Pre-Inspection
|
7/23/2024
|
Approved
|
PAUL DAVIDSON
|
|
Deputy Reinf. Concrete
|
7/26/2024
|
Conditional Approval
|
PAUL DAVIDSON
|
|
Special/Order Compliance
|
7/30/2024
|
Partial Inspection
|
PAUL DAVIDSON
|
|
Deputy Reinf. Concrete
|
8/28/2024
|
Conditional Approval
|
DANIEL VARNUM
|
|
Excavation/Setback/Form/Re-Bar
|
8/28/2024
|
No Access for Inspection
|
DANIEL VARNUM
|
|
Deputy Other (see comments)
|
9/10/2024
|
Conditional Approval
|
DANIEL VARNUM
|
|
Deputy Reinf. Concrete
|
9/16/2024
|
Conditional Approval
|
PAUL DAVIDSON
|
|
Deputy Drilled-In Anchors
|
9/18/2024
|
Conditional Approval
|
PAUL DAVIDSON
|
|
Deputy Other (see comments)
|
10/1/2024
|
Approved
|
DERRICK SPENCER
|
|
Deputy Other (see comments)
|
10/2/2024
|
Corrections Issued
|
DERRICK SPENCER
|
|
Deputy Other (see comments)
|
10/11/2024
|
Conditional Approval
|
DANIEL VARNUM
|
|
Footing/Foundation/Slab
|
10/22/2024
|
Partial Inspection
|
DANIEL VARNUM
|
|
Deputy Shotcrete
|
10/24/2024
|
Conditional Approval
|
PAUL DAVIDSON
|
|
Deputy Other (see comments)
|
10/30/2024
|
Conditional Approval
|
DANIEL VARNUM
|
|
Deputy Shotcrete
|
10/30/2024
|
Conditional Approval
|
PAUL DAVIDSON
|
|
Deputy Other (see comments)
|
11/5/2024
|
Conditional Approval
|
PAUL DAVIDSON
|
|
Deputy Reinf. Concrete
|
11/12/2024
|
Conditional Approval
|
PAUL DAVIDSON
|
|
Deputy Shotcrete
|
11/12/2024
|
Conditional Approval
|
PAUL DAVIDSON
|
|
Footing/Foundation/Slab
|
11/22/2024
|
Not Ready for Inspection
|
PAUL DAVIDSON
|
|
Excavation/Setback/Form/Re-Bar
|
11/26/2024
|
Partial Approval
|
PAUL DAVIDSON
|
|
Deputy Reinf. Concrete
|
11/27/2024
|
Conditional Approval
|
PAUL DAVIDSON
|
|
Deputy Reinf. Masonry
|
12/6/2024
|
Conditional Approval
|
PAUL DAVIDSON
|
|
Excavation/Setback/Form/Re-Bar
|
12/9/2024
|
Not Ready for Inspection
|
PAUL DAVIDSON
|
|
Excavation/Setback/Form/Re-Bar
|
12/10/2024
|
Corrections Issued
|
PAUL DAVIDSON
|
|
Special/Order Compliance
|
12/10/2024
|
Partial Approval
|
RICARDO ROBLES
|
|
Excavation/Setback/Form/Re-Bar
|
12/12/2024
|
Partial Approval
|
PAUL DAVIDSON
|
|
Deputy Shotcrete
|
12/13/2024
|
Conditional Approval
|
PAUL DAVIDSON
|
|
Excavation/Setback/Form/Re-Bar
|
12/13/2024
|
Not Ready for Inspection
|
PAUL DAVIDSON
|
|
Deputy Shotcrete
|
12/16/2024
|
Conditional Approval
|
PAUL DAVIDSON
|
|
Excavation/Setback/Form/Re-Bar
|
12/16/2024
|
Partial Approval
|
DANIEL VARNUM
|
|
Deputy Shotcrete
|
12/23/2024
|
Conditional Approval
|
DANIEL VARNUM
|
|
Deputy Shotcrete
|
12/24/2024
|
Conditional Approval
|
DANIEL VARNUM
|
|
Deputy Shotcrete
|
12/26/2024
|
Conditional Approval
|
PAUL DAVIDSON
|
|
Masonry Wall/Backfill
|
1/6/2025
|
Partial Approval
|
DANIEL VARNUM
|
|
Footing/Foundation/Slab
|
2/4/2025
|
Partial Approval
|
DANIEL VARNUM
|
|
Special/Order Compliance
|
2/13/2025
|
No Access for Inspection
|
PAUL DAVIDSON
|
|
Deputy Reinf. Concrete
|
2/24/2025
|
Conditional Approval
|
DANIEL VARNUM
|
|
Footing/Foundation/Slab
|
2/24/2025
|
Partial Approval
|
DANIEL VARNUM
|
|
Deputy Reinf. Masonry
|
4/16/2025
|
Approved
|
DERRICK SPENCER
|
|
Deputy Drilled-In Anchors
