12921 W NORRIS AVE 91342

Certificate Information: 12921 W NORRIS AVE 91342

Application / Permit
19010-20000-02965
Plan Check / Job No.
B19VN11513
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 20'X30' TWO-STORY DETACHED ADU PER AB 494 AND SB 229 [SEE COMMENTS].
Permit Issued
Issued on 12/31/2019
Issuing Office
West Los Angeles
Current Status
CofO Issued on 4/1/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/11/2019 APPLICANT
Green Plans Picked Up 7/24/2019 APPLICANT
Assigned to Plan Check Engineer 8/1/2019 DAWN MC NULTY
Corrections Issued 8/5/2019 DAWN MC NULTY
Quality Review Completed 8/8/2019 CHON CHIO KUO
Building Plans Picked Up 8/12/2019 APPLICANT
Applicant returned to address corrections 12/16/2019 DAWN MC NULTY
Plan Check Approved 12/19/2019 DAWN MC NULTY
Issued 12/31/2019 LADBS
CofO in Progress 3/18/2025 ROBERT GOLD
Permit Finaled 4/1/2025 RUBEN SALAS
CofO Issued 4/1/2025 RUBEN SALAS
Permit Finaled 4/1/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 9/18/2019 LEE GUILBEAUX
Miscellaneous Cleared 9/18/2019 LEE GUILBEAUX
Permit Cleared 9/18/2019 LEE GUILBEAUX
Low Impact Development Cleared 9/20/2019 JORGE MEJIA LEMUS
Hydrant and Access approval Cleared 9/24/2019 GEORGE SUCHAND
Roof/Waste drainage to street Cleared 9/24/2019 MARKOS PEREZ-BRAN
Green Code Cleared 10/22/2019 DAVID MATSON
Eng Process Fee Ord 176,300 Cleared 12/5/2019 GUILLERMO PETRA
Sewer availability Cleared 12/5/2019 GUILLERMO PETRA
Hold Cleared 1/24/2020 LOURDES RAMIRO

Contact Information

Contractor Owner-Builder       ,
Engineer Gosen,, James W; Lic. No.: C43590 15315 BLEDSOE ST      SYLMAR, CA 91342

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 1/23/2020 Partial Approval CHARLES POWELL
Excavation/Setback/Form/Re-Bar 1/28/2020 Corrections Issued ROBERT MINASSIANS
Footing/Foundation/Slab 2/7/2020 Corrections Issued ROBERT MINASSIANS
Footing/Foundation/Slab 2/25/2020 Partial Approval MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 3/9/2020 Approved TROY SANDERS
BUILDING-Rough-Frame 3/20/2020 Partial Approval TROY SANDERS
ELECTRICAL-Rough 3/20/2020 Approved TROY SANDERS
Green Building Rough 3/20/2020 Approved TROY SANDERS
HVAC-Rough 3/20/2020 Approved TROY SANDERS
PLUMBING-Rough 3/20/2020 Approved TROY SANDERS
Verify Sprinkler Sign Off 3/20/2020 Approved TROY SANDERS
Insulation 3/26/2020 Approved TROY SANDERS
Interior/Exterior Lathing 3/26/2020 Approved TROY SANDERS
Drywall Nailing 4/1/2020 Approved TROY SANDERS
Interior/Exterior Lathing 4/1/2020 Approved TROY SANDERS
Shower Pan 4/1/2020 Approved TROY SANDERS
BUILDING-Rough-Frame 5/27/2020 Approved TROY SANDERS
ELECTRICAL-Final 5/27/2020 Approved TROY SANDERS
Final 5/27/2020 Not Ready for Inspection TROY SANDERS
Footing/Foundation/Slab 5/27/2020 Approved TROY SANDERS
Green Building Final 5/27/2020 Not Ready for Inspection TROY SANDERS
HVAC-Final 5/27/2020 Approved TROY SANDERS
PLUMBING-Final 5/27/2020 Approved TROY SANDERS
SGSOV-Seismic Gas S/O Valve 5/27/2020 SGSOV Approved TROY SANDERS
Service/Power Release 5/27/2020 Approved TROY SANDERS
Smoke Detectors 5/27/2020 Approved TROY SANDERS
Final 6/5/2020 OK to Issue CofO TROY SANDERS
Green Building Final 6/5/2020 Approved TROY SANDERS