15419 W TUBA ST 91345

Certificate Information: 15419 W TUBA ST 91345

Application / Permit
19010-20000-02507
Plan Check / Job No.
B19VN09784
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW IRREGULAR 37'-9" X 40'-0" DETACHED ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. ALL WORK PER WFPP.
Permit Issued
Issued on 9/18/2019
Issuing Office
Valley
Current Status
CofO Issued on 6/22/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/12/2019 APPLICANT
Assigned to Plan Check Engineer 7/3/2019 JENNIFER LEE
Corrections Issued 7/8/2019 JENNIFER LEE
Quality Review Completed 7/9/2019 STEVEN KIM
Building Plans Picked Up 7/9/2019 APPLICANT
Green Plans Picked Up 7/9/2019 APPLICANT
Plan Check Approved 9/12/2019 JENNIFER LEE
Issued 9/18/2019 LADBS
CofO in Progress 5/26/2020 JENNIFER RABUCHIN
Permit Finaled 6/22/2020 MICHAEL SMITH
CofO Issued 6/22/2020 MICHAEL SMITH
Permit Finaled 6/22/2020 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 7/22/2019 SAFA JAVANMARDI
Eng Process Fee Ord 176,300 Cleared 7/22/2019 SAFA JAVANMARDI
Hydrant and Access approval Cleared 7/22/2019 GEORGE SUCHAND
Sewer availability Cleared 7/22/2019 SAFA JAVANMARDI
Low Impact Development Cleared 8/13/2019 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 8/13/2019 APEKSHYA BAJRACHARYA
Green Code Cleared 9/5/2019 DAVID MATSON

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 11/6/2019 Partial Approval JENNIFER RABUCHIN
Sewer 11/6/2019 Approved JENNIFER RABUCHIN
Excavation/Setback/Form/Re-Bar 11/13/2019 Approved JENNIFER RABUCHIN
Footing/Foundation/Slab 11/13/2019 Approved JENNIFER RABUCHIN
Underground Mechanical 11/13/2019 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 12/12/2019 Partial Approval JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 12/12/2019 Partial Approval JENNIFER RABUCHIN
Green Building Rough 12/12/2019 Not Ready for Inspection JENNIFER RABUCHIN
Verify Sprinkler Sign Off 12/12/2019 Partial Approval JENNIFER RABUCHIN
BUILDING-Rough-Frame 1/10/2020 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Rough 1/10/2020 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 1/10/2020 Approved JENNIFER RABUCHIN
HVAC-Rough 1/10/2020 Approved JENNIFER RABUCHIN
PLUMBING-Rough 1/10/2020 Approved JENNIFER RABUCHIN
Insulation 1/17/2020 Partial Approval JENNIFER RABUCHIN
Interior/Exterior Lathing 1/17/2020 Partial Approval JENNIFER RABUCHIN
Drywall Nailing 1/23/2020 Approved JENNIFER RABUCHIN
Green Building Rough 1/23/2020 Approved JENNIFER RABUCHIN
Shower Pan 2/26/2020 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 2/28/2020 No Access for Inspection TROY SANDERS
Interior/Exterior Lathing 3/3/2020 Approved JENNIFER RABUCHIN
Service/Power Release 4/15/2020 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 4/23/2020 Approved JENNIFER RABUCHIN
Final 4/23/2020 OK to Issue CofO JENNIFER RABUCHIN
Green Building Final 4/23/2020 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 4/23/2020 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 4/23/2020 Approved JENNIFER RABUCHIN
Verify Sprinkler Sign Off 4/23/2020 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 5/21/2020 Approved JENNIFER RABUCHIN
Final 5/21/2020 Partial Approval JENNIFER RABUCHIN
HVAC-Final 5/21/2020 Approved JENNIFER RABUCHIN
MERV13>=Final 5/21/2020 Approved JENNIFER RABUCHIN
PLUMBING-Final 5/21/2020 Approved JENNIFER RABUCHIN