3950 N ROYAL OAK PL 91436

Certificate Information: 3950 N ROYAL OAK PL 91436

Application / Permit
19010-20000-02579
Plan Check / Job No.
B19VN09946
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Accessory Living Quarters
Work Description
NEW 21' x 23' (2)-STORY ACCESSORY LIVING QUARTERS; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
Permit Issued
Issued on 9/20/2019
Issuing Office
Valley
Current Status
CofO Issued on 1/19/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/14/2019 APPLICANT
Green Plans Picked Up 6/25/2019 APPLICANT
Assigned to Plan Check Engineer 7/11/2019 SELLA BENYAMIN
Corrections Issued 7/15/2019 SELLA BENYAMIN
Quality Review Completed 7/16/2019 STEVEN KIM
Building Plans Picked Up 7/17/2019 APPLICANT
Plan Check Approved 9/19/2019 SELLA BENYAMIN
Issued 9/20/2019 LADBS
CofO in Progress 1/14/2021 RONALD COWAN
Permit Finaled 1/19/2021 MICHAEL SMITH
CofO Issued 1/19/2021 MICHAEL SMITH
Permit Finaled 1/19/2021 MICHAEL SMITH

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 8/2/2019 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 8/2/2019 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 8/2/2019 LEE GUILBEAUX
Hydrant and Access approval Cleared 8/2/2019 GEORGE SUCHAND
Sewer availability Cleared 8/2/2019 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 8/9/2019 APEKSHYA BAJRACHARYA
Low Impact Development Cleared 8/21/2019 MITESH PATEL
Green Code Cleared 8/22/2019 PARISA ZAHABI
Roof/Waste drainage to street Cleared 8/26/2019 JOSHUA DIAZ
GPI Written Notices Cleared 9/19/2019 SELLA BENYAMIN
Grading Pre-Inspection Cleared 9/19/2019 SELLA BENYAMIN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 10/31/2019 Approved RONALD COWAN
Underground Mechanical 11/1/2019 Partial Approval RONALD COWAN
Footing/Foundation/Slab 11/12/2019 Partial Approval RONALD COWAN
Floor/Roof Diaphrgm/Shear Wall 12/9/2019 Partial Approval RONALD COWAN
Floor/Roof Diaphrgm/Shear Wall 12/23/2019 Partial Approval RONALD COWAN
Floor/Roof Diaphrgm/Shear Wall 1/6/2020 Partial Approval RONALD COWAN
Floor/Roof Diaphrgm/Shear Wall 1/29/2020 Partial Approval RONALD COWAN
PLUMBING-Rough 1/29/2020 Approved RONALD COWAN
Interior/Exterior Lathing 2/10/2020 Partial Approval RONALD COWAN
BUILDING-Rough-Frame 2/28/2020 Partial Approval RONALD COWAN
ELECTRICAL-Rough 2/28/2020 Approved RONALD COWAN
Green Building Rough 2/28/2020 Approved RONALD COWAN
HVAC-Rough 2/28/2020 Approved RONALD COWAN
Verify Sprinkler Sign Off 2/28/2020 Approved RONALD COWAN
Insulation 3/6/2020 Approved RONALD COWAN
Interior/Exterior Lathing 3/10/2020 Approved RONALD COWAN
Drywall Nailing 3/17/2020 Approved RONALD COWAN
BUILDING-Rough-Frame 1/11/2021 Approved RONALD COWAN
Final 1/11/2021 OK to Issue CofO RONALD COWAN
Footing/Foundation/Slab 1/11/2021 Approved RONALD COWAN
Green Building Final 1/11/2021 Approved RONALD COWAN
SGSOV-Seismic Gas S/O Valve 1/11/2021 SGSOV Approved RONALD COWAN
Service/Power Release 1/11/2021 Approved RONALD COWAN
Smoke Detectors 1/11/2021 Approved RONALD COWAN