4021 N ROYAL OAK PL 91436
Certificate Information: 4021 N ROYAL OAK PL 91436
- Application / Permit
- 19010-20000-02566
- Plan Check / Job No.
- B19VN09920
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (1 OF 4) NEW 2-STORY SFD WITH ATTACHED GARAGE, BASEMENT AND ROOF DECK.
- Permit Issued
- Issued on 1/3/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/8/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/14/2019 | APPLICANT |
| Green Plans Picked Up | 6/25/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 7/11/2019 | CHON CHIO KUO |
| Corrections Issued | 7/15/2019 | CHON CHIO KUO |
| Quality Review Completed | 7/17/2019 | STEVEN KIM |
| Building Plans Picked Up | 7/17/2019 | APPLICANT |
| Applicant returned to address corrections | 8/13/2019 | CHON CHIO KUO |
| Applicant returned to address corrections | 9/12/2019 | CHON CHIO KUO |
| Plan Check Approved | 12/20/2019 | CHON CHIO KUO |
| Issued | 1/3/2020 | LADBS |
| CofO in Progress | 4/1/2022 | DAVID SANDOVAL |
| Re-Activate Permit | 4/8/2022 | JOHN JANSON |
| Permit Finaled-Status Void | 4/8/2022 | JOHN JANSON |
| Permit Finaled | 4/8/2022 | JOHN JANSON |
| CofO Issued | 4/8/2022 | JOHN JANSON |
| Permit Finaled | 4/8/2022 | JOHN JANSON |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 7/24/2019 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 7/24/2019 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 7/24/2019 | LEE GUILBEAUX |
| Highway dedication | Cleared | 7/24/2019 | LEE GUILBEAUX |
| Miscellaneous | Cleared | 7/24/2019 | LEE GUILBEAUX |
| Permit | Cleared | 7/24/2019 | LEE GUILBEAUX |
| Sewer availability | Cleared | 7/24/2019 | LEE GUILBEAUX |
| Work Adjacent to Public Way | Cleared | 7/24/2019 | LEE GUILBEAUX |
| Hydrant and Access approval | Cleared | 7/25/2019 | GEORGE SUCHAND |
| Green Code | Cleared | 8/2/2019 | PARISA ZAHABI |
| GPI Written Notices | Cleared | 8/13/2019 | CHON CHIO KUO |
| Grading Pre-Inspection | Cleared | 8/13/2019 | CHON CHIO KUO |
| BHO/Hillside ordinance | Cleared | 8/15/2019 | JOHN LIN |
| Low Impact Development | Cleared | 8/21/2019 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 8/26/2019 | JOSHUA DIAZ |
| Excavation more than 5-ft deep | Cleared | 9/12/2019 | CALOSHA APPROVED |
| Disturb/Remove Protected Trees | Cleared | 11/14/2019 | JOHN KIM |
| Trees in Parkway | Cleared | 11/14/2019 | JOHN KIM |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Nazari,, Arthur; Lic. No.: C53497 | PO BOX 7112 NORTHRIDGE, CA 91327 |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Grading | 2/18/2020 | Approved | RONALD COWAN |
| Deputy Grading | 5/12/2020 | Approved | RONALD COWAN |
| Piling/Pier/Caisson | 5/21/2020 | Partial Approval | RONALD COWAN |
| Deputy Reinf. Concrete | 5/26/2020 | Approved | RONALD COWAN |
| Footing/Foundation/Slab | 6/25/2020 | Partial Approval | RONALD COWAN |
| PLUMBING-Rough | 6/25/2020 | Partial Approval | RONALD COWAN |
| Deputy Reinf. Concrete | 6/26/2020 | Approved | RONALD COWAN |
| Deputy Reinf. Concrete | 7/8/2020 | Approved | RONALD COWAN |
| Deputy Shotcrete | 7/14/2020 | Conditional Approval | SEAN WIRCH |
