Excavation/Setback/Form/Re-Bar
|
2/14/2024
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Footing/Foundation/Slab
|
2/15/2024
|
Corrections Issued
|
JEFFREY FULTON
|
|
Footing/Foundation/Slab
|
2/23/2024
|
Corrections Issued
|
JEFFREY FULTON
|
|
Footing/Foundation/Slab
|
2/29/2024
|
Partial Approval
|
GREGORY POMISH
|
|
Deputy Steel/Welding
|
3/7/2024
|
Conditional Approval
|
GREGORY POMISH
|
|
Footing/Foundation/Slab
|
3/21/2024
|
Corrections Issued
|
ROBERT DAVIS
|
|
Green Building Rough
|
3/21/2024
|
Not Ready for Inspection
|
ROBERT DAVIS
|
|
Structural Steel Frame
|
3/21/2024
|
Conditional Approval
|
ROBERT DAVIS
|
|
Verify Sprinkler Sign Off
|
3/21/2024
|
Not Ready for Inspection
|
ROBERT DAVIS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/20/2024
|
Not Ready for Inspection
|
GREGORY POMISH
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/29/2024
|
Partial Approval
|
GREGORY POMISH
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/24/2024
|
Partial Approval
|
GREGORY POMISH
|
|
Green Building Rough
|
6/24/2024
|
Approved
|
GREGORY POMISH
|
|
Structural Steel Frame
|
6/24/2024
|
Partial Inspection
|
GREGORY POMISH
|
|
Verify Sprinkler Sign Off
|
6/24/2024
|
Not Ready for Inspection
|
GREGORY POMISH
|
|
Wood Frame
|
6/24/2024
|
Partial Approval
|
GREGORY POMISH
|
|
Interior/Exterior Lathing
|
7/9/2024
|
Approved
|
GREGORY POMISH
|
|
Footing/Foundation/Slab
|
10/17/2024
|
Not Ready for Inspection
|
GREGORY POMISH
|
|
Footing/Foundation/Slab
|
10/18/2024
|
Partial Approval
|
GREGORY POMISH
|
|
Excavation/Setback/Form/Re-Bar
|
10/29/2024
|
Partial Approval
|
GREGORY POMISH
|
|
Masonry Wall/Backfill
|
10/29/2024
|
Partial Approval
|
GREGORY POMISH
|
|
Interior/Exterior Lathing
|
11/13/2024
|
Approved
|
GREGORY POMISH
|
|
Verify Sprinkler Sign Off
|
12/18/2024
|
Partial Inspection
|
GREGORY POMISH
|
|
Wood Frame
|
12/18/2024
|
Partial Approval
|
GREGORY POMISH
|
|
Drywall Nailing
|
12/26/2024
|
Not Ready for Inspection
|
GREGORY POMISH
|
|
Insulation
|
1/10/2025
|
Approved
|
GREGORY POMISH
|
|
Drywall Nailing
|
1/27/2025
|
Approved
|
GREGORY POMISH
|
|
Pre-Inspection
|
2/19/2025
|
Not Ready for Inspection
|
GREGORY POMISH
|
|
T-Bar Ceiling
|
3/11/2025
|
Not Ready for Inspection
|
GREGORY POMISH
|
|
T-Bar Ceiling
|
3/27/2025
|
Not Ready for Inspection
|
GREGORY POMISH
|
|
Footing/Foundation/Slab
|
3/28/2025
|
Partial Inspection
|
ROBERT DAVIS
|
|
Reinforced Concrete Frame
|
3/28/2025
|
Not Ready for Inspection
|
ROBERT DAVIS
|
|
T-Bar Ceiling
|
4/15/2025
|
Approved
|
GREGORY POMISH
|
|
Footing/Foundation/Slab
|
4/28/2025
|
Corrections Issued
|
DANNY RODRIGUEZ
|
|
Masonry Wall/Backfill
|
4/30/2025
|
Partial Approval
|
GREGORY POMISH
|
|
Excavation/Setback/Form/Re-Bar
|
5/22/2025
|
Partial Inspection
|
GREGORY POMISH
|
|
Footing/Foundation/Slab
|
5/28/2025
|
Partial Approval
|
