7961 N PASO ROBLES AVE 91406

Certificate Information: 7961 N PASO ROBLES AVE 91406

Application / Permit
19010-20000-02807
Plan Check / Job No.
B19VN10891
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Accessory Living Quarters
Work Description
PROPOSED (20'-6" X 34'-4") ACCESSORY LIVING QUARTERS. ALL WORK PER WFPP. NFPA 13D FIRE SPRINKLERS THROUGHOUT.
Permit Issued
Issued on 2/13/2020
Issuing Office
Valley
Current Status
CofO Issued on 5/16/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/1/2019 APPLICANT
Assigned to Plan Check Engineer 8/1/2019 RAPHAEL ROSAS
Corrections Issued 8/3/2019 RAPHAEL ROSAS
Quality Review Completed 8/6/2019 CHON CHIO KUO
Green Plans Picked Up 8/6/2019 APPLICANT
Building Plans Picked Up 8/13/2019 APPLICANT
Plan Check Approved 2/13/2020 RAPHAEL ROSAS
Issued 2/13/2020 LADBS
CofO in Progress 5/16/2022 RAUL OLAGI
Permit Finaled 5/16/2022 MICHAEL SMITH
CofO Issued 5/16/2022 MICHAEL SMITH
Permit Finaled 5/16/2022 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/22/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 1/22/2020 JOHN TRIANTAFYLLOS
Hydrant and Access approval Cleared 1/23/2020 GEORGE SUCHAND
Low Impact Development Cleared 2/11/2020 SARAH YOUSSEF
Construction near power lines Cleared 2/13/2020 OSCAR CASTRO
Green Code Cleared 2/13/2020 MICHAEL AYERS
Roof/Waste drainage to street Cleared 2/13/2020 JOHN TRIANTAFYLLOS

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/28/2020 Partial Approval JACK KARGODORIAN
Excavation/Setback/Form/Re-Bar 3/6/2020 Approved JACK KARGODORIAN
Footing/Foundation/Slab 3/6/2020 Approved JACK KARGODORIAN
Grounding or Bonding 4/21/2020 Partial Inspection MATTHEW NELSON
BUILDING-Rough-Frame 4/29/2020 Corrections Issued BRENDAN LOONEY
Green Building Rough 4/29/2020 Not Ready for Inspection BRENDAN LOONEY
Insulation 4/29/2020 Not Ready for Inspection BRENDAN LOONEY
Rough-Elec/Plmb/HVAC 4/29/2020 Not Ready for Inspection BRENDAN LOONEY
Verify Sprinkler Sign Off 4/29/2020 Approved BRENDAN LOONEY
BUILDING-Rough-Frame 5/15/2020 Not Ready for Inspection MISAEL ESPARZA
Green Building Rough 5/15/2020 Not Ready for Inspection MISAEL ESPARZA
Rough-Elec/Plmb/HVAC 5/15/2020 Corrections Issued MISAEL ESPARZA
BUILDING-Rough-Frame 5/18/2020 Approved WILLIAM KUEHN
Floor/Roof Diaphrgm/Shear Wall 5/18/2020 Partial Inspection WILLIAM KUEHN
Rough-Elec/Plmb/HVAC 5/18/2020 Approved WILLIAM KUEHN
Insulation 5/21/2020 Approved MATTHEW NELSON
Interior/Exterior Lathing 5/21/2020 Approved MATTHEW NELSON
Shower Pan 5/27/2020 Approved GREGG CUMMINGS
Drywall Nailing 5/28/2020 Approved GREGG CUMMINGS
Green Building Rough 5/28/2020 Approved GREGG CUMMINGS
Interior/Exterior Lathing 6/23/2020 Partial Inspection WILLIAM KUEHN
Shower Pan 6/23/2020 Approved WILLIAM KUEHN
Underground Mechanical 7/7/2020 Approved DANIEL DREW
Final 5/4/2022 Corrections Issued RAUL OLAGI
Green Building Final 5/4/2022 Not Ready for Inspection RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 5/4/2022 SGSOV Not Ready RAUL OLAGI
Service/Power Release 5/4/2022 Not Ready for Inspection RAUL OLAGI
Smoke Detectors 5/4/2022 Not Ready for Inspection RAUL OLAGI
Final 5/10/2022 Corrections Issued RAUL OLAGI
Gas Test 5/10/2022 Approved RAUL OLAGI
Green Building Final 5/10/2022 Approved RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 5/10/2022 SGSOV Approved RAUL OLAGI
Service/Power Release 5/10/2022 Not Required RAUL OLAGI
Smoke Detectors 5/10/2022 Approved RAUL OLAGI
Final 5/13/2022 OK to Issue CofO RAUL OLAGI