4228 S HOBART BLVD 90062

Certificate Information: 4228 S HOBART BLVD 90062

Application / Permit
19010-20000-02408
Plan Check / Job No.
B19VN09458
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 23' x 17'-6" TWO-STORY ACCESSORY DWELLING UNIT PER AB494 AND SB229
Permit Issued
Issued on 5/6/2020
Issuing Office
Valley
Current Status
CofO Issued on 5/24/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/7/2019 APPLICANT
Green Plans Picked Up 6/25/2019 APPLICANT
Assigned to Plan Check Engineer 6/27/2019 ROSENDO MEDINA
Corrections Issued 7/1/2019 ROSENDO MEDINA
Quality Review Completed 7/3/2019 OMID HEDAYAT
Building Plans Picked Up 7/3/2019 APPLICANT
Applicant returned to address corrections 2/19/2020 ROSENDO MEDINA
Plan Check Approved 5/4/2020 ROSENDO MEDINA
Issued 5/6/2020 LADBS
CofO in Progress 10/26/2020 ROBERT MCDOWELL
Permit Finaled 5/24/2022 DEROLD HAUFF
CofO Issued 5/24/2022 DEROLD HAUFF
Permit Finaled 5/24/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/23/2019 EMIL KYUPELYAN
Eng Process Fee Ord 176,300 Cleared 12/23/2019 EMIL KYUPELYAN
Sewer availability Cleared 12/23/2019 EMIL KYUPELYAN
Hydrant and Access approval Cleared 2/3/2020 GILBERT URREA
Low Impact Development Cleared 2/3/2020 MITESH PATEL
Roof/Waste drainage to street Cleared 2/3/2020 JAMES MORALEZ
Green Code Cleared 2/13/2020 PARISA ZAHABI
Hold Cleared 6/5/2020 JASON SHEETS

Contact Information

Contractor Sergio'S & Ivan General Construction Inc; Lic. No.: 985967-B 4318 SOUTH HARVAR BLVD      LOS ANGELES, CA 90062
Engineer Zelada,, Mynor Anibal; Lic. No.: C48666 14545 VICTORY BLVD 405      VAN NUYS, CA 91411

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 6/8/2020 Approved ROBERT MCDOWELL
Footing/Foundation/Slab 6/16/2020 Approved ROBERT MCDOWELL
BUILDING-Rough-Frame 6/23/2020 Not Ready for Inspection ROBERT MCDOWELL
Green Building Rough 6/23/2020 Not Ready for Inspection ROBERT MCDOWELL
Verify Sprinkler Sign Off 6/23/2020 Not Ready for Inspection ROBERT MCDOWELL
BUILDING-Rough-Frame 7/7/2020 Corrections Issued COREY HUPP
Green Building Rough 7/7/2020 Not Ready for Inspection COREY HUPP
Verify Sprinkler Sign Off 7/7/2020 Not Ready for Inspection COREY HUPP
BUILDING-Rough-Frame 7/20/2020 Partial Approval ENRIQUE MIRELES
ELECTRICAL-Rough 7/20/2020 Not Ready for Inspection ENRIQUE MIRELES
Green Building Rough 7/20/2020 Approved ENRIQUE MIRELES
Underground Mechanical 7/20/2020 Partial Approval ENRIQUE MIRELES
Verify Sprinkler Sign Off 7/20/2020 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 7/29/2020 Approved ROBERT MCDOWELL
ELECTRICAL-Rough 7/29/2020 Approved ROBERT MCDOWELL
Gas Test 7/29/2020 Partial Approval ROBERT MCDOWELL
PLUMBING-Rough 7/29/2020 Approved ROBERT MCDOWELL
Insulation 8/4/2020 Not Ready for Inspection SABAS ALONSO
Insulation 8/10/2020 Approved SABAS ALONSO
Interior/Exterior Lathing 8/10/2020 Partial Approval SABAS ALONSO
Drywall Nailing 8/18/2020 Corrections Issued THOMAS LOGRASSO
Final 10/20/2020 Not Ready for Inspection ROBERT MCDOWELL
Green Building Final 10/20/2020 Not Ready for Inspection ROBERT MCDOWELL
SGSOV-Seismic Gas S/O Valve 10/20/2020 SGSOV Not Ready ROBERT MCDOWELL
Service/Power Release 10/20/2020 Not Ready for Inspection ROBERT MCDOWELL
Smoke Detectors 10/20/2020 Not Ready for Inspection ROBERT MCDOWELL
Drywall Nailing 10/26/2020 Approved ROBERT MCDOWELL
Final 10/26/2020 OK to Issue CofO ROBERT MCDOWELL
Green Building Final 10/26/2020 Approved ROBERT MCDOWELL
SGSOV-Seismic Gas S/O Valve 10/26/2020 SGSOV Approved ROBERT MCDOWELL
Service/Power Release 10/26/2020 Approved ROBERT MCDOWELL
Smoke Detectors 10/26/2020 Approved ROBERT MCDOWELL