15601 W MEADOWGATE ROAD 91436

Certificate Information: 15601 W MEADOWGATE ROAD 91436

Application / Permit
19010-20000-02438
Plan Check / Job No.
B19VN09542
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 2-STORY SFD W/ ATTACHED GARAGE & BASEMENT (NFPA-13D FIRE SPRINKLERS THROUGHOUT)
Permit Issued
Issued on 8/28/2019
Issuing Office
Valley
Current Status
CofO Issued on 11/24/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/7/2019 APPLICANT
Assigned to Plan Check Engineer 6/27/2019 NILOOFAR MEHRAIN
Corrections Issued 7/1/2019 NILOOFAR MEHRAIN
Quality Review Completed 7/5/2019 STEVEN KIM
Building Plans Picked Up 7/8/2019 APPLICANT
Green Plans Picked Up 8/1/2019 APPLICANT
Applicant returned to address corrections 8/7/2019 NILOOFAR MEHRAIN
Applicant returned to address corrections 8/14/2019 NILOOFAR MEHRAIN
Applicant returned to address corrections 8/19/2019 NILOOFAR MEHRAIN
Plan Check Approved 8/26/2019 NILOOFAR MEHRAIN
Issued 8/28/2019 LADBS
CofO in Progress 11/18/2020 RONALD COWAN
CofO Issued 11/24/2020 MICHAEL SMITH
Permit Finaled 11/24/2020 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 8/2/2019 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 8/2/2019 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 8/2/2019 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 8/2/2019 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 8/2/2019 LEE GUILBEAUX
Hydrant and Access approval Cleared 8/2/2019 GEORGE SUCHAND
Permit Cleared 8/2/2019 LEE GUILBEAUX
Sewer availability Cleared 8/2/2019 LEE GUILBEAUX
GPI Written Notices Cleared 8/7/2019 NILOOFAR MEHRAIN
Grading Pre-Inspection Cleared 8/7/2019 NILOOFAR MEHRAIN
Green Code Cleared 8/13/2019 MICHAEL AYERS
Haul Route Cleared 8/14/2019 NILOOFAR MEHRAIN
Low Impact Development Cleared 8/14/2019 MITESH PATEL
Roof/Waste drainage to street Cleared 8/14/2019 ELAINE LEI
Trees in Parkway Cleared 8/14/2019 ADRIAN SANCHEZ
Excavation more than 5-ft deep Cleared 8/26/2019 CALOSHA APPROVED

Contact Information

Contractor Owner-Builder       ,
Engineer Barr,, Joseph Daniel; Lic. No.: C70708 1243 21ST AVE NE APT B      HICKORY, NC 28601
Engineer Nazari,, Arthur; Lic. No.: C53497 PO BOX 7112      NORTHRIDGE, CA 91327
Geologist Miller,, Jonathan Steven; Lic. No.: EG2391 1423 S BEVERLY GLEN BLVD APT B      LOS ANGELES, CA 90024

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/8/2019 Partial Approval RONALD COWAN
Footing/Foundation/Slab 10/8/2019 Partial Approval RONALD COWAN
PLUMBING-Rough 10/8/2019 Partial Approval RONALD COWAN
Sewer 10/8/2019 Partial Approval RONALD COWAN
Underground Mechanical 10/8/2019 Approved RONALD COWAN
Deputy Steel/Welding 10/16/2019 Approved RONALD COWAN
Structural Steel Frame 10/16/2019 Partial Approval RONALD COWAN
Footing/Foundation/Slab 10/25/2019 Partial Approval RONALD COWAN
Footing/Foundation/Slab 10/31/2019 Partial Approval RONALD COWAN
Deputy Steel/Welding 11/1/2019 Approved RONALD COWAN
BUILDING-Rough-Frame 11/18/2019 Not Ready for Inspection RONALD COWAN
Green Building Rough 11/18/2019 Partial Approval RONALD COWAN
Verify Sprinkler Sign Off 11/18/2019 Not Ready for Inspection RONALD COWAN
Deputy Steel/Welding 11/25/2019 Approved RONALD COWAN
Wood Frame 12/3/2019 Partial Approval RONALD COWAN
Deputy Steel/Welding 12/16/2019 Approved RONALD COWAN
BUILDING-Rough-Frame 12/18/2019 Partial Approval RONALD COWAN
Floor/Roof Diaphrgm/Shear Wall 12/18/2019 Partial Approval RONALD COWAN
Green Building Rough 12/18/2019 Not Ready for Inspection RONALD COWAN
Verify Sprinkler Sign Off 12/18/2019 Not Ready for Inspection RONALD COWAN
PLUMBING-Rough 1/6/2020 Corrections Issued RONALD COWAN
HVAC-Rough 1/16/2020 Corrections Issued RONALD COWAN
ELECTRICAL-Rough 1/17/2020 Not Ready for Inspection RONALD COWAN
BUILDING-Rough-Frame 1/27/2020 Approved RONALD COWAN
ELECTRICAL-Rough 1/27/2020 Approved RONALD COWAN
Green Building Rough 1/27/2020 Approved RONALD COWAN
HVAC-Rough 1/27/2020 Approved RONALD COWAN
Verify Sprinkler Sign Off 1/27/2020 Approved RONALD COWAN
Wood Frame 1/27/2020 Not Ready for Inspection RONALD COWAN
Deputy Wood Construction 1/30/2020 Approved RONALD COWAN
Shower Pan 1/31/2020 Not Ready for Inspection RONALD COWAN
Interior/Exterior Lathing 2/4/2020 Approved RONALD COWAN
Drywall Nailing 2/12/2020 Approved RONALD COWAN
Interior/Exterior Lathing 2/12/2020 Approved RONALD COWAN
ELECTRICAL-Final 7/6/2020 Corrections Issued RONALD COWAN
HVAC-Final 7/6/2020 Approved RONALD COWAN
PLUMBING-Final 7/6/2020 Corrections Issued RONALD COWAN
Service/Power Release 8/6/2020 Approved RONALD COWAN
Final 8/7/2020 Corrections Issued RONALD COWAN
Footing/Foundation/Slab 8/7/2020 Approved RONALD COWAN
Green Building Final 8/7/2020 Approved RONALD COWAN
HVAC-Final 8/7/2020 Approved RONALD COWAN
PLUMBING-Final 8/7/2020 Approved RONALD COWAN
SGSOV-Seismic Gas S/O Valve 8/7/2020 SGSOV Approved RONALD COWAN
Service/Power Release 8/7/2020 Approved RONALD COWAN
Smoke Detectors 8/7/2020 Approved RONALD COWAN
Final 10/30/2020 Corrections Issued RONALD COWAN
Final 11/12/2020 OK to Issue CofO RONALD COWAN