7501 N YARMOUTH AVE 91335

Certificate Information: 7501 N YARMOUTH AVE 91335

Application / Permit
19010-20000-02553
Plan Check / Job No.
B19VN09897
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
(N) 40' x 22'-3" One Story Detached Two-Car Garage and Storage per Eng.
Permit Issued
Issued on 2/11/2020
Issuing Office
Valley
Current Status
CofO Issued on 6/16/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/13/2019 APPLICANT
Green Plans Picked Up 7/19/2019 APPLICANT
Assigned to Plan Check Engineer 7/25/2019 OMID HEDAYAT
Corrections Issued 8/12/2019 OMID HEDAYAT
Quality Review Completed 8/15/2019 STEVEN KIM
Building Plans Picked Up 8/27/2019 APPLICANT
Applicant returned to address corrections 10/29/2019 OMID HEDAYAT
Applicant returned to address corrections 1/23/2020 OMID HEDAYAT
Applicant returned to address corrections 2/10/2020 OMID HEDAYAT
Plan Check Approved 2/11/2020 OMID HEDAYAT
Issued 2/11/2020 LADBS
CofO in Progress 5/29/2020 MICHAEL SMITH
Permit Finaled 6/16/2020 DONALD SUNSERI
CofO Issued 6/16/2020 DONALD SUNSERI
Permit Finaled 6/16/2020 DONALD SUNSERI

Permit Application Clearance Information

Construction within easement Cleared 8/23/2019 RIDWAN HARDY
Green Code Cleared 10/16/2019 AARON COSTA
Hydrant and Access approval Cleared 10/24/2019 GEORGE SUCHAND
Eng Process Fee Ord 176,300 Cleared 1/15/2020 GABRIEL ROBLES
Construction near power lines Cleared 2/5/2020 TORI CHEN
Low Impact Development Cleared 2/5/2020 ORVAL HERNANDEZ-MARCIAL
Roof/Waste drainage to street Cleared 2/5/2020 JAMES MORALEZ

Contact Information

Architect Newbern,, Walter Pedro; Lic. No.: C22914 1010 NO. MADISON AVENUE      PASADENA, CA 91104
Contractor Owner-Builder       ,
Engineer Arsen, Adzhemyan; Lic. No.: C89103 1010 RALEIGH ST   APT 107    GLENDALE, CA 91205

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/18/2020 Approved VINCENT HANLEY
Footing/Foundation/Slab 2/18/2020 Approved VINCENT HANLEY
PLUMBING-Rough 2/18/2020 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 3/3/2020 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 3/10/2020 Approved VINCENT HANLEY
Interior/Exterior Lathing 3/10/2020 Partial Approval VINCENT HANLEY
Shower Pan 3/10/2020 Approved VINCENT HANLEY
BUILDING-Rough-Frame 3/12/2020 Approved VINCENT HANLEY
ELECTRICAL-Rough 3/12/2020 Approved VINCENT HANLEY
Green Building Rough 3/12/2020 Approved VINCENT HANLEY
HVAC-Rough 3/12/2020 Approved VINCENT HANLEY
PLUMBING-Rough 3/12/2020 Approved VINCENT HANLEY
Shower Pan 3/12/2020 Approved VINCENT HANLEY
ELECTRICAL-Rough 4/15/2020 Approved VINCENT HANLEY
Drywall Nailing 4/16/2020 Approved VINCENT HANLEY
Interior/Exterior Lathing 4/16/2020 Approved VINCENT HANLEY
Final 4/29/2020 Corrections Issued VINCENT HANLEY
Green Building Final 4/29/2020 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 4/29/2020 SGSOV Not Ready VINCENT HANLEY
Service/Power Release 4/29/2020 Approved VINCENT HANLEY
Smoke Detectors 4/29/2020 Approved VINCENT HANLEY
ELECTRICAL-Final 5/28/2020 Approved VINCENT HANLEY
Final 5/28/2020 OK to Issue CofO VINCENT HANLEY
HVAC-Final 5/28/2020 Approved VINCENT HANLEY
PLUMBING-Final 5/28/2020 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 5/28/2020 SGSOV Approved VINCENT HANLEY