5805 N CLEON AVE 91601

Certificate Information: 5805 N CLEON AVE 91601

Application / Permit
19010-20000-02785
Plan Check / Job No.
B19VN10810
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 46'7" X 35'6" 2 STORY' SFD WITH 18' X 18' ONE CAR GARAGE AND WITH 20'6" X 6' OPEN TRELLIS, NFPA-13D FIRE SPRINKLERS REQUIRED , ALL WORK PER ENGINEERING
Permit Issued
Issued on 2/26/2020
Issuing Office
Valley
Current Status
CofO Issued on 11/6/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/28/2019 APPLICANT
Green Plans Picked Up 7/10/2019 APPLICANT
Assigned to Plan Check Engineer 7/18/2019 RARES BODEA
Corrections Issued 7/21/2019 RARES BODEA
Quality Review Completed 7/24/2019 OMID HEDAYAT
Building Plans Picked Up 7/26/2019 APPLICANT
Applicant returned to address corrections 9/20/2019 RARES BODEA
Plan Check Approved 1/24/2020 RARES BODEA
Issued 2/26/2020 LADBS
CofO in Progress 11/4/2021 MICHAEL PELHAM
Permit Finaled 11/6/2021 MICHAEL SMITH
CofO Issued 11/6/2021 MICHAEL SMITH
Permit Finaled 11/6/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 8/26/2019 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 8/26/2019 GABRIEL ROBLES
Permit Cleared 8/26/2019 GABRIEL ROBLES
Sewer availability Cleared 8/26/2019 GABRIEL ROBLES
Hydrant and Access approval Cleared 8/27/2019 GEORGE SUCHAND
Trees in Parkway Cleared 8/28/2019 JOHN KIM
Low Impact Development Cleared 9/9/2019 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 9/9/2019 ELENA LOPEZ
Green Code Cleared 9/13/2019 PARISA ZAHABI
Miscellaneous Cleared 9/24/2019 GABRIEL ROBLES

Contact Information

Contractor Orantes Builders Inc; Lic. No.: 1011856-B 225 E 12TH ST   #9    LOS ANGELES, CA 90015
Engineer Wang,, Hongyu; Lic. No.: C72679 6270 MCLEOD DR STE 140      LAS VEGAS, NV 89120

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 4/3/2020 Approved RAYMOND KEHOE
Footing/Foundation/Slab 4/17/2020 No Access for Inspection RAYMOND KEHOE
Floor/Roof Diaphrgm/Shear Wall 5/12/2020 Approved DANIEL ORRANTE
Posting Pre-Inspection 6/3/2020 Partial Inspection MISAEL ESPARZA
Sewer 6/3/2020 Partial Inspection MISAEL ESPARZA
Grounding or Bonding 6/10/2020 Not Ready for Inspection JOHN HAYES
Posting Pre-Inspection 6/10/2020 Not Ready for Inspection JOHN HAYES
Special/Order Compliance 6/10/2020 Not Ready for Inspection JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 6/26/2020 Partial Approval RAYMOND KEHOE
ELECTRICAL-Rough 7/8/2020 Not Ready for Inspection BEAU COLLINS
HVAC-Rough 7/8/2020 Not Ready for Inspection BEAU COLLINS
PLUMBING-Rough 7/8/2020 Not Ready for Inspection BEAU COLLINS
Posting Pre-Inspection 7/8/2020 Approved BEAU COLLINS
Rough-Elec/Plmb/HVAC 7/8/2020 Corrections Issued BEAU COLLINS
Shower Pan 7/8/2020 Not Ready for Inspection BEAU COLLINS
Verify Sprinkler Sign Off 7/8/2020 Not Ready for Inspection BEAU COLLINS
Wood Frame 7/8/2020 Not Ready for Inspection BEAU COLLINS
ELECTRICAL-Rough 7/30/2020 Approved RAYMOND KEHOE
PLUMBING-Rough 7/30/2020 Approved RAYMOND KEHOE
Rough-Elec/Plmb/HVAC 7/30/2020 Approved RAYMOND KEHOE
Sewer 7/31/2020 Approved RAYMOND KEHOE
PLUMBING-Rough 8/13/2020 Approved BEAU COLLINS
Sewer 8/13/2020 Approved BEAU COLLINS
BUILDING-Rough-Frame 10/9/2020 Not Ready for Inspection DANIEL DREW
Green Building Rough 10/9/2020 Corrections Issued DANIEL DREW
Interior/Exterior Lathing 10/9/2020 Not Ready for Inspection DANIEL DREW
Verify Sprinkler Sign Off 10/9/2020 Approved DANIEL DREW
Insulation 10/15/2020 Not Ready for Inspection DANIEL DREW
Interior/Exterior Lathing 10/15/2020 Approved DANIEL DREW
Insulation 10/21/2020 Approved DANIEL DREW
Drywall Nailing 10/26/2020 Approved DANIEL ORRANTE
Green Building Rough 10/26/2020 Approved DANIEL ORRANTE
Pre-Inspection 11/6/2020 Approved DANIEL DREW
ELECTRICAL-Final 11/20/2020 Not Ready for Inspection DANIEL DREW
Gas Test 1/13/2021 Not Ready for Inspection DANIEL DREW
Service/Power Release 1/13/2021 Not Ready for Inspection DANIEL DREW
PLUMBING-Final 2/11/2021 Approved DANIEL DREW
ELECTRICAL-Final 2/16/2021 Corrections Issued DANIEL DREW
ELECTRICAL-Final 2/22/2021 Approved DANIEL DREW
Service/Power Release 2/22/2021 Not Ready for Inspection DANIEL DREW
HVAC-Final 2/25/2021 Conditional Approval DANIEL DREW
Service/Power Release 4/8/2021 Not Ready for Inspection DANIEL DREW
BUILDING-Rough-Frame 8/10/2021 Approved DANIEL DREW
Final 8/10/2021 Corrections Issued DANIEL DREW
Footing/Foundation/Slab 8/10/2021 Approved DANIEL DREW
Green Building Final 8/10/2021 No Access for Inspection DANIEL DREW
SGSOV-Seismic Gas S/O Valve 8/10/2021 SGSOV Not Ready DANIEL DREW
Service/Power Release 8/10/2021 Not Ready for Inspection DANIEL DREW
Smoke Detectors 8/10/2021 Approved DANIEL DREW
Final 9/29/2021 Corrections Issued DANIEL DREW
Green Building Final 9/29/2021 Approved DANIEL DREW
SGSOV-Seismic Gas S/O Valve 9/29/2021 SGSOV Approved DANIEL DREW
Service/Power Release 9/29/2021 Not Ready for Inspection DANIEL DREW
Final 10/6/2021 Not Ready for Inspection DANIEL DREW
Service/Power Release 10/6/2021 Not Ready for Inspection DANIEL DREW
HVAC-Final 10/8/2021 Approved DANIEL DREW
Final 10/18/2021 Corrections Issued DANIEL DREW
Service/Power Release 10/18/2021 Approved DANIEL DREW
Final 11/4/2021 OK to Issue CofO MICHAEL PELHAM