519 N LAUREL AVE 90048

Certificate Information: 519 N LAUREL AVE 90048

Application / Permit
19010-20000-02562
Plan Check / Job No.
B19VN09905
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Patio Cover
Work Description
NEW (13'-0"x 34'-0") DETACHED CABANA WITH OPEN TRELLIS. WORK PER ENGINEER.
Permit Issued
Issued on 9/2/2020
Issuing Office
Current Status
CofO Issued on 10/8/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/13/2019 APPLICANT
Green Plans Picked Up 6/25/2019 APPLICANT
Assigned to Plan Check Engineer 7/3/2019 TROY DEGUZMAN
Corrections Issued 7/8/2019 TROY DEGUZMAN
Quality Review Completed 7/10/2019 CHON CHIO KUO
Building Plans Picked Up 7/10/2019 APPLICANT
Applicant returned to address corrections 9/5/2019 TROY DEGUZMAN
Applicant returned to address corrections 1/8/2020 TROY DEGUZMAN
Plan Check Approved 1/22/2020 TROY DEGUZMAN
Issued 9/2/2020 APPLICANT
CofO in Progress 10/7/2021 CHRIS CHRISTENSEN
Permit Finaled 10/8/2021 DEROLD HAUFF
CofO Issued 10/8/2021 DEROLD HAUFF
Permit Finaled 10/8/2021 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/18/2019 MARKOS PEREZ-BRAN
Permit Cleared 7/18/2019 MARKOS PEREZ-BRAN
Sewer availability Cleared 7/18/2019 MARKOS PEREZ-BRAN
Low Impact Development Cleared 7/22/2019 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 7/26/2019 ADRIAN SANCHEZ
Construction within easement Cleared 9/10/2019 RIDWAN HARDY
Green Code Cleared 10/10/2019 TROY DEGUZMAN

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno S; Lic. No.: S3454 25531 PRADO DELAS BELLOTAS      CALABASAS, CA 91302

Inspector Information

JOSE MACIAS, (213) 202-3125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/7/2020 Approved CHRIS CHRISTENSEN
METHANE-Barrier 10/7/2020 Approved CHRIS CHRISTENSEN
METHANE-Subgrade 10/7/2020 Approved CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 11/2/2020 Partial Approval CHRIS CHRISTENSEN
BUILDING-Rough-Frame 1/20/2021 Partial Approval CHRIS CHRISTENSEN
METHANE-Rough 1/20/2021 Approved CHRIS CHRISTENSEN
Verify Sprinkler Sign Off 1/20/2021 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 2/9/2021 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 7/20/2021 Approved CHRIS CHRISTENSEN
Drywall Nailing 7/20/2021 Approved CHRIS CHRISTENSEN
Final 7/20/2021 Corrections Issued CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 7/20/2021 SGSOV Approved CHRIS CHRISTENSEN
Service/Power Release 7/20/2021 Not Required CHRIS CHRISTENSEN
Smoke Detectors 7/20/2021 Approved CHRIS CHRISTENSEN
Final 9/2/2021 Not Ready for Inspection CHRIS CHRISTENSEN
Final 10/6/2021 OK to Issue CofO CHRIS CHRISTENSEN