4702 E BALTIMORE ST 90042
Certificate Information: 4702 E BALTIMORE ST 90042
- Application / Permit
- 19010-20000-02618
- Plan Check / Job No.
- B19VN10148
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 14' X 29' ACCESSORY DWELLING UNIT W/ STORAGE ABOVE PER AB 494 AND SB 229. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 2/12/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/20/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/18/2019 | APPLICANT |
| Green Plans Picked Up | 7/2/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 7/11/2019 | JENNIFER LEE |
| Corrections Issued | 7/16/2019 | JENNIFER LEE |
| Quality Review Completed | 7/17/2019 | STEVEN KIM |
| Building Plans Picked Up | 7/25/2019 | APPLICANT |
| Plan Check Approved | 2/12/2020 | JENNIFER LEE |
| Issued | 2/12/2020 | LADBS |
| CofO in Progress | 9/28/2020 | HAMIK HARTOUNIAN |
| Permit Finaled | 11/20/2020 | DEROLD HAUFF |
| CofO Issued | 11/20/2020 | DEROLD HAUFF |
| Permit Finaled | 11/20/2020 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 1/28/2020 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 1/28/2020 | GABRIEL ROBLES |
| Green Code | Cleared | 1/28/2020 | DAVID MATSON |
| Hydrant and Access approval | Cleared | 1/28/2020 | GEORGE SUCHAND |
| Roof/Waste drainage to street | Cleared | 1/28/2020 | GABRIEL ROBLES |
| Sewer availability | Cleared | 1/28/2020 | GABRIEL ROBLES |
| Grading Pre-Inspection | Cleared | 2/5/2020 | JENNIFER LEE |
Contact Information
| Contractor | Espana Builders; Lic. No.: 1002026-B | 6701 ETON AVE #104 WOODLAND HILLS, CA 91303 |
| Engineer | Chiu,, Ivan Wai-Kuen; Lic. No.: C44672 | 2160 PARNELL WY ALTADENA, CA 91001 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/18/2020 | Approved | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 2/25/2020 | Approved | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 2/25/2020 | Approved | HAMIK HARTOUNIAN |
| Pre-Inspection | 2/25/2020 | Approved | HAMIK HARTOUNIAN |
| Underground Mechanical | 2/25/2020 | Partial Approval | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/23/2020 | Corrections Issued | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 5/13/2020 | Conditional Approval | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 5/20/2020 | Approved | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/20/2020 | Partial Approval | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 5/20/2020 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 5/26/2020 | Conditional Approval | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/26/2020 | Partial Approval | HAMIK HARTOUNIAN |
| Green Building Rough | 5/26/2020 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 5/26/2020 | Partial Approval | HAMIK HARTOUNIAN |
| Shower Pan | 5/26/2020 | Approved | HAMIK HARTOUNIAN |
| Verify Sprinkler Sign Off | 5/26/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 5/27/2020 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| Insulation | 5/28/2020 | Approved | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 6/2/2020 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 6/2/2020 | Approved | HAMIK HARTOUNIAN |
| Sewer | 6/18/2020 | Corrections Issued | HAMIK HARTOUNIAN |
| Underground Mechanical | 6/18/2020 | Conditional Approval | HAMIK HARTOUNIAN |
| Sewer | 6/23/2020 | Approved | HAMIK HARTOUNIAN |
| Underground Mechanical | 6/23/2020 | Approved | HAMIK HARTOUNIAN |
| ELECTRICAL-Final | 9/3/2020 | Approved | HAMIK HARTOUNIAN |
| HVAC-Final | 9/3/2020 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Final | 9/3/2020 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 9/22/2020 | Approved | HAMIK HARTOUNIAN |
| Final | 9/22/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Green Building Final | 9/22/2020 | Approved | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 9/22/2020 | SGSOV Not Ready | HAMIK HARTOUNIAN |
| Service/Power Release | 9/22/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Smoke Detectors | 9/22/2020 | Approved | HAMIK HARTOUNIAN |
| Verify Sprinkler Sign Off | 9/22/2020 | Approved | HAMIK HARTOUNIAN |
| Final | 9/28/2020 | OK to Issue CofO | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 9/28/2020 | SGSOV Approved | HAMIK HARTOUNIAN |
| Service/Power Release | 9/28/2020 | Approved | HAMIK HARTOUNIAN |