335 W 48TH ST 90037
Certificate Information: 335 W 48TH ST 90037
- Application / Permit
- 19010-20000-02540
- Plan Check / Job No.
- B19VN09861
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 30'-0" x 27'-0" IRREGULAR SHAPED DETACHED TWO CAR GARAGE WITH 30'-0" x 30'-4" IRREGULAR SHAPED (N) ACCESSORY DWELLING UNIT PER AB 494 AND SB 229 ON SECOND FLOOR.
- Permit Issued
- Issued on 8/12/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/20/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/13/2019 | APPLICANT |
| Green Plans Picked Up | 6/26/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 7/3/2019 | SARKIS HARABEDIAN |
| Corrections Issued | 7/8/2019 | SARKIS HARABEDIAN |
| Quality Review Completed | 7/8/2019 | ABDUL CHEGENI |
| Building Plans Picked Up | 7/9/2019 | APPLICANT |
| Applicant returned to address corrections | 7/24/2019 | SARKIS HARABEDIAN |
| Plan Check Approved | 8/9/2019 | SARKIS HARABEDIAN |
| Issued | 8/12/2019 | LADBS |
| CofO in Progress | 8/16/2022 | JOAQUIN GREENOUGH |
| Permit Finaled | 8/20/2022 | DEROLD HAUFF |
| CofO Issued | 8/20/2022 | DEROLD HAUFF |
| Permit Finaled | 8/20/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 7/9/2019 | SAFA JAVANMARDI |
| Eng Process Fee Ord 176,300 | Cleared | 7/9/2019 | SAFA JAVANMARDI |
| Permit | Cleared | 7/9/2019 | SAFA JAVANMARDI |
| Trees in Parkway | Cleared | 7/12/2019 | HECTOR BANUELOS |
| Low Impact Development | Cleared | 7/26/2019 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 7/26/2019 | ELAINE LEI |
| Green Code | Cleared | 7/29/2019 | DAVID MATSON |
| ZI | Cleared | 8/2/2019 | NOAH MCCOY |
| Sewer availability | Cleared | 8/8/2019 | GUILLERMO PETRA |
| Hydrant and Access approval | Cleared | 8/9/2019 | GEORGE SUCHAND |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Hedjran,, Nader; Lic. No.: C68179 | 1311 VISTA COLINA DR SAN MARCOS, CA 92078 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/3/2019 | Corrections Issued | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 4/9/2020 | Not Ready for Inspection | FREDDIE RIVERA |
| ELECTRICAL-Rough | 4/9/2020 | Approved | FREDDIE RIVERA |
| Green Building Rough | 4/9/2020 | Not Ready for Inspection | FREDDIE RIVERA |
| HVAC-Rough | 4/9/2020 | Not Ready for Inspection | FREDDIE RIVERA |
| MERV13>=Rough | 4/9/2020 | Not Ready for Inspection | FREDDIE RIVERA |
| PLUMBING-Rough | 4/9/2020 | Not Ready for Inspection | FREDDIE RIVERA |
| Verify Sprinkler Sign Off | 4/9/2020 | Not Ready for Inspection | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 4/16/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 4/16/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| Green Building Rough | 4/16/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| MERV13>=Rough | 4/16/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 4/16/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| Verify Sprinkler Sign Off | 4/16/2020 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 4/27/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 4/27/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| Green Building Rough | 4/27/2020 | Corrections Issued | ENRIQUE MIRELES |
| MERV13>=Rough | 4/27/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| Verify Sprinkler Sign Off | 4/27/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| PLUMBING-Rough | 4/29/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 5/4/2020 | Partial Approval | FREDDIE RIVERA |
| PLUMBING-Rough | 5/6/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| BUILDING-Rough-Frame | 5/14/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| Green Building Rough | 5/14/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| MERV13>=Rough | 5/14/2020 | Approved | ROBERT MCDOWELL |
| Verify Sprinkler Sign Off | 5/14/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| Footing/Foundation/Slab | 5/26/2020 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Insulation | 5/26/2020 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 5/26/2020 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 6/10/2020 | Approved | SABAS ALONSO |
| Green Building Rough | 6/10/2020 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 6/10/2020 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 8/7/2020 | Conditional Approval | ROBERT MCDOWELL |
| ELECTRICAL-Final | 8/7/2020 | Approved | ROBERT MCDOWELL |
| Final | 8/7/2020 | Corrections Issued | ROBERT MCDOWELL |
| Footing/Foundation/Slab | 8/7/2020 | Approved | ROBERT MCDOWELL |
| Green Building Final | 8/7/2020 | Approved | ROBERT MCDOWELL |
| Green Building Rough | 8/7/2020 | Approved | ROBERT MCDOWELL |
| HVAC-Final | 8/7/2020 | Approved | ROBERT MCDOWELL |
| MERV13>=Final | 8/7/2020 | Approved | ROBERT MCDOWELL |
| PLUMBING-Final | 8/7/2020 | Approved | ROBERT MCDOWELL |
| SGSOV-Seismic Gas S/O Valve | 8/7/2020 | SGSOV Not Ready | ROBERT MCDOWELL |
| Service/Power Release | 8/7/2020 | Approved | ROBERT MCDOWELL |
| Smoke Detectors | 8/7/2020 | Approved | ROBERT MCDOWELL |
| Verify Sprinkler Sign Off | 8/7/2020 | Partial Inspection | ROBERT MCDOWELL |
| Service/Power Release | 11/9/2020 | Not Ready for Inspection | DAVID FEILER |
| Pre-Inspection | 5/12/2021 | Approved | HORACE FULTZ |
| BUILDING-Rough-Frame | 2/1/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Final | 2/1/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 2/1/2022 | SGSOV Not Ready | JOAQUIN GREENOUGH |
| Verify Sprinkler Sign Off | 2/1/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 4/6/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Final | 4/6/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 4/6/2022 | SGSOV Not Ready | JOAQUIN GREENOUGH |
| Verify Sprinkler Sign Off | 4/6/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 4/14/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Final | 4/14/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 4/14/2022 | SGSOV Not Ready | JOAQUIN GREENOUGH |
| Verify Sprinkler Sign Off | 4/14/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 4/22/2022 | SGSOV Not Ready | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 5/10/2022 | Approved | JOAQUIN GREENOUGH |
| Final | 5/10/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 5/10/2022 | SGSOV Approved | JOAQUIN GREENOUGH |
| Verify Sprinkler Sign Off | 5/10/2022 | Approved | JOAQUIN GREENOUGH |
| Final | 6/28/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Final | 8/2/2022 | OK to Issue CofO | JOAQUIN GREENOUGH |
| Service/Power Release | 8/2/2022 | Approved | JOAQUIN GREENOUGH |