13452 N KISMET AVE 91342

Certificate Information: 13452 N KISMET AVE 91342

Application / Permit
19010-20000-02910
Plan Check / Job No.
B19VN11247
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW (42'-11"x 27'-11") DETACHED ACCESSORY DWELLING UNIT PER AB 494 & SB 229. WORK PER LA STD WFPP.
Permit Issued
Issued on 10/31/2019
Issuing Office
Valley
Current Status
CofO Issued on 12/17/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/8/2019 APPLICANT
Green Plans Picked Up 8/2/2019 APPLICANT
Assigned to Plan Check Engineer 8/8/2019 TROY DEGUZMAN
Corrections Issued 8/14/2019 TROY DEGUZMAN
Quality Review Completed 8/14/2019 CHON CHIO KUO
Building Plans Picked Up 8/16/2019 APPLICANT
Plan Check Approved 10/18/2019 TROY DEGUZMAN
Issued 10/31/2019 LADBS
CofO in Progress 9/25/2021 JOHN HAYES
CofO Issued 12/17/2021 MICHAEL SMITH
Permit Finaled 12/17/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 8/22/2019 GABRIEL ROBLES
Green Code Cleared 8/29/2019 AARON COSTA
Low Impact Development Cleared 10/7/2019 ORVAL HERNANDEZ-MARCI
Eng Process Fee Ord 176,300 Cleared 10/10/2019 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 10/10/2019 ADRIAN CASTRO
Sewer availability Cleared 10/10/2019 ADRIAN CASTRO
Hydrant and Access approval Cleared 10/11/2019 GEORGE SUCHAND

Contact Information

Contractor Owner-Builder       ,

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/5/2020 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 2/5/2020 Partial Approval JENNIFER RABUCHIN
Excavation/Setback/Form/Re-Bar 2/11/2020 Corrections Issued JOHN HAYES
Excavation/Setback/Form/Re-Bar 6/23/2020 Approved GREGG CUMMINGS
PLUMBING-Rough 6/23/2020 Partial Approval GREGG CUMMINGS
Floor/Roof Diaphrgm/Shear Wall 8/4/2020 Not Ready for Inspection MISAEL ESPARZA
ELECTRICAL-Rough 8/13/2020 Corrections Issued MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 8/13/2020 Not Ready for Inspection MISAEL ESPARZA
HVAC-Rough 8/13/2020 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 8/13/2020 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 8/21/2020 Partial Approval MISAEL ESPARZA
ELECTRICAL-Rough 8/21/2020 Approved MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 8/21/2020 Approved MISAEL ESPARZA
HVAC-Rough 8/21/2020 Conditional Approval MISAEL ESPARZA
Insulation 8/27/2020 Approved MISAEL ESPARZA
Interior/Exterior Lathing 8/27/2020 Partial Approval MISAEL ESPARZA
Shower Pan 8/27/2020 Approved MISAEL ESPARZA
Drywall Nailing 9/1/2020 Approved MISAEL ESPARZA
Green Building Rough 9/1/2020 Approved MISAEL ESPARZA
Interior/Exterior Lathing 9/1/2020 Corrections Issued MISAEL ESPARZA
Interior/Exterior Lathing 9/9/2020 Approved MISAEL ESPARZA
Gas Test 10/6/2020 Partial Approval JENNIFER RABUCHIN
Sewer 10/6/2020 Approved JENNIFER RABUCHIN
Underground Mechanical 10/6/2020 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 11/24/2020 Approved MISAEL ESPARZA
ELECTRICAL-Final 11/24/2020 Corrections Issued MISAEL ESPARZA
Final 11/24/2020 Not Ready for Inspection MISAEL ESPARZA
Footing/Foundation/Slab 11/24/2020 Approved MISAEL ESPARZA
Green Building Final 11/24/2020 Not Ready for Inspection MISAEL ESPARZA
HVAC-Final 11/24/2020 Corrections Issued MISAEL ESPARZA
PLUMBING-Final 11/24/2020 Corrections Issued MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 11/24/2020 SGSOV Not Ready MISAEL ESPARZA
Service/Power Release 11/24/2020 Not Ready for Inspection MISAEL ESPARZA
Smoke Detectors 11/24/2020 Approved MISAEL ESPARZA
Verify Sprinkler Sign Off 11/24/2020 Approved MISAEL ESPARZA
Final 12/11/2020 Corrections Issued MISAEL ESPARZA
Green Building Final 12/11/2020 Not Ready for Inspection MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 12/11/2020 SGSOV Not Ready MISAEL ESPARZA
Service/Power Release 12/11/2020 Not Ready for Inspection MISAEL ESPARZA
Final 3/2/2021 Not Ready for Inspection MISAEL ESPARZA
Green Building Final 3/2/2021 Not Ready for Inspection MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 3/2/2021 SGSOV Approved MISAEL ESPARZA
Service/Power Release 3/2/2021 Not Ready for Inspection MISAEL ESPARZA
Final 9/17/2021 Not Ready for Inspection JOHN HAYES
Green Building Final 9/17/2021 Not Ready for Inspection JOHN HAYES
Service/Power Release 9/17/2021 Not Ready for Inspection JOHN HAYES
Final 9/24/2021 OK to Issue CofO JOHN HAYES
Green Building Final 9/24/2021 Approved JOHN HAYES
Service/Power Release 9/24/2021 Approved JOHN HAYES