5527 N SYLVIA AVE 91356

Certificate Information: 5527 N SYLVIA AVE 91356

Application / Permit
19010-20000-02422
Plan Check / Job No.
B19VN09494
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) (65'-4"x 33'-0") TWO STORY SINGLE FAMILY DWELLING & BASEMENT WITH ATT. 2-CAR GARAGE. NFPA-13D FIRE SPRINKLER THROUGHOUT. WORK PER ENGINEER.
Permit Issued
Issued on 12/5/2019
Issuing Office
Valley
Current Status
CofO Issued on 10/26/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/7/2019 APPLICANT
Green Plans Picked Up 7/12/2019 APPLICANT
Assigned to Plan Check Engineer 7/18/2019 TROY DEGUZMAN
Corrections Issued 7/25/2019 TROY DEGUZMAN
Quality Review Completed 7/26/2019 CHON CHIO KUO
Building Plans Picked Up 8/2/2019 APPLICANT
Applicant returned to address corrections 9/12/2019 TROY DEGUZMAN
Applicant returned to address corrections 10/4/2019 TROY DEGUZMAN
Plan Check Approved 12/2/2019 TROY DEGUZMAN
Issued 12/5/2019 LADBS
CofO in Progress 10/26/2021 DAVID SANDOVAL
Permit Finaled 10/26/2021 MICHAEL SMITH
CofO Issued 10/26/2021 MICHAEL SMITH
Permit Finaled 10/26/2021 MICHAEL SMITH

Permit Application Clearance Information

Low Impact Development Cleared 10/17/2019 MITESH PATEL
Sewer availability Cleared 11/26/2019 GUILLERMO PETRA
Green Code Cleared 11/27/2019 TROY DEGUZMAN
Eng Process Fee Ord 176,300 Cleared 12/2/2019 LEE GUILBEAUX
Hydrant and Access approval Cleared 12/2/2019 GEORGE SUCHAND
Permit Cleared 12/2/2019 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 12/2/2019 LEE GUILBEAUX
Excavation more than 5-ft deep Cleared 12/4/2019 CALOSHA APPROVED
GPI Written Notices Cleared 12/4/2019 TROY DEGUZMAN
Grading Pre-Inspection Cleared 12/4/2019 TROY DEGUZMAN
Permit Cleared 12/4/2019 ADRIAN CASTRO
Trees in Parkway Cleared 12/5/2019 ADRIAN SANCHEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Adams,, Robert Charles; Lic. No.: C21234 22129 BRYANT STREET      CANOGA PARK, CA 91304

Inspector Information

JOHN KIDWELL, (818) 774-4314 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/24/2020 Partial Approval DAVID SANDOVAL
Footing/Foundation/Slab 1/24/2020 Partial Approval DAVID SANDOVAL
Underground Mechanical 1/24/2020 Partial Approval DAVID SANDOVAL
Excavation/Setback/Form/Re-Bar 2/19/2020 Partial Approval JOHN KIDWELL
Footing/Foundation/Slab 2/19/2020 Partial Approval JOHN KIDWELL
Footing/Foundation/Slab 3/25/2020 Partial Approval MICHAEL TEMPLE
Floor/Roof Diaphrgm/Shear Wall 4/22/2020 Partial Approval DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 4/30/2020 Partial Approval DAVID SANDOVAL
Pre-Inspection 5/11/2020 Approved DAVID SANDOVAL
Footing/Foundation/Slab 6/8/2020 Approved DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 7/17/2020 Corrections Issued DAVID SANDOVAL
HVAC-Rough 7/17/2020 Approved DAVID SANDOVAL
MERV13>=Rough 7/17/2020 Approved DAVID SANDOVAL
PLUMBING-Rough 7/17/2020 Approved DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 7/22/2020 Partial Approval DAVID SANDOVAL
BUILDING-Rough-Frame 8/5/2020 Partial Approval DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 8/5/2020 Approved DAVID SANDOVAL
Gas Test 8/5/2020 Partial Approval DAVID SANDOVAL
Green Building Rough 8/5/2020 Not Ready for Inspection DAVID SANDOVAL
Verify Sprinkler Sign Off 8/5/2020 Approved DAVID SANDOVAL
BUILDING-Rough-Frame 8/7/2020 Approved DAVID SANDOVAL
Green Building Rough 8/7/2020 Approved DAVID SANDOVAL
Insulation 8/7/2020 Approved DAVID SANDOVAL
Interior/Exterior Lathing 8/7/2020 Partial Approval DAVID SANDOVAL
Shower Pan 8/7/2020 Approved DAVID SANDOVAL
Drywall Nailing 8/14/2020 Approved DAVID SANDOVAL
Interior/Exterior Lathing 8/14/2020 Approved DAVID SANDOVAL
ELECTRICAL-Final 2/5/2021 No Access for Inspection DAVID SANDOVAL
Gas Test 2/5/2021 No Access for Inspection DAVID SANDOVAL
HVAC-Final 2/5/2021 No Access for Inspection DAVID SANDOVAL
PLUMBING-Final 2/5/2021 No Access for Inspection DAVID SANDOVAL
ELECTRICAL-Final 2/9/2021 Corrections Issued VINCENT HANLEY
Gas Test 2/9/2021 Not Ready for Inspection VINCENT HANLEY
HVAC-Final 2/9/2021 Corrections Issued VINCENT HANLEY
PLUMBING-Final 2/9/2021 Corrections Issued VINCENT HANLEY
ELECTRICAL-Final 2/26/2021 Approved DAVID SANDOVAL
Gas Test 2/26/2021 Approved DAVID SANDOVAL
HVAC-Final 2/26/2021 Approved DAVID SANDOVAL
PLUMBING-Final 2/26/2021 Approved DAVID SANDOVAL
Final 10/25/2021 OK to Issue CofO DAVID SANDOVAL
Green Building Final 10/25/2021 Approved DAVID SANDOVAL
MERV13>=Final 10/25/2021 Approved DAVID SANDOVAL
Reinforced Concrete Frame 10/25/2021 Approved DAVID SANDOVAL
SGSOV-Seismic Gas S/O Valve 10/25/2021 SGSOV Approved DAVID SANDOVAL
Service/Power Release 10/25/2021 Approved DAVID SANDOVAL
Smoke Detectors 10/25/2021 Approved DAVID SANDOVAL