2555 S THURMAN AVE 90016
Certificate Information: 2555 S THURMAN AVE 90016
- Application / Permit
- 19010-20000-02372
- Plan Check / Job No.
- B19VN09272
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- NEW 3 STORY 4 UNIT APARTMENT BUILDING WITH ROOF DECK; EQUIPPED WITH NFPA 13-R FIRE SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 11/6/2020
- Issuing Office
- Current Status
- CofO Issued on 6/7/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/5/2019 | APPLICANT |
| Disabled Access Plans Picked Up | 7/12/2019 | APPLICANT |
| Green Plans Picked Up | 7/12/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 7/18/2019 | SELLA BENYAMIN |
| Corrections Issued | 7/25/2019 | SELLA BENYAMIN |
| Quality Review Completed | 8/6/2019 | STEVEN KIM |
| Building Plans Picked Up | 8/8/2019 | APPLICANT |
| Applicant returned to address corrections | 12/24/2019 | SELLA BENYAMIN |
| Applicant returned to address corrections | 2/13/2020 | SELLA BENYAMIN |
| Applicant returned to address corrections | 3/12/2020 | SELLA BENYAMIN |
| Plan Check Approved | 10/7/2020 | SELLA BENYAMIN |
| Issued | 11/6/2020 | APPLICANT |
| CofO in Progress | 6/7/2024 | EDWIN GREGORYONA |
| CofO Issued | 6/7/2024 | RAFAEL ESPINOZA |
| Permit Finaled | 6/7/2024 | RAFAEL ESPINOZA |
Permit Application Clearance Information
| Highway dedication | Cleared | 8/14/2019 | ELAINE LEI |
| Green Code | Cleared | 11/7/2019 | MICHAEL AYERS |
| DAS Clearance | Cleared | 12/23/2019 | SELLA BENYAMIN |
| Address approval | Cleared | 2/4/2020 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 2/4/2020 | LEE GUILBEAUX |
| Frnt yard landscape/Water mgmt | Cleared | 2/4/2020 | PABLO ESTRADA |
| Opn space landscape/Water mgmt | Cleared | 2/4/2020 | PABLO ESTRADA |
| Permit | Cleared | 2/4/2020 | LEE GUILBEAUX |
| Building over 3-story or 36-ft | Cleared | 2/13/2020 | CALOSHA APPROVED |
| Sewer availability | Cleared | 2/20/2020 | JUAN ASHTON |
| Trees in Parkway | Cleared | 2/20/2020 | JOHN KIM |
| Hydrant and Access approval | Cleared | 8/5/2020 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 10/8/2020 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 11/5/2020 | JUAN ASHTON |
Contact Information
| Contractor | Lum Raymond Construction; Lic. No.: 720927-B | 4625 WEST 64TH STREET LOS ANGELES, CA 90043 |
| Engineer | Bustillos, Portillo, Alejandro Ivan; Lic. No.: C87257 | 4749 W 169TH STREET LAWNDALE, CA 90260 |
Inspector Information
| MARTIN TAVITIAN, (213) 482-7357 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/23/2021 | Off-Hour Fees Due | |
| Footing/Foundation/Slab | 4/30/2021 | Partial Inspection | EDWIN GREGORYONA |
| Footing/Foundation/Slab | 5/17/2021 | Partial Approval | EDWIN GREGORYONA |
| Floor/Roof Diaphrgm/Shear Wall | 7/8/2021 | Partial Approval | RUSSELL BONVOULOIR |
| Floor/Roof Diaphrgm/Shear Wall | 7/27/2021 | Partial Approval | RUSSELL BONVOULOIR |
| Green Building Rough | 7/27/2021 | Not Ready for Inspection | RUSSELL BONVOULOIR |
| Verify Sprinkler Sign Off | 7/27/2021 | Not Ready for Inspection | RUSSELL BONVOULOIR |
| Wood Frame | 7/27/2021 | Partial Approval | RUSSELL BONVOULOIR |
| Floor/Roof Diaphrgm/Shear Wall | 8/25/2021 | Partial Approval | RUSSELL BONVOULOIR |
| Floor/Roof Diaphrgm/Shear Wall | 12/17/2021 | Partial Approval | RUSSELL BONVOULOIR |
| Green Building Rough | 12/17/2021 | Partial Inspection | RUSSELL BONVOULOIR |
| Verify Sprinkler Sign Off | 12/17/2021 | Partial Inspection | RUSSELL BONVOULOIR |
| Wood Frame | 12/17/2021 | Partial Approval | RUSSELL BONVOULOIR |
| Green Building Rough | 4/29/2022 | Conditional Approval | DARRYL ARNOLD |
| Verify Sprinkler Sign Off | 4/29/2022 | Conditional Approval | DARRYL ARNOLD |
| Wood Frame | 4/29/2022 | Conditional Approval | DARRYL ARNOLD |
| Green Building Rough | 5/24/2022 | Partial Inspection | RUSSELL BONVOULOIR |
| Verify Sprinkler Sign Off | 5/24/2022 | Partial Inspection | RUSSELL BONVOULOIR |
| Wood Frame | 5/24/2022 | Partial Inspection | RUSSELL BONVOULOIR |
| Insulation | 6/6/2022 | Partial Approval | RUSSELL BONVOULOIR |
| Drywall Nailing | 6/22/2022 | Partial Approval | EDWIN GREGORYONA |
| Drywall Nailing | 6/29/2022 | Partial Approval | RUSSELL BONVOULOIR |
| Interior/Exterior Lathing | 6/29/2022 | Approved | RUSSELL BONVOULOIR |
| Insulation | 9/26/2022 | Approved | RUSSELL BONVOULOIR |
| Drywall Nailing | 11/29/2022 | Approved | RUSSELL BONVOULOIR |
| Interior/Exterior Lathing | 12/7/2022 | Partial Approval | EDWIN GREGORYONA |
| Special/Order Compliance | 2/14/2023 | Approved | DARRYL ARNOLD |
| Final | 3/5/2024 | Partial Inspection | EDWIN GREGORYONA |
| Footing/Foundation/Slab | 3/5/2024 | Approved | EDWIN GREGORYONA |
| Green Building Final | 3/5/2024 | Approved | EDWIN GREGORYONA |
| Green Building Rough | 3/5/2024 | Approved | EDWIN GREGORYONA |
| SGSOV-Seismic Gas S/O Valve | 3/5/2024 | SGSOV Approved | EDWIN GREGORYONA |
| Smoke Detectors | 3/5/2024 | Approved | EDWIN GREGORYONA |
| Verify Sprinkler Sign Off | 3/5/2024 | Approved | EDWIN GREGORYONA |
| Wood Frame | 3/5/2024 | Approved | EDWIN GREGORYONA |
| Final | 4/25/2024 | Partial Inspection | EDWIN GREGORYONA |
| Final | 6/7/2024 | OK to Issue CofO | EDWIN GREGORYONA |