18153 W GRESHAM ST 91325
Certificate Information: 18153 W GRESHAM ST 91325
- Application / Permit
- 19010-20000-02866
- Plan Check / Job No.
- B19VN11087
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW (2) STORY 34'-8" x 32 ACCESSORY DWELLING UNIT PER AB494 AND SB229
- Permit Issued
- Issued on 11/16/2020
- Issuing Office
- Current Status
- Issued on 11/16/2020
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/3/2019 | APPLICANT |
| Green Plans Picked Up | 8/5/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 8/8/2019 | LUIS RINCON |
| Corrections Issued | 8/16/2019 | LUIS RINCON |
| Quality Review Completed | 8/21/2019 | OMID HEDAYAT |
| Building Plans Picked Up | 9/6/2019 | APPLICANT |
| Plan Check Approved | 7/17/2020 | SELLA BENYAMIN |
| Issued | 11/16/2020 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 11/20/2019 | LEE GUILBEAUX |
| Sewer availability | Cleared | 11/20/2019 | LEE GUILBEAUX |
| Construction near power lines | Cleared | 11/27/2019 | RIDWAN HARDY |
| Green Code | Cleared | 12/5/2019 | MICHAEL AYERS |
| Hydrant and Access approval | Cleared | 12/5/2019 | GEORGE SUCHAND |
| Low Impact Development | Cleared | 2/19/2020 | ORVAL HERNANDEZ-MARCIAL |
| Eng Process Fee Ord 176,300 | Cleared | 8/17/2020 | GABRIEL ROBLES |
| Roof/Waste drainage to street | Cleared | 8/24/2020 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Gorgy,, Moheb Shohdy; Lic. No.: C53260 | 1545 VICTORY BLVD STE 102 GLENDALE, CA 91201 |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/19/2021 | Partial Approval | JEFFREY PARD |
| Excavation/Setback/Form/Re-Bar | 3/5/2021 | Approved | JEFFREY PARD |
| Footing/Foundation/Slab | 3/5/2021 | Approved | JEFFREY PARD |
| BUILDING-Rough-Frame | 4/5/2021 | Not Ready for Inspection | JEFFREY PARD |
| Floor/Roof Diaphrgm/Shear Wall | 4/5/2021 | Approved | JEFFREY PARD |
| Green Building Rough | 4/5/2021 | Not Ready for Inspection | JEFFREY PARD |
| Verify Sprinkler Sign Off | 4/5/2021 | Not Ready for Inspection | JEFFREY PARD |
| Wood Frame | 4/5/2021 | Not Ready for Inspection | JEFFREY PARD |
| Floor/Roof Diaphrgm/Shear Wall | 4/22/2021 | Approved | JEFFREY PARD |
| Wood Frame | 4/22/2021 | Approved | JEFFREY PARD |
| ELECTRICAL-Rough | 9/3/2021 | Corrections Issued | JEFFREY PARD |
| HVAC-Rough | 9/3/2021 | Approved | JEFFREY PARD |
| PLUMBING-Rough | 9/3/2021 | Approved | JEFFREY PARD |
| Deputy Wood Construction | 10/1/2021 | Approved | JEFFREY PARD |
| Floor/Roof Diaphrgm/Shear Wall | 10/7/2021 | Approved | JEFFREY PARD |
| Rough-Elec/Plmb/HVAC | 10/7/2021 | Approved | JEFFREY PARD |
| Wood Frame | 10/7/2021 | Approved | JEFFREY PARD |
| Interior/Exterior Lathing | 11/1/2021 | Approved | JEFFREY PARD |
| Insulation | 11/12/2021 | Approved | STEVEN BACK |
| Sewer | 11/12/2021 | No Access for Inspection | STEVEN BACK |
| Drywall Nailing | 11/24/2021 | Approved | JEFFREY PARD |
| Green Building Rough | 11/24/2021 | Approved | JEFFREY PARD |
| Sewer | 11/24/2021 | Approved | JEFFREY PARD |
| Grading Pre-Inspection | 4/22/2022 | Not Ready for Inspection | JEFFREY PARD |
| Underground Mechanical | 4/22/2022 | Approved | JEFFREY PARD |
| Smoke Detectors | 5/12/2023 | Not Ready for Inspection | JOHN KIDWELL |
| ELECTRICAL-Final | 6/22/2023 | Approved | JOHN KIDWELL |
| HVAC-Final | 6/22/2023 | Approved | JOHN KIDWELL |
| ELECTRICAL-Final | 7/16/2024 | Not Ready for Inspection | KRISTEN CAUSEY |
| HVAC-Final | 7/16/2024 | Not Ready for Inspection | KRISTEN CAUSEY |
| Shower Pan | 7/31/2024 | Approved | KRISTEN CAUSEY |