15228 W SATICOY ST 91405
Certificate Information: 15228 W SATICOY ST 91405
- Application / Permit
- 19010-20000-03023
- Plan Check / Job No.
- B19VN11698
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New 19'4" x 32'10" two-story Accessory Dwelling Unit per AB 494 & SB 229.
- Permit Issued
- Issued on 3/3/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/12/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/16/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 8/15/2019 | LUIS RINCON |
| Green Plans Picked Up | 8/21/2019 | APPLICANT |
| Corrections Issued | 8/29/2019 | LUIS RINCON |
| Quality Review Completed | 8/30/2019 | OMID HEDAYAT |
| Building Plans Picked Up | 9/9/2019 | APPLICANT |
| Plan Check Approved | 12/10/2019 | LUIS RINCON |
| Issued | 3/3/2020 | LADBS |
| CofO in Progress | 10/27/2020 | GREGG CUMMINGS |
| Permit Finaled | 1/12/2021 | MICHAEL SMITH |
| CofO Issued | 1/12/2021 | MICHAEL SMITH |
| Permit Finaled | 1/12/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 10/15/2019 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 10/15/2019 | LEE GUILBEAUX |
| Hydrant and Access approval | Cleared | 10/15/2019 | GEORGE SUCHAND |
| Sewer availability | Cleared | 10/15/2019 | LEE GUILBEAUX |
| Green Code | Cleared | 11/21/2019 | DAVID MATSON |
| Low Impact Development | Cleared | 11/21/2019 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 11/21/2019 | THOMAS LANG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Isaac,, Raymond; Lic. No.: C84605 | 21040 PARTHENIA ST APT 14 CANOGA PARK, CA 91304 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/9/2020 | Partial Inspection | WILLIAM KUEHN |
| Excavation/Setback/Form/Re-Bar | 3/27/2020 | Conditional Approval | WILLIAM KUEHN |
| Floor/Roof Diaphrgm/Shear Wall | 4/2/2020 | Partial Approval | BRENDAN LOONEY |
| Wood Frame | 4/2/2020 | Partial Approval | BRENDAN LOONEY |
| Floor/Roof Diaphrgm/Shear Wall | 4/13/2020 | Partial Inspection | WILLIAM KUEHN |
| Wood Frame | 4/13/2020 | Not Ready for Inspection | WILLIAM KUEHN |
| Floor/Roof Diaphrgm/Shear Wall | 4/15/2020 | Not Ready for Inspection | MISAEL ESPARZA |
| PLUMBING-Rough | 4/15/2020 | Approved | MISAEL ESPARZA |
| Wood Frame | 4/15/2020 | Not Ready for Inspection | MISAEL ESPARZA |
| ELECTRICAL-Rough | 4/21/2020 | Not Ready for Inspection | WILLIAM KUEHN |
| HVAC-Rough | 4/21/2020 | Not Ready for Inspection | WILLIAM KUEHN |
| Floor/Roof Diaphrgm/Shear Wall | 4/22/2020 | Not Ready for Inspection | WILLIAM KUEHN |
| Insulation | 4/23/2020 | Not Ready for Inspection | WILLIAM KUEHN |
| ELECTRICAL-Rough | 4/27/2020 | Corrections Issued | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 4/27/2020 | Not Ready for Inspection | MATTHEW NELSON |
| HVAC-Rough | 4/27/2020 | Approved | MATTHEW NELSON |
| Special/Order Compliance | 4/27/2020 | Approved | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 5/6/2020 | Conditional Approval | WILLIAM KUEHN |
| Floor/Roof Diaphrgm/Shear Wall | 5/6/2020 | Partial Inspection | WILLIAM KUEHN |
| Rough-Elec/Plmb/HVAC | 5/6/2020 | Approved | WILLIAM KUEHN |
| Insulation | 5/11/2020 | Corrections Issued | GREGG CUMMINGS |
| Interior/Exterior Lathing | 5/11/2020 | Approved | GREGG CUMMINGS |
| Insulation | 5/13/2020 | Approved | WILLIAM KUEHN |
| Drywall Nailing | 5/21/2020 | Approved | WILLIAM KUEHN |
| ELECTRICAL-Rough | 5/21/2020 | Approved | WILLIAM KUEHN |
| Green Building Rough | 5/21/2020 | Approved | WILLIAM KUEHN |
| BUILDING-Rough-Frame | 8/10/2020 | Approved | GREGG CUMMINGS |
| Final | 8/10/2020 | Corrections Issued | GREGG CUMMINGS |
| Footing/Foundation/Slab | 8/10/2020 | Approved | GREGG CUMMINGS |
| Green Building Final | 8/10/2020 | Approved | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 8/10/2020 | SGSOV Not Ready | GREGG CUMMINGS |
| Service/Power Release | 8/10/2020 | Not Ready for Inspection | GREGG CUMMINGS |
| Smoke Detectors | 8/10/2020 | Not Ready for Inspection | GREGG CUMMINGS |
| Verify Sprinkler Sign Off | 8/10/2020 | Approved | GREGG CUMMINGS |
| Final | 8/21/2020 | Not Ready for Inspection | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 8/21/2020 | SGSOV Approved | GREGG CUMMINGS |
| Service/Power Release | 8/21/2020 | Corrections Issued | GREGG CUMMINGS |
| Smoke Detectors | 8/21/2020 | Approved | GREGG CUMMINGS |
| Final | 8/31/2020 | Not Ready for Inspection | GREGG CUMMINGS |
| Service/Power Release | 8/31/2020 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 9/22/2020 | Not Ready for Inspection | GREGG CUMMINGS |
| Service/Power Release | 9/22/2020 | Partial Inspection | GREGG CUMMINGS |
| ELECTRICAL-Final | 10/26/2020 | Approved | GREGG CUMMINGS |
| Final | 10/26/2020 | OK to Issue CofO | GREGG CUMMINGS |
| HVAC-Final | 10/26/2020 | Approved | GREGG CUMMINGS |
| PLUMBING-Final | 10/26/2020 | Approved | GREGG CUMMINGS |
| Service/Power Release | 10/26/2020 | Approved | GREGG CUMMINGS |