Ready for Inspection THOMAS FINNILA
Green Building Rough 5/13/2020 Not Ready for Inspection THOMAS FINNILA
Verify Sprinkler Sign Off 5/13/2020 Not Ready for Inspection THOMAS FINNILA
Wood Frame 5/13/2020 Not Ready for Inspection THOMAS FINNILA
Footing/Foundation/Slab 5/28/2020 Not Ready for Inspection ARAM AVEDISIAN
Deputy Reinf. Concrete 6/3/2020 Conditional Approval ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 7/2/2020 Conditional Approval ARAM AVEDISIAN
HVAC-Rough 8/5/2020 Approved DANIEL DREW
BUILDING-Rough-Frame 8/11/2020 Corrections Issued ARAM AVEDISIAN
ELECTRICAL-Rough 8/11/2020 Corrections Issued ARAM AVEDISIAN
Green Building Rough 8/11/2020 Not Ready for Inspection ARAM AVEDISIAN
PLUMBING-Rough 8/11/2020 Corrections Issued ARAM AVEDISIAN
Verify Sprinkler Sign Off 8/11/2020 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 8/17/2020 Approved ARAM AVEDISIAN
ELECTRICAL-Rough 8/17/2020 Approved ARAM AVEDISIAN
Green Building Rough 8/17/2020 Approved ARAM AVEDISIAN
PLUMBING-Rough 8/17/2020 Approved ARAM AVEDISIAN
Insulation 8/26/2020 Conditional Approval ARAM AVEDISIAN
Drywall Nailing 9/4/2020 Approved ARAM AVEDISIAN
Shower Pan 9/4/2020 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 9/14/2020 Partial Approval ARAM AVEDISIAN
Interior/Exterior Lathing 9/21/2020 Partial Approval ARAM AVEDISIAN
Service/Power Release 10/7/2020 Approved ARAM AVEDISIAN
ELECTRICAL-Final 1/5/2021 Not Ready for Inspection ARAM AVEDISIAN
HVAC-Final 1/5/2021 Not Ready for Inspection ARAM AVEDISIAN
ELECTRICAL-Final 2/4/2021 Approved BEAU COLLINS
HVAC-Final 2/4/2021 Approved BEAU COLLINS
Final 3/10/2021 Corrections Issued JOHN HAYES
Footing/Foundation/Slab 3/10/2021 Not Ready for Inspection JOHN HAYES
Green Building Final 3/10/2021 Not Ready for Inspection JOHN HAYES
PLUMBING-Final 3/10/2021 Not Ready for Inspection JOHN HAYES
SGSOV-Seismic Gas S/O Valve 3/10/2021 SGSOV Not Ready JOHN HAYES
Smoke Detectors 3/10/2021 Not Ready for Inspection JOHN HAYES
PLUMBING-Final 3/17/2021 Approved ARAM AVEDISIAN
Final 4/23/2021 Corrections Issued JOHN HAYES
Footing/Foundation/Slab 4/23/2021 Not Ready for Inspection JOHN HAYES
Green Building Final 4/23/2021 Not Ready for Inspection JOHN HAYES
SGSOV-Seismic Gas S/O Valve 4/23/2021 SGSOV Not Ready JOHN HAYES
Smoke Detectors 4/23/2021 Not Ready for Inspection JOHN HAYES
Final 5/3/2021 Corrections Issued ARAM AVEDISIAN
Footing/Foundation/Slab 5/3/2021 Approved ARAM AVEDISIAN
Green Building Final 5/3/2021 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 5/3/2021 SGSOV Approved ARAM AVEDISIAN
Smoke Detectors 5/3/2021 Approved ARAM AVEDISIAN
Final 5/18/2021 Not Ready for Inspection ARAM AVEDISIAN
Final 5/21/2021 OK to Issue CofO ARAM AVEDISIAN