245-245 1/2 E 66TH ST 90003
Certificate Information: 245-245 1/2 E 66TH ST 90003
- Application / Permit
- 19010-20000-02792
- Plan Check / Job No.
- B19VN10826
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- PROPOSE 25'X70'-6" TWO STORY DUPLEX- BUILDING SHALL BE FULLY SPRINKLER THROUGH OUT WITH NFPA 13D.
- Permit Issued
- Issued on 3/18/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/22/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/28/2019 | APPLICANT |
| Green Plans Picked Up | 7/10/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 7/18/2019 | DAWN MC NULTY |
| Corrections Issued | 7/22/2019 | DAWN MC NULTY |
| Quality Review Completed | 7/22/2019 | CHON CHIO KUO |
| Building Plans Picked Up | 7/23/2019 | APPLICANT |
| Applicant returned to address corrections | 2/28/2020 | DAWN MC NULTY |
| Applicant returned to address corrections | 3/9/2020 | DAWN MC NULTY |
| Plan Check Approved | 3/18/2020 | DAWN MC NULTY |
| Issued | 3/18/2020 | LADBS |
| CofO in Progress | 6/16/2021 | EUGENE CASSIDY |
| Permit Finaled | 7/22/2021 | DEROLD HAUFF |
| CofO Issued | 7/22/2021 | DEROLD HAUFF |
| Permit Finaled | 7/22/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/28/2019 | ERIK BEASLEY |
| Highway dedication | Cleared | 8/28/2019 | ERIK BEASLEY |
| Permit | Cleared | 8/28/2019 | ERIK BEASLEY |
| ZI | Cleared | 12/13/2019 | HELEN JADALI |
| Green Code | Cleared | 1/8/2020 | MICHAEL AYERS |
| Frnt yard landscape/Water mgmt | Cleared | 1/23/2020 | TERRI OSBORNE |
| Low Impact Development | Cleared | 1/23/2020 | SARAH YOUSSEF |
| Eng Process Fee Ord 176,300 | Cleared | 1/24/2020 | JEANETTE VONG |
| Hydrant and Access approval | Cleared | 1/24/2020 | JOHN CONNEALLY |
| Roof/Waste drainage to street | Cleared | 1/24/2020 | JEANETTE VONG |
| Sewer availability | Cleared | 1/24/2020 | JEANETTE VONG |
Contact Information
| Contractor | Aardvark Group Inc The; Lic. No.: 762498-B | 13337 SOUTH STREET # 134 CERRITOS, CA 90703 |
| Engineer | Dorta,, Michael Rohrs; Lic. No.: C72538 | 26851 GRAYSLAKE ROAD RANCHO PALOS VERDES, CA 90275 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 8/20/2020 | Conditional Approval | FREDDIE RIVERA |
| Excavation/Setback/Form/Re-Bar | 9/4/2020 | Corrections Issued | DAVID FEILER |
| Grounding or Bonding | 9/4/2020 | Not Ready for Inspection | DAVID FEILER |
| Excavation/Setback/Form/Re-Bar | 9/9/2020 | Approved | FREDDIE RIVERA |
| Grounding or Bonding | 9/10/2020 | Approved | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 9/29/2020 | Partial Approval | FREDDIE RIVERA |
| Deputy Wood Construction | 11/4/2020 | No Access for Inspection | ELMER BLAND |
| Floor/Roof Diaphrgm/Shear Wall | 11/10/2020 | Partial Approval | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 12/10/2020 | Not Ready for Inspection | DAVID FEILER |
| Green Building Rough | 12/10/2020 | Corrections Issued | DAVID FEILER |
| Rough-Elec/Plmb/HVAC | 12/10/2020 | Corrections Issued | DAVID FEILER |
| Verify Sprinkler Sign Off | 12/10/2020 | Approved | DAVID FEILER |
| BUILDING-Rough-Frame | 12/14/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Rough | 12/14/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| Rough-Elec/Plmb/HVAC | 12/14/2020 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 12/17/2020 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Rough | 12/17/2020 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 12/17/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 12/17/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| Insulation | 12/18/2020 | Approved | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 12/22/2020 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Rough | 12/22/2020 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 12/22/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 3/30/2021 | Corrections Issued | DAVID FEILER |
| Footing/Foundation/Slab | 3/30/2021 | Approved | DAVID FEILER |
| Gas Test | 3/30/2021 | Approved | DAVID FEILER |
| Green Building Final | 3/30/2021 | Approved | DAVID FEILER |
| HVAC-Final | 3/30/2021 | Approved | DAVID FEILER |
| SGSOV-Seismic Gas S/O Valve | 3/30/2021 | SGSOV Approved | DAVID FEILER |
| Service/Power Release | 3/30/2021 | Not Ready for Inspection | DAVID FEILER |
| Smoke Detectors | 3/30/2021 | Approved | DAVID FEILER |
| Final | 4/13/2021 | Corrections Issued | EUGENE CASSIDY |
| Service/Power Release | 4/13/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| Service/Power Release | 6/14/2021 | Corrections Issued | EUGENE CASSIDY |
| ELECTRICAL-Final | 6/16/2021 | Approved | EUGENE CASSIDY |
| Final | 6/16/2021 | OK to Issue CofO | EUGENE CASSIDY |
| PLUMBING-Final | 6/16/2021 | Approved | EUGENE CASSIDY |
| Service/Power Release | 6/16/2021 | Approved | EUGENE CASSIDY |