18604 W CITRONIA ST 91324

Certificate Information: 18604 W CITRONIA ST 91324

Application / Permit
19010-20000-02435
Plan Check / Job No.
B19VN09536
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW (31'-9"x 40'-0") DETACHED ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. WORK PER LA STD WFPP.
Permit Issued
Issued on 12/6/2019
Issuing Office
Valley
Current Status
CofO Issued on 5/3/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/7/2019 APPLICANT
Green Plans Picked Up 6/18/2019 APPLICANT
Assigned to Plan Check Engineer 6/27/2019 TROY DEGUZMAN
Corrections Issued 7/1/2019 TROY DEGUZMAN
Quality Review Completed 7/5/2019 STEVEN KIM
Building Plans Picked Up 7/8/2019 APPLICANT
Applicant returned to address corrections 8/26/2019 TROY DEGUZMAN
Plan Check Approved 8/30/2019 TROY DEGUZMAN
Issued 12/6/2019 LADBS
CofO in Progress 5/2/2021 JEFFREY PARD
Permit Finaled 5/3/2021 JOHN JANSON
CofO Issued 5/3/2021 JOHN JANSON
Permit Finaled 5/3/2021 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 8/8/2019 MARKOS PEREZ-BRAN
Eng Process Fee Ord 176,300 Cleared 8/8/2019 MARKOS PEREZ-BRAN
Sewer availability Cleared 8/8/2019 MARKOS PEREZ-BRAN
Low Impact Development Cleared 8/12/2019 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 8/12/2019 APEKSHYA BAJRACHARYA
Green Code Cleared 8/26/2019 MICHAEL AYERS
Hydrant and Access approval Cleared 8/29/2019 GEORGE SUCHAND
Hold Cleared 4/23/2020 LOURDES RAMIRO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/27/2020 Corrections Issued MICHAEL TEMPLE
Footing/Foundation/Slab 5/6/2020 Corrections Issued MICHAEL TEMPLE
Footing/Foundation/Slab 5/22/2020 Not Ready for Inspection DONALD SUNSERI
Footing/Foundation/Slab 6/9/2020 Approved MICHAEL TEMPLE
PLUMBING-Rough 6/30/2020 Corrections Issued JEFFREY PARD
PLUMBING-Rough 7/6/2020 Approved JEFFREY PARD
BUILDING-Rough-Frame 7/9/2020 Partial Approval JEFFREY PARD
Green Building Rough 7/9/2020 Partial Approval JEFFREY PARD
Insulation 7/9/2020 Partial Approval JEFFREY PARD
Verify Sprinkler Sign Off 7/9/2020 Not Ready for Inspection JEFFREY PARD
BUILDING-Rough-Frame 7/14/2020 Partial Approval DONALD SUNSERI
Floor/Roof Diaphrgm/Shear Wall 7/14/2020 Partial Approval DONALD SUNSERI
Floor/Roof Diaphrgm/Shear Wall 8/3/2020 Partial Approval JEFFREY PARD
ELECTRICAL-Rough 9/17/2020 Approved DAVID SCANTLIN
HVAC-Rough 9/17/2020 Approved DAVID SCANTLIN
PLUMBING-Rough 9/17/2020 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 9/30/2020 Approved JEFFREY PARD
Green Building Rough 9/30/2020 Not Ready for Inspection JEFFREY PARD
Verify Sprinkler Sign Off 9/30/2020 Approved JEFFREY PARD
Insulation 10/6/2020 Approved JEFFREY PARD
Drywall Nailing 10/15/2020 Not Ready for Inspection DONALD SUNSERI
Underground Mechanical 10/15/2020 Not Ready for Inspection DONALD SUNSERI
Drywall Nailing 10/22/2020 Approved JEFFREY PARD
Interior/Exterior Lathing 10/22/2020 Approved JEFFREY PARD
Sewer 11/30/2020 Approved JEFFREY PARD
BUILDING-Rough-Frame 12/29/2020 Approved JEFFREY PARD
Final 12/29/2020 Corrections Issued JEFFREY PARD
Green Building Final 12/29/2020 Corrections Issued JEFFREY PARD
Green Building Rough 12/29/2020 Approved JEFFREY PARD
SGSOV-Seismic Gas S/O Valve 12/29/2020 SGSOV Approved JEFFREY PARD
Service/Power Release 12/29/2020 Not Ready for Inspection JEFFREY PARD
Smoke Detectors 12/29/2020 Approved JEFFREY PARD
Final 4/5/2021 Corrections Issued JEFFREY PARD
Green Building Final 4/5/2021 Corrections Issued JEFFREY PARD
Service/Power Release 4/5/2021 Approved JEFFREY PARD
Final 4/30/2021 OK to Issue CofO JEFFREY PARD
Green Building Final 4/30/2021 Approved JEFFREY PARD