GREGORY POMISH
|
|
Reinforced Concrete Frame
|
5/28/2025
|
Partial Inspection
|
GREGORY POMISH
|
|
Piling/Pier/Caisson
|
8/29/2025
|
Partial Approval
|
ROBERT DAVIS
|
|
Final
|
9/26/2025
|
Not Ready for Inspection
|
GREGORY POMISH
|
|
Footing/Foundation/Slab
|
9/26/2025
|
Not Ready for Inspection
|
GREGORY POMISH
|
|
Grading Pre-Inspection
|
9/26/2025
|
Not Ready for Inspection
|
GREGORY POMISH
|
|
Green Building Final
|
9/26/2025
|
Not Ready for Inspection
|
GREGORY POMISH
|
|
Posting Pre-Inspection
|
9/26/2025
|
Not Ready for Inspection
|
GREGORY POMISH
|
|
SGSOV-Seismic Gas S/O Valve
|
9/26/2025
|
SGSOV Not Ready
|
GREGORY POMISH
|
|
Smoke Detectors
|
9/26/2025
|
Not Ready for Inspection
|
GREGORY POMISH
|
|
Structural Steel Frame
|
9/26/2025
|
Not Ready for Inspection
|
GREGORY POMISH
|
|
Verify Sprinkler Sign Off
|
9/26/2025
|
Not Ready for Inspection
|
GREGORY POMISH
|
|
Wood Frame
|
9/26/2025
|
Not Ready for Inspection
|
GREGORY POMISH
|
|
Final
|
11/4/2025
|
Not Ready for Inspection
|
GREGORY POMISH
|
|
Footing/Foundation/Slab
|
11/4/2025
|
Partial Inspection
|
GREGORY POMISH
|
|
Green Building Final
|
11/4/2025
|
Not Ready for Inspection
|
GREGORY POMISH
|
|
SGSOV-Seismic Gas S/O Valve
|
11/4/2025
|
SGSOV Not Ready
|
GREGORY POMISH
|
|
Smoke Detectors
|
11/4/2025
|
Not Ready for Inspection
|
GREGORY POMISH
|
|
Structural Steel Frame
|
11/4/2025
|
Not Ready for Inspection
|
GREGORY POMISH
|
|
Verify Rec and Parks Fee Memo
|
11/4/2025
|
Approved
|
GREGORY POMISH
|
|
Verify Sprinkler Sign Off
|
11/4/2025
|
Not Ready for Inspection
|
GREGORY POMISH
|
|
Wood Frame
|
11/4/2025
|
Not Ready for Inspection
|
GREGORY POMISH
|
|
Final
|
11/13/2025
|
Not Ready for Inspection
|
GREGORY POMISH
|
|
Footing/Foundation/Slab
|
11/13/2025
|
Approved
|
GREGORY POMISH
|
|
Green Building Final
|
11/13/2025
|
Not Ready for Inspection
|
GREGORY POMISH
|
|
SGSOV-Seismic Gas S/O Valve
|
11/13/2025
|
SGSOV Not Ready
|
GREGORY POMISH
|
|
Smoke Detectors
|
11/13/2025
|
Not Ready for Inspection
|
GREGORY POMISH
|
|
Structural Steel Frame
|
11/13/2025
|
Partial Inspection
|
GREGORY POMISH
|
|
Verify Rec and Parks Fee Memo
|
11/13/2025
|
Approved
|
GREGORY POMISH
|
|
Verify Sprinkler Sign Off
|
11/13/2025
|
Partial Inspection
|
GREGORY POMISH
|
|
Wood Frame
|
11/13/2025
|
Partial Inspection
|
GREGORY POMISH
|
|
Pre-Inspection
|
11/18/2025
|
Not Ready for Inspection
|
GREGORY POMISH
|
|
Final
|
3/23/2026
|
OK to Issue CofO
|
GREGORY POMISH
|
|
Green Building Final
|
3/23/2026
|
Approved
|
GREGORY POMISH
|
|
SGSOV-Seismic Gas S/O Valve
|
3/23/2026
|
SGSOV No Gas
|
GREGORY POMISH
|
|
Smoke Detectors
|
3/23/2026
|
Approved
|
GREGORY POMISH
|
|
Structural Steel Frame
|
3/23/2026
|
Approved
|
GREGORY POMISH
|
|
Verify Sprinkler Sign Off
|
3/23/2026
|
Approved
|
GREGORY POMISH
|
|
Wood Frame
|
3/23/2026
|
Approved
|
GREGORY POMISH
|