4228 S HOBART BLVD 90062
Certificate Information: 4228 S HOBART BLVD 90062
- Application / Permit
- 19010-20000-02408
- Plan Check / Job No.
- B19VN09458
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 23' x 17'-6" TWO-STORY ACCESSORY DWELLING UNIT PER AB494 AND SB229
- Permit Issued
- Issued on 5/6/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/24/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/7/2019 | APPLICANT |
| Green Plans Picked Up | 6/25/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 6/27/2019 | ROSENDO MEDINA |
| Corrections Issued | 7/1/2019 | ROSENDO MEDINA |
| Quality Review Completed | 7/3/2019 | OMID HEDAYAT |
| Building Plans Picked Up | 7/3/2019 | APPLICANT |
| Applicant returned to address corrections | 2/19/2020 | ROSENDO MEDINA |
| Plan Check Approved | 5/4/2020 | ROSENDO MEDINA |
| Issued | 5/6/2020 | LADBS |
| CofO in Progress | 10/26/2020 | ROBERT MCDOWELL |
| Permit Finaled | 5/24/2022 | DEROLD HAUFF |
| CofO Issued | 5/24/2022 | DEROLD HAUFF |
| Permit Finaled | 5/24/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 12/23/2019 | EMIL KYUPELYAN |
| Eng Process Fee Ord 176,300 | Cleared | 12/23/2019 | EMIL KYUPELYAN |
| Sewer availability | Cleared | 12/23/2019 | EMIL KYUPELYAN |
| Hydrant and Access approval | Cleared | 2/3/2020 | GILBERT URREA |
| Low Impact Development | Cleared | 2/3/2020 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 2/3/2020 | JAMES MORALEZ |
| Green Code | Cleared | 2/13/2020 | PARISA ZAHABI |
| Hold | Cleared | 6/5/2020 | JASON SHEETS |
Contact Information
| Contractor | Sergio'S & Ivan General Construction Inc; Lic. No.: 985967-B | 4318 SOUTH HARVAR BLVD LOS ANGELES, CA 90062 |
| Engineer | Zelada,, Mynor Anibal; Lic. No.: C48666 | 14545 VICTORY BLVD 405 VAN NUYS, CA 91411 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 6/8/2020 | Approved | ROBERT MCDOWELL |
| Footing/Foundation/Slab | 6/16/2020 | Approved | ROBERT MCDOWELL |
| BUILDING-Rough-Frame | 6/23/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| Green Building Rough | 6/23/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| Verify Sprinkler Sign Off | 6/23/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| BUILDING-Rough-Frame | 7/7/2020 | Corrections Issued | COREY HUPP |
| Green Building Rough | 7/7/2020 | Not Ready for Inspection | COREY HUPP |
| Verify Sprinkler Sign Off | 7/7/2020 | Not Ready for Inspection | COREY HUPP |
| BUILDING-Rough-Frame | 7/20/2020 | Partial Approval | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 7/20/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| Green Building Rough | 7/20/2020 | Approved | ENRIQUE MIRELES |
| Underground Mechanical | 7/20/2020 | Partial Approval | ENRIQUE MIRELES |
| Verify Sprinkler Sign Off | 7/20/2020 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 7/29/2020 | Approved | ROBERT MCDOWELL |
| ELECTRICAL-Rough | 7/29/2020 | Approved | ROBERT MCDOWELL |
| Gas Test | 7/29/2020 | Partial Approval | ROBERT MCDOWELL |
| PLUMBING-Rough | 7/29/2020 | Approved | ROBERT MCDOWELL |
| Insulation | 8/4/2020 | Not Ready for Inspection | SABAS ALONSO |
| Insulation | 8/10/2020 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 8/10/2020 | Partial Approval | SABAS ALONSO |
| Drywall Nailing | 8/18/2020 | Corrections Issued | THOMAS LOGRASSO |
| Final | 10/20/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| Green Building Final | 10/20/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| SGSOV-Seismic Gas S/O Valve | 10/20/2020 | SGSOV Not Ready | ROBERT MCDOWELL |
| Service/Power Release | 10/20/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| Smoke Detectors | 10/20/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| Drywall Nailing | 10/26/2020 | Approved | ROBERT MCDOWELL |
| Final | 10/26/2020 | OK to Issue CofO | ROBERT MCDOWELL |
| Green Building Final | 10/26/2020 | Approved | ROBERT MCDOWELL |
| SGSOV-Seismic Gas S/O Valve | 10/26/2020 | SGSOV Approved | ROBERT MCDOWELL |
| Service/Power Release | 10/26/2020 | Approved | ROBERT MCDOWELL |
| Smoke Detectors | 10/26/2020 | Approved | ROBERT MCDOWELL |