6942 N COLBATH AVE 91405
Certificate Information: 6942 N COLBATH AVE 91405
- Application / Permit
- 19010-20000-02580
- Plan Check / Job No.
- B19VN09960
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 1-STORY ACCESSORY DWELLING UNIT (23'-11" X 46'-6") PER AB494 & SB229
- Permit Issued
- Issued on 9/30/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/17/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/14/2019 | APPLICANT |
| Green Plans Picked Up | 6/27/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 7/3/2019 | NILOOFAR MEHRAIN |
| Corrections Issued | 7/5/2019 | NILOOFAR MEHRAIN |
| Quality Review Completed | 7/8/2019 | CHON CHIO KUO |
| Building Plans Picked Up | 7/8/2019 | APPLICANT |
| Plan Check Approved | 9/30/2019 | NILOOFAR MEHRAIN |
| Issued | 9/30/2019 | LADBS |
| CofO in Progress | 11/16/2021 | RICHARD DOCKUS |
| CofO Issued | 12/17/2021 | MICHAEL SMITH |
| Permit Finaled | 12/17/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Construction near power lines | Cleared | 9/10/2019 | RIDWAN HARDY |
| Construction within easement | Cleared | 9/10/2019 | RIDWAN HARDY |
| Address approval | Cleared | 9/11/2019 | MARKOS PEREZ-BRAN |
| Low Impact Development | Cleared | 9/17/2019 | RYAN HUDSON |
| Eng Process Fee Ord 176,300 | Cleared | 9/19/2019 | GUILLERMO PETRA |
| Green Code | Cleared | 9/19/2019 | PARISA ZAHABI |
| Roof/Waste drainage to street | Cleared | 9/19/2019 | GUILLERMO PETRA |
| Sewer availability | Cleared | 9/19/2019 | GUILLERMO PETRA |
| Hydrant and Access approval | Cleared | 9/23/2019 | GILBERT URREA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/9/2019 | Approved | ARAM AVEDISIAN |
| PLUMBING-Rough | 12/24/2019 | Partial Approval | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 3/6/2020 | No Access for Inspection | MISAEL ESPARZA |
| Footing/Foundation/Slab | 3/11/2020 | Corrections Issued | MISAEL ESPARZA |
| Excavation/Setback/Form/Re-Bar | 3/16/2020 | Approved | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 8/31/2020 | Partial Inspection | WILLIAM KUEHN |
| BUILDING-Rough-Frame | 2/22/2021 | Corrections Issued | HENRY KIM |
| ELECTRICAL-Final | 2/22/2021 | Corrections Issued | HENRY KIM |
| ELECTRICAL-Rough | 2/22/2021 | Approved | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 2/22/2021 | Approved | HENRY KIM |
| Footing/Foundation/Slab | 2/22/2021 | Corrections Issued | HENRY KIM |
| Green Building Rough | 2/22/2021 | Not Ready for Inspection | HENRY KIM |
| HVAC-Rough | 2/22/2021 | Corrections Issued | HENRY KIM |
| PLUMBING-Rough | 2/22/2021 | Approved | HENRY KIM |
| Verify Sprinkler Sign Off | 2/22/2021 | Not Ready for Inspection | HENRY KIM |
| Insulation | 3/4/2021 | Not Ready for Inspection | JOHN HAYES |
| Interior/Exterior Lathing | 3/4/2021 | Partial Approval | JOHN HAYES |
| BUILDING-Rough-Frame | 3/11/2021 | Conditional Approval | MICHAEL TEMPLE |
| Green Building Rough | 3/11/2021 | Approved | MICHAEL TEMPLE |
| HVAC-Rough | 3/11/2021 | Approved | MICHAEL TEMPLE |
| Insulation | 3/11/2021 | Approved | MICHAEL TEMPLE |
| Pre-Inspection | 3/12/2021 | Corrections Issued | MICHAEL TEMPLE |
| Drywall Nailing | 3/19/2021 | Conditional Approval | RICHARD DOCKUS |
| Shower Pan | 4/19/2021 | Approved | DANIEL ORRANTE |
| Interior/Exterior Lathing | 5/26/2021 | Approved | JOHN HAYES |
| Sewer | 7/26/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Underground Mechanical | 7/26/2021 | Partial Approval | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 9/15/2021 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 9/15/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 9/15/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 9/15/2021 | Approved | JENNIFER RABUCHIN |
| Green Building Final | 9/15/2021 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 9/15/2021 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 9/15/2021 | SGSOV Approved | JENNIFER RABUCHIN |
| Service/Power Release | 9/15/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Smoke Detectors | 9/15/2021 | Approved | JENNIFER RABUCHIN |
| Final | 9/23/2021 | Not Ready for Inspection | RICHARD DOCKUS |
| Service/Power Release | 9/23/2021 | Corrections Issued | RICHARD DOCKUS |
| Final | 10/29/2021 | OK to Issue CofO | RICHARD DOCKUS |
| Service/Power Release | 10/29/2021 | Approved | RICHARD DOCKUS |