|
5/1/2025
|
Conditional Approval
|
PAUL DAVIDSON
|
|
Deputy Reinf. Concrete
|
5/1/2025
|
Conditional Approval
|
PAUL DAVIDSON
|
|
Footing/Foundation/Slab
|
5/5/2025
|
Partial Approval
|
DANIEL VARNUM
|
|
Deputy Reinf. Concrete
|
5/6/2025
|
Conditional Approval
|
DANIEL VARNUM
|
|
Deputy Reinf. Masonry
|
5/19/2025
|
Conditional Approval
|
PAUL DAVIDSON
|
|
Masonry Wall/Backfill
|
5/20/2025
|
Partial Approval
|
PAUL DAVIDSON
|
|
Deputy Reinf. Masonry
|
6/5/2025
|
Approved
|
VASIL MIHALEV
|
|
Special/Order Compliance
|
7/7/2025
|
Partial Inspection
|
PAUL DAVIDSON
|
|
Deputy Reinf. Concrete
|
7/10/2025
|
Conditional Approval
|
PAUL DAVIDSON
|
|
Deputy Reinf. Concrete
|
8/1/2025
|
Conditional Approval
|
PAUL DAVIDSON
|
|
Footing/Foundation/Slab
|
8/1/2025
|
Partial Approval
|
PAUL DAVIDSON
|
|
Deputy Reinf. Concrete
|
8/8/2025
|
Conditional Approval
|
DANIEL VARNUM
|
|
Deputy Reinf. Concrete
|
8/8/2025
|
Conditional Approval
|
PAUL DAVIDSON
|
|
Green Building Rough
|
8/26/2025
|
Not Ready for Inspection
|
DANIEL VARNUM
|
|
Verify Sprinkler Sign Off
|
8/26/2025
|
Not Ready for Inspection
|
DANIEL VARNUM
|
|
Wood Frame
|
8/26/2025
|
Partial Approval
|
DANIEL VARNUM
|
|
Deputy Wood Construction
|
8/27/2025
|
Conditional Approval
|
DANIEL VARNUM
|
|
Green Building Rough
|
9/17/2025
|
Not Ready for Inspection
|
DANIEL VARNUM
|
|
Verify Sprinkler Sign Off
|
9/17/2025
|
Not Ready for Inspection
|
DANIEL VARNUM
|
|
Wood Frame
|
9/17/2025
|
Partial Approval
|
DANIEL VARNUM
|
|
Deputy Wood Construction
|
9/30/2025
|
Conditional Approval
|
DANIEL VARNUM
|
|
Green Building Rough
|
9/30/2025
|
Not Ready for Inspection
|
DANIEL VARNUM
|
|
Verify Sprinkler Sign Off
|
9/30/2025
|
Not Ready for Inspection
|
DANIEL VARNUM
|
|
Wood Frame
|
9/30/2025
|
Partial Approval
|
DANIEL VARNUM
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/23/2025
|
Partial Approval
|
DANIEL VARNUM
|
|
Green Building Rough
|
11/7/2025
|
Approved
|
DERRICK SPENCER
|
|
Verify Sprinkler Sign Off
|
11/7/2025
|
Approved
|
DERRICK SPENCER
|
|
Wood Frame
|
11/7/2025
|
Partial Approval
|
DERRICK SPENCER
|
|
Special/Order Compliance
|
1/6/2026
|
Partial Inspection
|
PAUL DAVIDSON
|
|
Interior/Exterior Lathing
|
1/9/2026
|
Partial Approval
|
PAUL DAVIDSON
|
|
Insulation
|
1/28/2026
|
Corrections Issued
|
PAUL DAVIDSON
|
|
Wood Frame
|
2/9/2026
|
Partial Approval
|
PAUL DAVIDSON
|
|
Drywall Nailing
|
2/23/2026
|
Partial Approval
|
PAUL DAVIDSON
|
|
Insulation
|
2/25/2026
|
Approved
|
PAUL DAVIDSON
|
|
Wood Frame
|
2/25/2026
|
Approved
|
PAUL DAVIDSON
|
|
Special/Order Compliance
|
4/3/2026
|
Partial Inspection
|
PAUL DAVIDSON
|
|
Drywall Nailing
|
4/9/2026
|
Partial Approval
|
PAUL DAVIDSON
|
|
Interior/Exterior Lathing
|
4/9/2026
|
Approved
|
PAUL DAVIDSON
|
|
Special/Order Compliance
|
5/4/2026
|
Partial Inspection
|
PAUL DAVIDSON
|
|
Special/Order Compliance
|
6/11/2026
|
Partial Inspection
|
PAUL DAVIDSON
|
|
Special/Order Compliance
|
7/13/2026
|
Partial Inspection
|
PAUL DAVIDSON
|
|
Special/Order Compliance
|
7/14/2026
|
No Result Entered
|
PAUL DAVIDSON
|