8274 W 4TH ST 90048
Certificate Information: 8274 W 4TH ST 90048
- Application / Permit
- 19010-20000-02440
- Plan Check / Job No.
- B19VN09547
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New two-story (38' x 80'-2" Irr.) Single Family Dwelling with attached two-car garage, and a rooftop deck.
- Permit Issued
- Issued on 6/2/2021
- Issuing Office
- Current Status
- CofO Issued on 6/27/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/10/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 6/27/2019 | LUIS RINCON |
| Corrections Issued | 6/29/2019 | LUIS RINCON |
| Green Plans Picked Up | 7/2/2019 | APPLICANT |
| Quality Review Completed | 7/29/2019 | OMID HEDAYAT |
| Building Plans Picked Up | 8/1/2019 | APPLICANT |
| Applicant returned to address corrections | 9/30/2020 | LUIS RINCON |
| Plan Check Approved | 2/3/2021 | LUIS RINCON |
| Issued | 6/2/2021 | APPLICANT |
| CofO in Progress | 6/13/2023 | JEREMY TODD |
| Permit Finaled | 6/27/2023 | DANIEL ORRANTE |
| CofO Issued | 6/27/2023 | DANIEL ORRANTE |
| Permit Finaled | 6/27/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Low Impact Development | Cleared | 7/16/2019 | ANDRES COVARRUBIAS |
| Eng Process Fee Ord 176,300 | Cleared | 7/23/2019 | LEE GUILBEAUX |
| Green Code | Cleared | 7/23/2019 | MICHAEL AYERS |
| Hydrant and Access approval | Cleared | 7/23/2019 | GEORGE SUCHAND |
| Methane Ordinance | Cleared | 7/23/2019 | GEORGE SUCHAND |
| Permit | Cleared | 7/23/2019 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 7/23/2019 | LEE GUILBEAUX |
| Sewer availability | Cleared | 7/23/2019 | LEE GUILBEAUX |
| Historic monument | Cleared | 1/22/2021 | MELISSA JONES |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Lerner,, George; Lic. No.: C40288 | 4668 WILLIS AVE SHERMAN OAKS, CA 91403 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/5/2021 | Corrections Issued | EVAN COOPER |
| METHANE-Barrier | 8/5/2021 | Approved | EVAN COOPER |
| METHANE-Subgrade | 8/5/2021 | Approved | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 8/27/2021 | Partial Approval | EVAN COOPER |
| Footing/Foundation/Slab | 8/27/2021 | Approved | EVAN COOPER |
| PLUMBING-Rough | 8/27/2021 | Corrections Issued | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 9/3/2021 | Partial Approval | EVAN COOPER |
| PLUMBING-Rough | 9/3/2021 | Partial Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 9/8/2021 | Partial Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 10/4/2021 | Partial Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 12/7/2021 | Corrections Issued | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 2/7/2022 | Partial Approval | EVAN COOPER |
| HVAC-Rough | 4/20/2022 | Approved | EVAN COOPER |
| PLUMBING-Rough | 4/20/2022 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 5/13/2022 | Partial Approval | EVAN COOPER |
| ELECTRICAL-Rough | 5/13/2022 | Approved | EVAN COOPER |
| Green Building Rough | 5/13/2022 | Approved | EVAN COOPER |
| METHANE-Rough | 5/13/2022 | Approved | EVAN COOPER |
| Special/Order Compliance | 5/13/2022 | Corrections Issued | EVAN COOPER |
| Verify Sprinkler Sign Off | 5/13/2022 | Approved | EVAN COOPER |
| Insulation | 5/23/2022 | Corrections Issued | EVAN COOPER |
| Drywall Nailing | 6/9/2022 | Corrections Issued | STEPHANIE SWANSON |
| Shower Pan | 6/9/2022 | Approved | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 7/7/2022 | Approved | EVAN COOPER |
| Pre-Gunite | 10/17/2022 | Partial Inspection | ANDREW NAVE |
| PLUMBING-Rough | 11/8/2022 | Corrections Issued | EVAN COOPER |
| Deck | 11/30/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Grounding or Bonding | 11/30/2022 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Final | 4/27/2023 | Approved | JEREMY TODD |
| HVAC-Final | 4/27/2023 | Approved | JEREMY TODD |
| PLUMBING-Final | 4/27/2023 | Approved | JEREMY TODD |
| Green Building Final | 5/31/2023 | No Access for Inspection | JEREMY TODD |
| BUILDING-Rough-Frame | 6/1/2023 | Approved | JEREMY TODD |
| Drywall Nailing | 6/1/2023 | Approved | JEREMY TODD |
| Final | 6/1/2023 | Corrections Issued | JEREMY TODD |
| Green Building Final | 6/1/2023 | Approved | JEREMY TODD |
| SGSOV-Seismic Gas S/O Valve | 6/1/2023 | SGSOV Approved | JEREMY TODD |
| Service/Power Release | 6/1/2023 | Approved | JEREMY TODD |
| Smoke Detectors | 6/1/2023 | Approved | JEREMY TODD |
| Final | 6/12/2023 | OK to Issue CofO | JEREMY TODD |
| Service/Power Release | 6/12/2023 | Approved | JEREMY TODD |