519 N LAUREL AVE 90048

Certificate Information: 519 N LAUREL AVE 90048

Application / Permit
19010-20000-02561
Plan Check / Job No.
B19VN09905
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW (67'-0"x 38'-0") 2-STORY SINGLE FAMILY DWELLING WITH ATTACHED 2- CAR GARAGE, WORK PER ENGINEER.
Permit Issued
Issued on 7/30/2020
Issuing Office
Current Status
CofO Issued on 10/8/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/13/2019 APPLICANT
Green Plans Picked Up 6/25/2019 APPLICANT
Assigned to Plan Check Engineer 7/3/2019 TROY DEGUZMAN
Corrections Issued 7/8/2019 TROY DEGUZMAN
Quality Review Completed 7/10/2019 CHON CHIO KUO
Building Plans Picked Up 7/10/2019 APPLICANT
Applicant returned to address corrections 9/5/2019 TROY DEGUZMAN
Applicant returned to address corrections 1/8/2020 TROY DEGUZMAN
Plan Check Approved 1/22/2020 TROY DEGUZMAN
Issued 7/30/2020 APPLICANT
CofO in Progress 10/7/2021 CHRIS CHRISTENSEN
Permit Finaled 10/8/2021 DEROLD HAUFF
CofO Issued 10/8/2021 DEROLD HAUFF
Permit Finaled 10/8/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 7/18/2019 MARKOS PEREZ-BRAN
Address approval Cleared 7/18/2019 MARKOS PEREZ-BRAN
Distance to fire station Cleared 7/18/2019 GEORGE SUCHAND
Eng Process Fee Ord 176,300 Cleared 7/18/2019 MARKOS PEREZ-BRAN
Hydrant and Access approval Cleared 7/18/2019 GEORGE SUCHAND
Permit Cleared 7/18/2019 MARKOS PEREZ-BRAN
Sewer availability Cleared 7/18/2019 MARKOS PEREZ-BRAN
Low Impact Development Cleared 7/22/2019 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 7/26/2019 ADRIAN SANCHEZ
Trees in Parkway Cleared 7/29/2019 JOHN KIM
Green Code Cleared 10/10/2019 PARISA ZAHABI

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno S; Lic. No.: S3454 25531 PRADO DELAS BELLOTAS      CALABASAS, CA 91302

Inspector Information

JOSE MACIAS, (213) 202-3125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 8/26/2020 Approved CHRIS CHRISTENSEN
Underground Mechanical 8/26/2020 Partial Approval CHRIS CHRISTENSEN
Excavation/Setback/Form/Re-Bar 9/10/2020 Approved CHRIS CHRISTENSEN
Footing/Foundation/Slab 9/10/2020 Approved CHRIS CHRISTENSEN
METHANE-Barrier 9/10/2020 Approved CHRIS CHRISTENSEN
METHANE-Subgrade 9/10/2020 Approved CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 10/20/2020 Partial Approval CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 11/2/2020 Conditional Approval CHRIS CHRISTENSEN
Deputy Steel/Welding 12/2/2020 Conditional Approval CHRIS CHRISTENSEN
PLUMBING-Rough 12/8/2020 Approved CHRIS CHRISTENSEN
HVAC-Rough 12/16/2020 Approved CHRIS CHRISTENSEN
Shower Pan 12/18/2020 Corrections Issued JOSEPH MCGARRY
ELECTRICAL-Rough 12/28/2020 Approved CHRIS CHRISTENSEN
Shower Pan 12/28/2020 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 1/20/2021 Approved CHRIS CHRISTENSEN
Green Building Rough 1/20/2021 Not Ready for Inspection CHRIS CHRISTENSEN
METHANE-Rough 1/20/2021 Approved CHRIS CHRISTENSEN
Verify Sprinkler Sign Off 1/20/2021 Approved CHRIS CHRISTENSEN
Wood Frame 1/20/2021 Approved CHRIS CHRISTENSEN
Drywall Nailing 2/9/2021 Conditional Approval CHRIS CHRISTENSEN
Green Building Rough 2/9/2021 Approved CHRIS CHRISTENSEN
Insulation 2/9/2021 Conditional Approval CHRIS CHRISTENSEN
Interior/Exterior Lathing 2/9/2021 Approved CHRIS CHRISTENSEN
HVAC-Final 6/28/2021 Approved CHRIS CHRISTENSEN
ELECTRICAL-Final 7/20/2021 Approved CHRIS CHRISTENSEN
PLUMBING-Final 7/20/2021 Approved CHRIS CHRISTENSEN
Service/Power Release 7/20/2021 Not Ready for Inspection CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 8/12/2021 SGSOV Not Ready CHRIS CHRISTENSEN
Green Building Final 8/20/2021 Approved CHRIS CHRISTENSEN
Service/Power Release 8/20/2021 Approved CHRIS CHRISTENSEN
Smoke Detectors 8/20/2021 Approved CHRIS CHRISTENSEN
Drywall Nailing 9/2/2021 Approved CHRIS CHRISTENSEN
Final 9/2/2021 Conditional Approval CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 9/2/2021 SGSOV Approved CHRIS CHRISTENSEN
Final 10/6/2021 OK to Issue CofO CHRIS CHRISTENSEN