19545 W SAN JOSE ST 91326
Certificate Information: 19545 W SAN JOSE ST 91326
- Application / Permit
- 19010-20000-02685
- Plan Check / Job No.
- B19VN10384
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSE 30'X40' ONES STORY ACCESSORY DWELLING UNIT PER AB 494 & SB 229 _ BUILDING SHALL BE FULLY SPRINKLER THROUGH OUT WITH NFPA 13D_ TYPE VA CONSTRUCTION [SEE COMMENTS]. "COMPLY WITH DEPARTMENT ORDER effective date 05/22/2019. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
- Permit Issued
- Issued on 6/24/2022
- Issuing Office
- Current Status
- CofO Issued on 11/14/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/21/2019 | APPLICANT |
| Green Plans Picked Up | 7/29/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 8/1/2019 | DAWN MC NULTY |
| Corrections Issued | 8/5/2019 | DAWN MC NULTY |
| Quality Review Completed | 8/9/2019 | CHON CHIO KUO |
| Building Plans Picked Up | 8/13/2019 | APPLICANT |
| Applicant returned to address corrections | 11/12/2019 | DAWN MC NULTY |
| Plan Check Approved | 12/17/2019 | DAWN MC NULTY |
| Issued | 6/24/2022 | APPLICANT |
| Permit Finaled | 11/14/2025 | DAVID JAMES |
| CofO Issued | 11/14/2025 | DAVID JAMES |
| Permit Finaled | 11/14/2025 | DAVID JAMES |
Permit Application Clearance Information
| Address approval | Cleared | 9/23/2019 | ADRIAN CASTRO |
| BHO/Hillside ordinance | Cleared | 9/23/2019 | ADRIAN CASTRO |
| BHO/Hillside ordinance | Cleared | 9/23/2019 | ADRIAN CASTRO |
| BHO/Hillside ordinance | Cleared | 9/23/2019 | ADRIAN CASTRO |
| Permit | Cleared | 9/23/2019 | ADRIAN CASTRO |
| Green Code | Cleared | 10/22/2019 | MICHAEL AYERS |
| Construction near power lines | Cleared | 11/3/2019 | RIDWAN HARDY |
| Low Impact Development | Cleared | 11/5/2019 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 11/12/2019 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 11/13/2019 | ROSE MARIE SMITH |
| Sewer availability | Cleared | 11/13/2019 | ROSE MARIE SMITH |
| Hydrant and Access approval | Cleared | 12/2/2019 | JEREMY CARTER |
| GPI Written Notices | Cleared | 12/17/2019 | DAWN MC NULTY |
| Grading Pre-Inspection | Cleared | 12/17/2019 | DAWN MC NULTY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Moradian,, Helbert; Lic. No.: C76618 | 6944 BECKETT STREET TUJUNGA, CA 91042 |
Inspector Information
| ARA SINANIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HASANTHA WEERASEKARA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| SCOTT SHUSTER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOEL GUARDADO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIYA MIHALEVA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOSE RUBIO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID JAMES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID HICKMAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN HAMILTON, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN STEPHENS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| PIERRE VEGA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK VAN SLOOTEN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MICKEY YAMASHITA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RICHARD ROBLES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HAGOP BADOSSIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM BEAUCHAMP, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK DOVICO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| THOMAS WOODS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL VASQUEZ, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| AUGUSTUS ALBAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| FELIPE PENICHE, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| LEO MILBAUER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/21/2022 | Approved | JOHN STEPHENS |
| Pre-Inspection | 10/5/2022 | Approved | JOHN STEPHENS |
| PLUMBING-Rough | 1/11/2023 | Corrections Issued | JOHN STEPHENS |
| PLUMBING-Rough | 1/25/2023 | Partial Approval | JOHN STEPHENS |
| Footing/Foundation/Slab | 1/27/2023 | Approved | JOHN STEPHENS |
| BUILDING-Rough-Frame | 6/20/2023 | No Access for Inspection | MARK DOVICO |
| Green Building Rough | 6/20/2023 | No Access for Inspection | MARK DOVICO |
| Verify Sprinkler Sign Off | 6/20/2023 | No Access for Inspection | MARK DOVICO |
| ELECTRICAL-Rough | 7/19/2023 | Corrections Issued | MARK DOVICO |
| PLUMBING-Rough | 7/19/2023 | Approved | MARK DOVICO |
| ELECTRICAL-Rough | 8/9/2023 | Corrections Issued | MARIO CUEVAS |
| HVAC-Rough | 8/9/2023 | Not Ready for Inspection | MARIO CUEVAS |
| PLUMBING-Rough | 8/9/2023 | Corrections Issued | MARIO CUEVAS |
| ELECTRICAL-Rough | 9/19/2023 | Approved | GARY PARKER |
| HVAC-Rough | 9/19/2023 | Approved | GARY PARKER |
| PLUMBING-Rough | 9/19/2023 | Approved | GARY PARKER |
| Interior/Exterior Lathing | 10/20/2023 | Corrections Issued | GARY PARKER |
| Verify Sprinkler Sign Off | 10/23/2023 | Corrections Issued | GARY PARKER |
| BUILDING-Rough-Frame | 11/16/2023 | Corrections Issued | PIERRE VEGA |
| Green Building Rough | 11/16/2023 | Approved | PIERRE VEGA |
| Verify Sprinkler Sign Off | 11/16/2023 | Partial Approval | PIERRE VEGA |
| BUILDING-Rough-Frame | 12/7/2023 | Not Ready for Inspection | GARY PARKER |
| Verify Sprinkler Sign Off | 12/7/2023 | Not Ready for Inspection | GARY PARKER |
| Drywall Nailing | 3/27/2024 | Approved | GARY PARKER |
| Shower Pan | 4/23/2024 | Approved | ARA SINANIAN |
| Interior/Exterior Lathing | 5/7/2024 | Approved | ARA SINANIAN |
| Underground Mechanical | 5/10/2024 | Approved | ARA SINANIAN |
| ELECTRICAL-Rough | 9/19/2024 | Approved | ARA SINANIAN |
| BUILDING-Rough-Frame | 12/4/2024 | Approved | MARK DOVICO |
| ELECTRICAL-Final | 12/4/2024 | Approved | MARK DOVICO |
| Final | 12/4/2024 | Conditional Approval | MARK DOVICO |
| Green Building Final | 12/4/2024 | Approved | MARK DOVICO |
| HVAC-Rough | 12/4/2024 | Approved | MARK DOVICO |
| SGSOV-Seismic Gas S/O Valve | 12/4/2024 | SGSOV Approved | MARK DOVICO |
| Service/Power Release | 12/4/2024 | Approved | MARK DOVICO |
| Smoke Detectors | 12/4/2024 | Approved | MARK DOVICO |
| Verify Sprinkler Sign Off | 12/4/2024 | Approved | MARK DOVICO |
| Final | 5/27/2025 | Conditional Approval | ARA SINANIAN |
| Final | 11/6/2025 | Conditional Approval | MARK VAN SLOOTEN |