18911 W ERWIN ST 91335
Certificate Information: 18911 W ERWIN ST 91335
- Application / Permit
- 19010-20000-02938
- Plan Check / Job No.
- B19VN11416
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 33'-8" X 27'-0" IRREGULAR SHAPE 2-STORY ACCESSORY DWELLING UNIT WITH 6'-10" X 14'-10" OCCUPIED 2ND FLOOR ROOF DECK PER AB 494 & SB 229
- Permit Issued
- Issued on 12/23/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/4/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/10/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 8/8/2019 | ROSENDO MEDINA |
| Corrections Issued | 8/16/2019 | ROSENDO MEDINA |
| Quality Review Completed | 8/19/2019 | OMID HEDAYAT |
| Building Plans Picked Up | 8/23/2019 | APPLICANT |
| Green Plans Picked Up | 8/23/2019 | APPLICANT |
| Plan Check Approved | 9/23/2019 | ROSENDO MEDINA |
| Issued | 12/23/2020 | APPLICANT |
| CofO in Progress | 11/9/2022 | DAVID SANDOVAL |
| Permit Finaled | 3/4/2023 | DANIEL ORRANTE |
| CofO Issued | 3/4/2023 | DANIEL ORRANTE |
| Permit Finaled | 3/4/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Construction near power lines | Cleared | 8/20/2019 | RIDWAN HARDY |
| Address approval | Cleared | 9/5/2019 | APEKSHYA BAJRACHARYA |
| Eng Process Fee Ord 176,300 | Cleared | 9/5/2019 | APEKSHYA BAJRACHARYA |
| Sewer availability | Cleared | 9/5/2019 | APEKSHYA BAJRACHARYA |
| Low Impact Development | Cleared | 9/10/2019 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 9/10/2019 | SAFA JAVANMARDI |
| Green Code | Cleared | 9/12/2019 | MICHAEL AYERS |
| ZI | Cleared | 9/12/2019 | DAISY BENICIA |
| Hydrant and Access approval | Cleared | 9/23/2019 | GILBERT URREA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/28/2021 | No Access for Inspection | VINCENT HANLEY |
| Excavation/Setback/Form/Re-Bar | 2/10/2021 | Corrections Issued | STEVEN BACK |
| PLUMBING-Rough | 2/10/2021 | Partial Approval | STEVEN BACK |
| Footing/Foundation/Slab | 2/11/2021 | Corrections Issued | STEVEN BACK |
| Excavation/Setback/Form/Re-Bar | 3/3/2021 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 3/3/2021 | Corrections Issued | STEVEN BACK |
| Footing/Foundation/Slab | 3/3/2021 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 3/8/2021 | Partial Approval | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 3/23/2021 | Corrections Issued | STEVEN BACK |
| PLUMBING-Rough | 4/19/2021 | Partial Approval | STEVEN BACK |
| Sewer | 4/19/2021 | Approved | STEVEN BACK |
| Underground Mechanical | 4/19/2021 | Partial Approval | STEVEN BACK |
| ELECTRICAL-Rough | 5/12/2021 | Not Ready for Inspection | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 5/12/2021 | Corrections Issued | STEVEN BACK |
| HVAC-Rough | 5/12/2021 | Corrections Issued | STEVEN BACK |
| PLUMBING-Rough | 5/12/2021 | Corrections Issued | STEVEN BACK |
| ELECTRICAL-Rough | 5/21/2021 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 5/21/2021 | Partial Approval | STEVEN BACK |
| HVAC-Rough | 5/21/2021 | Corrections Issued | STEVEN BACK |
| PLUMBING-Rough | 5/21/2021 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 7/22/2021 | Approved | STEVEN BACK |
| Green Building Rough | 7/22/2021 | Approved | STEVEN BACK |
| HVAC-Rough | 7/22/2021 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 7/22/2021 | Partial Approval | STEVEN BACK |
| Verify Sprinkler Sign Off | 7/22/2021 | Approved | STEVEN BACK |
| Insulation | 7/29/2021 | Approved | RONALD COWAN |
| Drywall Nailing | 8/10/2021 | Approved | STEVEN BACK |
| Shower Pan | 10/5/2021 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 10/22/2021 | Approved | MORRIS JACKSON |
| ELECTRICAL-Final | 7/26/2022 | Approved | SEAN HAUPT |
| Final | 7/26/2022 | Corrections Issued | SEAN HAUPT |
| Green Building Final | 7/26/2022 | Not Ready for Inspection | SEAN HAUPT |
| HVAC-Final | 7/26/2022 | Approved | SEAN HAUPT |
| PLUMBING-Final | 7/26/2022 | Approved | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 7/26/2022 | SGSOV Approved | SEAN HAUPT |
| Service/Power Release | 7/26/2022 | Corrections Issued | SEAN HAUPT |
| Smoke Detectors | 7/26/2022 | Approved | SEAN HAUPT |
| ELECTRICAL-Final | 11/8/2022 | Approved | DAVID SANDOVAL |
| Final | 11/8/2022 | OK to Issue CofO | DAVID SANDOVAL |
| Green Building Final | 11/8/2022 | Approved | DAVID SANDOVAL |
| HVAC-Final | 11/8/2022 | Approved | DAVID SANDOVAL |
| Service/Power Release | 11/8/2022 | Approved | DAVID SANDOVAL |