16801 W DEVONSHIRE ST 100-101 91344

Certificate Information: 16801 W DEVONSHIRE ST 100-101 91344

Application / Permit
19010-20000-02720
Plan Check / Job No.
B19VN10539
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(16) Pharmacy prescription
Work Description
(N) 56'-9" x 51'-9" Irregular shape One-Story Doctor's Office & Pharmacy prescription, Type VB Construction.
Permit Issued
Issued on 10/20/2023
Issuing Office
Valley
Current Status
CofO Issued on 3/24/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/25/2019 APPLICANT
Assigned to Plan Check Engineer 7/18/2019 OMID HEDAYAT
Disabled Access Plans Picked Up 7/23/2019 APPLICANT
Green Plans Picked Up 7/23/2019 APPLICANT
Corrections Issued 7/25/2019 OMID HEDAYAT
Quality Review Completed 7/26/2019 STEVEN KIM
Building Plans Picked Up 8/1/2019 APPLICANT
Applicant returned to address corrections 4/14/2023 OMID HEDAYAT
Plan Check Approved 8/9/2023 SELLA BENYAMIN
Issued 10/20/2023 APPLICANT
CofO in Progress 3/24/2026 GREGORY POMISH
Permit Finaled 3/24/2026 JEFFREY DURAN
CofO Issued 3/24/2026 JEFFREY DURAN
Permit Finaled 3/24/2026 JEFFREY DURAN

Permit Application Clearance Information

Address approval Cleared 9/6/2019 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 9/6/2019 GUILLERMO PETRA
Hydrant and Access approval Cleared 9/6/2019 GEORGE SUCHAND
Sewer availability Cleared 9/6/2019 GUILLERMO PETRA
ZA Case Cleared 9/6/2019 HERMINIGILDO AGUSTIN
DAS Clearance Cleared 6/2/2022 NORLITO MEDRANO
Green Code Cleared 6/7/2022 MICHAEL AYERS
Highway dedication Cleared 8/26/2022 DAGOVERTO GUERRERO
Highway dedication Cleared 8/26/2022 DAGOVERTO GUERRERO
Permit Cleared 8/26/2022 DAGOVERTO GUERRERO
Low Impact Development Cleared 9/29/2022 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 1/5/2023 CARLOS AGUILERA
Comm Cor/Mini-Mall Cleared 3/2/2023 BRENNEN OBETO
Comm Cor/Mini-Mall Cleared 3/2/2023 BRENNEN OBETO
Specific Plan Cleared 3/2/2023 BRENNEN OBETO

Contact Information

Architect Elliott,, Bert Michael; Lic. No.: C8623 16421 WIMBLEDON LANE      HUNTINGTON BEACH, CA 92649
Contractor Ec1 Builders Inc; Lic. No.: 1075811-B 8040 DEERING AVE #4      CANOGA PARK, CA 91304
Engineer Skudlarski,, Jason James; Lic. No.: C67712 9751 OLYMPIC DR      HUNTINGTON BEACH, CA 92646

