509 N MOUNT HOLYOKE AVE 90272
Certificate Information: 509 N MOUNT HOLYOKE AVE 90272
- Application / Permit
- 19010-20000-02848
- Plan Check / Job No.
- B19VN11034
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- NEW DETACHED 22' X 32' 3-CAR GARAGE ON CONCRETE PILES. ALL WORK DONE PER STRUCTURAL ENGINEERING. NEW DETACHED 20' 4" X 30' 3-CAR GARAGE ON CONCRETE PILES. ALL WORK DONE PER STRUCTURAL ENGINEERING.
- Permit Issued
- Issued on 2/6/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/29/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/3/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 7/25/2019 | GURUNATH NESARAJAH |
| Corrections Issued | 7/27/2019 | GURUNATH NESARAJAH |
| Quality Review Completed | 7/30/2019 | OMID HEDAYAT |
| Building Plans Picked Up | 8/2/2019 | APPLICANT |
| Green Plans Picked Up | 8/2/2019 | APPLICANT |
| Plan Check Approved | 1/24/2020 | GURUNATH NESARAJAH |
| Issued | 2/6/2020 | LADBS |
| CofO in Progress | 12/19/2023 | EVAN COOPER |
| Permit Finaled | 2/29/2024 | DANIEL ORRANTE |
| CofO Issued | 2/29/2024 | DANIEL ORRANTE |
| Permit Finaled | 2/29/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 8/26/2019 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 8/26/2019 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 8/26/2019 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 8/26/2019 | LEE GUILBEAUX |
| Permit | Cleared | 8/26/2019 | LEE GUILBEAUX |
| Low Impact Development | Cleared | 9/20/2019 | RYAN HUDSON |
| Coastal Zone | Cleared | 9/23/2019 | NOAH MCCOY |
| Miscellaneous | Cleared | 9/23/2019 | NOAH MCCOY |
| Roof/Waste drainage to street | Cleared | 9/23/2019 | DINAH GARIN |
| ZI | Cleared | 9/23/2019 | NOAH MCCOY |
| Trees in Parkway | Cleared | 9/25/2019 | ADRIAN SANCHEZ |
| GPI Written Notices | Cleared | 10/24/2019 | GURUNATH NESARAJAH |
| Grading Pre-Inspection | Cleared | 10/24/2019 | GURUNATH NESARAJAH |
| Permit | Cleared | 12/17/2019 | JOHN LIN |
| Trees in Parkway | Cleared | 12/23/2019 | STEPHEN DUPREY |
Contact Information
| Architect | Kerr,, Robert E; Lic. No.: C28038 | 2551 S BUNDY DRIVE LOS ANGELES, CA 90064 |
| Contractor | A - 1 Construction; Lic. No.: 629700-B | 10650 OVERMAN AVENUE CHATSWORTH, CA 91311 |
| Engineer | Irvine,, Jon Alan; Lic. No.: GE2891 | 145 N SIERRA MADRE BLVD STE 1 PASADENA, CA 91107 |
| Engineer | Mahlow,, Elizabeth Joy Johnson; Lic. No.: C80463 | 4215 TOLAND WAY LOS ANGELES, CA 90065 |
Inspector Information
| STEPHANIE SWANSON, (213) 469-1255 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 3/5/2020 | Partial Approval | ANDREW NAVE |
| Deputy Reinf. Concrete | 3/9/2020 | Approved | ROBERT SHELLY |
| Footing/Foundation/Slab | 6/9/2020 | Partial Approval | ANDREW NAVE |
| Deputy Reinf. Concrete | 7/1/2020 | Corrections Issued | ROBERT SHELLY |
| Excavation/Setback/Form/Re-Bar | 7/1/2020 | Partial Approval | ANDREW NAVE |
| Footing/Foundation/Slab | 7/22/2020 | Partial Approval | ANDREW NAVE |
| Deputy Reinf. Concrete | 8/10/2020 | No Access for Inspection | KENNETH NAGLE |
| Deputy Reinf. Concrete | 8/14/2020 | Conditional Approval | ANDREW NAVE |
| Footing/Foundation/Slab | 8/18/2020 | Approved | ANDREW NAVE |
| Special/Order Compliance | 8/18/2020 | Corrections Issued | ANDREW NAVE |
| Deputy Reinf. Concrete | 8/19/2020 | Conditional Approval | ANDREW NAVE |
| BUILDING-Rough-Frame | 12/9/2020 | Approved | ANDREW NAVE |
| Green Building Rough | 12/9/2020 | Approved | ANDREW NAVE |
| ELECTRICAL-Rough | 12/17/2020 | Partial Approval | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 12/23/2020 | Partial Approval | OGANES TARAKHCHYAN |
| Drywall Nailing | 5/18/2021 | Approved | ANDREW NAVE |
| Final | 5/18/2021 | Corrections Issued | ANDREW NAVE |
| Green Building Final | 5/18/2021 | Not Ready for Inspection | ANDREW NAVE |
| Reinforced Concrete Frame | 5/18/2021 | Approved | ANDREW NAVE |
| SGSOV-Seismic Gas S/O Valve | 5/18/2021 | SGSOV Not Ready | ANDREW NAVE |
| Service/Power Release | 5/18/2021 | Not Required | ANDREW NAVE |
| Smoke Detectors | 5/18/2021 | Not Ready for Inspection | ANDREW NAVE |
| ELECTRICAL-Final | 8/9/2021 | Corrections Issued | ANDREW NAVE |
| ELECTRICAL-Final | 8/11/2021 | Conditional Approval | ANDREW NAVE |
| ELECTRICAL-Final | 8/30/2021 | Approved | ANDREW NAVE |
| Final | 9/26/2023 | Not Ready for Inspection | EVAN COOPER |
| Green Building Final | 9/26/2023 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 9/26/2023 | SGSOV Not Ready | EVAN COOPER |
| Smoke Detectors | 9/26/2023 | Approved | EVAN COOPER |
| Special/Order Compliance | 9/26/2023 | Corrections Issued | EVAN COOPER |
| Final | 11/14/2023 | Corrections Issued | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 11/14/2023 | SGSOV Approved | EVAN COOPER |
| Final | 12/19/2023 | OK to Issue CofO | EVAN COOPER |