| Footing/Foundation/Slab | 7/14/2020 | Partial Approval | JOSEPH SAGEN |
| Structural Steel Frame | 7/14/2020 | Partial Approval | JOSEPH SAGEN |
| Deputy Shotcrete | 7/20/2020 | Approved | RONALD COWAN |
| Footing/Foundation/Slab | 7/28/2020 | Partial Approval | RONALD COWAN |
| Deputy Reinf. Concrete | 7/30/2020 | Approved | RONALD COWAN |
| Special/Order Compliance | 7/30/2020 | Approved | RONALD COWAN |
| Deputy Reinf. Concrete | 9/3/2020 | Approved | RONALD COWAN |
| Piling/Pier/Caisson | 9/8/2020 | Partial Approval | RONALD COWAN |
| Masonry Wall/Backfill | 10/9/2020 | Partial Approval | RONALD COWAN |
| Deputy Shotcrete | 10/14/2020 | Approved | RONALD COWAN |
| Footing/Foundation/Slab | 10/16/2020 | Partial Approval | RONALD COWAN |
| PLUMBING-Rough | 10/16/2020 | Partial Approval | RONALD COWAN |
| Footing/Foundation/Slab | 10/26/2020 | Partial Approval | RONALD COWAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/3/2020 | Approved | RONALD COWAN |
| Deputy Wood Construction | 12/17/2020 | Approved | RONALD COWAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/17/2020 | Partial Approval | RONALD COWAN |
| BUILDING-Rough-Frame | 1/19/2021 | Corrections Issued | RONALD COWAN |
| Wood Frame | 2/2/2021 | Not Ready for Inspection | RONALD COWAN |
| PLUMBING-Rough | 2/25/2021 | Approved | RONALD COWAN |
| BUILDING-Rough-Frame | 3/1/2021 | Corrections Issued | RONALD COWAN |
| Green Building Rough | 3/1/2021 | Corrections Issued | RONALD COWAN |
| HVAC-Rough | 3/1/2021 | Approved | RONALD COWAN |
| Verify Sprinkler Sign Off | 3/1/2021 | Not Ready for Inspection | RONALD COWAN |
| ELECTRICAL-Rough | 3/17/2021 | Approved | RONALD COWAN |
| BUILDING-Rough-Frame | 3/25/2021 | Approved | RONALD COWAN |
| Green Building Rough | 3/25/2021 | Approved | RONALD COWAN |
| HVAC-Rough | 3/25/2021 | Approved | RONALD COWAN |
| Verify Sprinkler Sign Off | 3/25/2021 | Approved | RONALD COWAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/7/2021 | Approved | RONALD COWAN |
| Drywall Nailing | 4/21/2021 | Approved | RONALD COWAN |
| Interior/Exterior Lathing | 4/21/2021 | Approved | RONALD COWAN |
| Interior/Exterior Lathing | 4/27/2021 | Approved | RONALD COWAN |
| ELECTRICAL-Final | 11/5/2021 | Approved | RONALD COWAN |
| HVAC-Final | 11/5/2021 | Approved | RONALD COWAN |
| PLUMBING-Final | 11/5/2021 | Approved | RONALD COWAN |
| Service/Power Release | 11/5/2021 | Approved | RONALD COWAN |
| Final | 3/1/2022 | Corrections Issued | DAVID SANDOVAL |
| Footing/Foundation/Slab | 3/1/2022 | Approved | DAVID SANDOVAL |
| Green Building Final | 3/1/2022 | Approved | DAVID SANDOVAL |
| Reinforced Concrete Frame | 3/1/2022 | Approved | DAVID SANDOVAL |
| SGSOV-Seismic Gas S/O Valve | 3/1/2022 | SGSOV Not Ready | DAVID SANDOVAL |
| Smoke Detectors | 3/1/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| Final | 3/23/2022 | Partial Inspection | DAVID SANDOVAL |
| SGSOV-Seismic Gas S/O Valve | 3/23/2022 | SGSOV Approved | DAVID SANDOVAL |
| Smoke Detectors | 3/23/2022 | Approved | DAVID SANDOVAL |
| Final | 4/1/2022 | OK to Issue CofO | DAVID SANDOVAL |