Inspector Information

GREGORY POMISH, (818) 374-3303 Office Hours: 7:00-8:00 AM MON-FRI
EDWIN GREGORYONA, (818) 374-3303 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/14/2024 Not Ready for Inspection JEFFREY FULTON
Footing/Foundation/Slab 2/15/2024 Corrections Issued JEFFREY FULTON
Footing/Foundation/Slab 2/23/2024 Corrections Issued JEFFREY FULTON
Footing/Foundation/Slab 2/29/2024 Partial Approval GREGORY POMISH
Deputy Steel/Welding 3/7/2024 Conditional Approval GREGORY POMISH
Footing/Foundation/Slab 3/21/2024 Corrections Issued ROBERT DAVIS
Green Building Rough 3/21/2024 Not Ready for Inspection ROBERT DAVIS
Structural Steel Frame 3/21/2024 Conditional Approval ROBERT DAVIS
Verify Sprinkler Sign Off 3/21/2024 Not Ready for Inspection ROBERT DAVIS
Floor/Roof Diaphrgm/Shear Wall 5/20/2024 Not Ready for Inspection GREGORY POMISH
Floor/Roof Diaphrgm/Shear Wall 5/29/2024 Partial Approval GREGORY POMISH
Floor/Roof Diaphrgm/Shear Wall 6/24/2024 Partial Approval GREGORY POMISH
Green Building Rough 6/24/2024 Approved GREGORY POMISH
Structural Steel Frame 6/24/2024 Partial Inspection GREGORY POMISH
Verify Sprinkler Sign Off 6/24/2024 Not Ready for Inspection GREGORY POMISH
Wood Frame 6/24/2024 Partial Approval GREGORY POMISH
Interior/Exterior Lathing 7/9/2024 Approved GREGORY POMISH
Footing/Foundation/Slab 10/17/2024 Not Ready for Inspection GREGORY POMISH
Footing/Foundation/Slab 10/18/2024 Partial Approval GREGORY POMISH
Excavation/Setback/Form/Re-Bar 10/29/2024 Partial Approval GREGORY POMISH
Masonry Wall/Backfill 10/29/2024 Partial Approval GREGORY POMISH
Interior/Exterior Lathing 11/13/2024 Approved GREGORY POMISH
Verify Sprinkler Sign Off 12/18/2024 Partial Inspection GREGORY POMISH
Wood Frame 12/18/2024 Partial Approval GREGORY POMISH
Drywall Nailing 12/26/2024 Not Ready for Inspection GREGORY POMISH
Insulation 1/10/2025 Approved GREGORY POMISH
Drywall Nailing 1/27/2025 Approved GREGORY POMISH
Pre-Inspection 2/19/2025 Not Ready for Inspection GREGORY POMISH
T-Bar Ceiling 3/11/2025 Not Ready for Inspection GREGORY POMISH
T-Bar Ceiling 3/27/2025 Not Ready for Inspection GREGORY POMISH
Footing/Foundation/Slab 3/28/2025 Partial Inspection ROBERT DAVIS
Reinforced Concrete Frame 3/28/2025 Not Ready for Inspection ROBERT DAVIS
T-Bar Ceiling 4/15/2025 Approved GREGORY POMISH
Footing/Foundation/Slab 4/28/2025 Corrections Issued DANNY RODRIGUEZ
Masonry Wall/Backfill 4/30/2025 Partial Approval GREGORY POMISH
Excavation/Setback/Form/Re-Bar 5/22/2025 Partial Inspection GREGORY POMISH
Footing/Foundation/Slab 5/28/2025 Partial Approval GREGORY POMISH
Reinforced Concrete Frame 5/28/2025 Partial Inspection GREGORY POMISH
Piling/Pier/Caisson 8/29/2025 Partial Approval ROBERT DAVIS
Final 9/26/2025 Not Ready for Inspection GREGORY POMISH
Footing/Foundation/Slab 9/26/2025 Not Ready for Inspection GREGORY POMISH
Grading Pre-Inspection 9/26/2025 Not Ready for Inspection GREGORY POMISH
Green Building Final 9/26/2025 Not Ready for Inspection GREGORY POMISH
Posting Pre-Inspection 9/26/2025 Not Ready for Inspection GREGORY POMISH
SGSOV-Seismic Gas S/O Valve 9/26/2025 SGSOV Not Ready GREGORY POMISH
Smoke Detectors 9/26/2025 Not Ready for Inspection GREGORY POMISH
Structural Steel Frame 9/26/2025 Not Ready for Inspection GREGORY POMISH
Verify Sprinkler Sign Off 9/26/2025 Not Ready for Inspection GREGORY POMISH
Wood Frame 9/26/2025 Not Ready for Inspection GREGORY POMISH
Final 11/4/2025 Not Ready for Inspection GREGORY POMISH
Footing/Foundation/Slab 11/4/2025 Partial Inspection GREGORY POMISH
Green Building Final 11/4/2025 Not Ready for Inspection GREGORY POMISH
SGSOV-Seismic Gas S/O Valve 11/4/2025 SGSOV Not Ready GREGORY POMISH
Smoke Detectors 11/4/2025 Not Ready for Inspection GREGORY POMISH
Structural Steel Frame 11/4/2025 Not Ready for Inspection GREGORY POMISH
Verify Rec and Parks Fee Memo 11/4/2025 Approved GREGORY POMISH
Verify Sprinkler Sign Off 11/4/2025 Not Ready for Inspection GREGORY POMISH
Wood Frame 11/4/2025 Not Ready for Inspection GREGORY POMISH
Final 11/13/2025 Not Ready for Inspection GREGORY POMISH
Footing/Foundation/Slab 11/13/2025 Approved GREGORY POMISH
Green Building Final 11/13/2025 Not Ready for Inspection GREGORY POMISH
SGSOV-Seismic Gas S/O Valve 11/13/2025 SGSOV Not Ready GREGORY POMISH
Smoke Detectors 11/13/2025 Not Ready for Inspection GREGORY POMISH
Structural Steel Frame 11/13/2025 Partial Inspection GREGORY POMISH
Verify Rec and Parks Fee Memo 11/13/2025 Approved GREGORY POMISH
Verify Sprinkler Sign Off 11/13/2025 Partial Inspection GREGORY POMISH
Wood Frame 11/13/2025 Partial Inspection GREGORY POMISH
Pre-Inspection 11/18/2025 Not Ready for Inspection GREGORY POMISH
Final 3/23/2026 OK to Issue CofO GREGORY POMISH
Green Building Final 3/23/2026 Approved GREGORY POMISH
SGSOV-Seismic Gas S/O Valve 3/23/2026 SGSOV No Gas GREGORY POMISH
Smoke Detectors 3/23/2026 Approved GREGORY POMISH
Structural Steel Frame 3/23/2026 Approved GREGORY POMISH
Verify Sprinkler Sign Off 3/23/2026 Approved GREGORY POMISH
Wood Frame 3/23/2026 Approved GREGORY POMISH