5211 E MARMION WAY 90042
Certificate Information: 5211 E MARMION WAY 90042
- Application / Permit
- 19010-20000-02624
- Plan Check / Job No.
- B19VN10187
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (61) Use of Land
- Work Description
- PROPOSED USE OF LAND FOR STRIPING OF PARKING STALLS PER PLAN. SEE COMMENTS.
- Permit Issued
- Issued on 4/26/2021
- Issuing Office
- Current Status
- CofO Issued on 2/16/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/18/2019 | APPLICANT |
| Green Plans Picked Up | 7/1/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 7/11/2019 | HAYATO TSUCHIYA |
| Corrections Issued | 7/15/2019 | HAYATO TSUCHIYA |
| Quality Review Completed | 7/16/2019 | ABDUL CHEGENI |
| Building Plans Picked Up | 7/18/2019 | APPLICANT |
| Applicant returned to address corrections | 6/15/2020 | HAYATO TSUCHIYA |
| Plan Check Approved | 8/7/2020 | HAYATO TSUCHIYA |
| Issued | 4/26/2021 | APPLICANT |
| CofO in Progress | 3/15/2022 | SCOTT FINNILA |
| Permit Finaled | 2/16/2023 | DANIEL ORRANTE |
| CofO Issued | 2/16/2023 | DANIEL ORRANTE |
| Permit Finaled | 2/16/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/28/2019 | JOSHUA DIAZ |
| Specific Plan | Cleared | 8/28/2019 | MOHAMMAD HASAN |
| Metro Rail approval | Cleared | 9/4/2019 | HAYATO TSUCHIYA |
| Low Impact Development | Cleared | 9/11/2019 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 9/12/2019 | GUILLERMO PETRA |
| Green Code | Cleared | 10/3/2019 | DAVID MATSON |
| HPOZ | Cleared | 5/13/2020 | KATIE DEBIASE |
| ZI | Cleared | 5/13/2020 | KATIE DEBIASE |
| ZI | Cleared | 7/17/2020 | ADRINEH MELKONIAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Kardjian,, Vahe Matios; Lic. No.: C40821 | 1648 W GLENOAKS BLVD STE 102 GLENDALE, CA 91201 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Final | 3/4/2022 | Not Ready for Inspection | COREY HUPP |
| Green Building Final | 3/4/2022 | Not Ready for Inspection | COREY HUPP |
| Final | 3/9/2022 | Corrections Issued | SCOTT FINNILA |
| Green Building Final | 3/9/2022 | Approved | SCOTT FINNILA |
| Final | 3/11/2022 | Partial Approval | SCOTT FINNILA |
| Final | 3/14/2022 | OK to Issue CofO | SCOTT FINNILA |