20816 W ACORN CIR UNIT #232 91326
Certificate Information: 20816 W ACORN CIR UNIT #232 91326
- Application / Permit
- 19010-20000-02905
- Plan Check / Job No.
- B19VN11199
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (35) Condo-Single Family
- Work Description
- PROPOSE TWO STORY SFD-CONDO WITH ATTACH 2 CAR GARAGE_STANDARD PLAN 646_ PLAN #3CR (BUILDING SHALL BE FULLY SPRINKLER THROUGH OUT WITH NFPA 13D).
- Permit Issued
- Issued on 1/9/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/5/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/8/2019 | APPLICANT |
| Green Plans Picked Up | 7/25/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 8/1/2019 | DAWN MC NULTY |
| Corrections Issued | 8/21/2019 | DAWN MC NULTY |
| Quality Review Completed | 8/22/2019 | CHON CHIO KUO |
| Building Plans Picked Up | 8/27/2019 | APPLICANT |
| Plan Check Approved | 1/7/2020 | DAWN MC NULTY |
| Issued | 1/9/2020 | LADBS |
| CofO in Progress | 8/5/2020 | SEAN WIRCH |
| CofO Issued | 8/5/2020 | DONALD SUNSERI |
| Permit Finaled | 8/5/2020 | DONALD SUNSERI |
Permit Application Clearance Information
| Low Impact Development | Cleared | 9/16/2019 | AMMAR ELTAWIL |
| Hydrant and Access approval | Cleared | 9/25/2019 | ROBERT DUFF |
| "T" removal | Cleared | 10/23/2019 | SARAH GOLDMAN |
| APC | Cleared | 10/23/2019 | SARAH GOLDMAN |
| APC | Cleared | 10/23/2019 | SARAH GOLDMAN |
| CPC | Cleared | 10/23/2019 | SARAH GOLDMAN |
| Frnt yard landscape/Water mgmt | Cleared | 10/23/2019 | SARAH GOLDMAN |
| Miscellaneous | Cleared | 10/23/2019 | SARAH GOLDMAN |
| Opn space landscape/Water mgmt | Cleared | 10/23/2019 | SARAH GOLDMAN |
| Specific Plan | Cleared | 10/23/2019 | SARAH GOLDMAN |
| Tract Map conditions | Cleared | 10/23/2019 | SARAH GOLDMAN |
| Tract Map conditions | Cleared | 10/23/2019 | SARAH GOLDMAN |
| Tract Map conditions | Cleared | 10/23/2019 | SARAH GOLDMAN |
| Tract Map conditions | Cleared | 10/23/2019 | SARAH GOLDMAN |
| ZA Case | Cleared | 10/23/2019 | SARAH GOLDMAN |
| Address approval | Cleared | 10/24/2019 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 10/24/2019 | LEE GUILBEAUX |
| Permit | Cleared | 10/24/2019 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 10/24/2019 | LEE GUILBEAUX |
| Sewer availability | Cleared | 10/24/2019 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 10/24/2019 | LEE GUILBEAUX |
| Public Works-Open Permits | Cleared | 10/24/2019 | LEE GUILBEAUX |
| Green Code | Cleared | 1/7/2020 | MICHAEL AYERS |
Contact Information
| Architect | Falese, Debra Suzanne; Lic. No.: C24900 | 2943 PULLMAN SUITE A SANTA ANA, CA 92705 |
| Contractor | Shapell Homes Inc; Lic. No.: 1001034-B | 250 GIBRALTAR RD ATTN: GATES/LEGAL HORSHAM, PA 19044 |
| Engineer | Christian, Dale Alan; Lic. No.: S2705 | 1744 W KATELLA AVENUE SUITE 107 ORANGE, CA 92867 |
| Engineer | Hattar, Basil Ibrahim; Lic. No.: GE2734 | 3525 PARK MEADOW CT PALMDALE, CA 93551 |
| Engineer | Kim, Kevin Chae; Lic. No.: C53821 | 2349 N CAMPUS AVENUE UPLAND, CA 91784 |
| Engineer | Nelson, William Mc Kee; Lic. No.: S3417 | 5 DELLWOOD DOVE CANYON, CA 92679 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 1/23/2020 | Approved | SEAN WIRCH |
| Footing/Foundation/Slab | 2/7/2020 | Approved | SEAN WIRCH |
| Sewer | 2/19/2020 | Approved | SEAN WIRCH |
| Underground Mechanical | 2/24/2020 | Approved | SEAN WIRCH |
| Floor/Roof Diaphrgm/Shear Wall | 3/9/2020 | Approved | SEAN WIRCH |
| Floor/Roof Diaphrgm/Shear Wall | 3/27/2020 | Approved | SEAN WIRCH |
| Floor/Roof Diaphrgm/Shear Wall | 4/20/2020 | Approved | SEAN WIRCH |
| Floor/Roof Diaphrgm/Shear Wall | 4/21/2020 | Approved | SEAN WIRCH |
| BUILDING-Rough-Frame | 4/27/2020 | Approved | SEAN WIRCH |
| Green Building Rough | 4/27/2020 | Approved | SEAN WIRCH |
| Rough-Elec/Plmb/HVAC | 4/27/2020 | Approved | SEAN WIRCH |
| Verify Sprinkler Sign Off | 4/27/2020 | Approved | SEAN WIRCH |
| Drywall Nailing | 5/4/2020 | Approved | SEAN WIRCH |
| Interior/Exterior Lathing | 5/5/2020 | Approved | SEAN WIRCH |
| Interior/Exterior Lathing | 5/27/2020 | Approved | SEAN WIRCH |
| Gas Test | 6/2/2020 | Approved | SEAN WIRCH |
| Service/Power Release | 6/25/2020 | Approved | SEAN WIRCH |
| SGSOV-Seismic Gas S/O Valve | 7/7/2020 | SGSOV Approved | SEAN WIRCH |
| ELECTRICAL-Final | 8/4/2020 | Approved | SEAN WIRCH |
| Final | 8/4/2020 | OK to Issue CofO | SEAN WIRCH |
| Green Building Final | 8/4/2020 | Approved | SEAN WIRCH |
| HVAC-Final | 8/4/2020 | Approved | SEAN WIRCH |
| PLUMBING-Final | 8/4/2020 | Approved | SEAN WIRCH |
| Smoke Detectors | 8/4/2020 | Approved | SEAN WIRCH |