2553 S THURMAN AVE 90016

Certificate Information: 2553 S THURMAN AVE 90016

Application / Permit
19010-20000-02371
Plan Check / Job No.
B19VN09272
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW 3 STORY 4-UNIT APARTMENT BUILDING WITH ROOF DECK; EQUIPPED WITH NFPA 13-R FIRE SPRINKLERS THROUGHOUT
Permit Issued
Issued on 10/30/2020
Issuing Office
Current Status
CofO Issued on 6/7/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/5/2019 APPLICANT
Disabled Access Plans Picked Up 7/12/2019 APPLICANT
Green Plans Picked Up 7/12/2019 APPLICANT
Assigned to Plan Check Engineer 7/18/2019 SELLA BENYAMIN
Corrections Issued 7/25/2019 SELLA BENYAMIN
Quality Review Completed 8/6/2019 STEVEN KIM
Building Plans Picked Up 8/8/2019 APPLICANT
Applicant returned to address corrections 12/24/2019 SELLA BENYAMIN
Applicant returned to address corrections 2/13/2020 SELLA BENYAMIN
Applicant returned to address corrections 3/12/2020 SELLA BENYAMIN
Plan Check Approved 10/7/2020 SELLA BENYAMIN
Issued 10/30/2020 APPLICANT
CofO in Progress 6/3/2024 EDWIN GREGORYONA
CofO Issued 6/7/2024 RAFAEL ESPINOZA
Permit Finaled 6/7/2024 RAFAEL ESPINOZA

Permit Application Clearance Information

Highway dedication Cleared 8/14/2019 ELAINE LEI
Green Code Cleared 11/7/2019 MICHAEL AYERS
DAS Clearance Cleared 12/23/2019 SELLA BENYAMIN
Address approval Cleared 2/4/2020 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 2/4/2020 LEE GUILBEAUX
Frnt yard landscape/Water mgmt Cleared 2/4/2020 PABLO ESTRADA
Opn space landscape/Water mgmt Cleared 2/4/2020 PABLO ESTRADA
Permit Cleared 2/4/2020 LEE GUILBEAUX
Building over 3-story or 36-ft Cleared 2/13/2020 CALOSHA APPROVED
Sewer availability Cleared 2/20/2020 JUAN ASHTON
Trees in Parkway Cleared 2/20/2020 JOHN KIM
Hydrant and Access approval Cleared 4/7/2020 ROBERT DUFF
Low Impact Development Cleared 9/2/2020 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 10/29/2020 JUAN ASHTON

Contact Information

Contractor Lum Raymond Construction; Lic. No.: 720927-B 4625 WEST 64TH STREET      LOS ANGELES, CA 90043
Engineer Bustillos, Portillo, Alejandro Ivan; Lic. No.: C87257 4749 W 169TH STREET      LAWNDALE, CA 90260

Inspector Information

MARTIN TAVITIAN, (213) 482-7357 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/14/2021 Partial Approval LARRY ARNICK
Footing/Foundation/Slab 1/26/2021 Approved LARRY ARNICK
Deputy Drilled-In Anchors 5/6/2021 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 5/20/2021 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 5/21/2021 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 7/8/2021 Partial Approval RUSSELL BONVOULOIR
Floor/Roof Diaphrgm/Shear Wall 7/27/2021 Partial Approval RUSSELL BONVOULOIR
Green Building Rough 7/27/2021 Not Ready for Inspection RUSSELL BONVOULOIR
Verify Sprinkler Sign Off 7/27/2021 Not Ready for Inspection RUSSELL BONVOULOIR
Wood Frame 7/27/2021 Partial Approval RUSSELL BONVOULOIR
Floor/Roof Diaphrgm/Shear Wall 8/25/2021 Partial Approval RUSSELL BONVOULOIR
Special/Order Compliance 9/8/2021 Corrections Issued RUSSELL BONVOULOIR
Special/Order Compliance 9/22/2021 Partial Inspection RUSSELL BONVOULOIR
Special/Order Compliance 10/18/2021 Partial Inspection RUSSELL BONVOULOIR
Floor/Roof Diaphrgm/Shear Wall 12/17/2021 Partial Approval RUSSELL BONVOULOIR
Green Building Rough 12/17/2021 Partial Inspection RUSSELL BONVOULOIR
Verify Sprinkler Sign Off 12/17/2021 Partial Inspection RUSSELL BONVOULOIR
Wood Frame 12/17/2021 Partial Approval RUSSELL BONVOULOIR
Green Building Rough 1/21/2022 Partial Inspection RUSSELL BONVOULOIR
Verify Sprinkler Sign Off 1/21/2022 Partial Approval RUSSELL BONVOULOIR
Wood Frame 1/21/2022 Partial Inspection RUSSELL BONVOULOIR
Green Building Rough 3/1/2022 Partial Inspection RUSSELL BONVOULOIR
Verify Sprinkler Sign Off 3/1/2022 Partial Inspection RUSSELL BONVOULOIR
Wood Frame 3/1/2022 Not Ready for Inspection RUSSELL BONVOULOIR
Green Building Rough 3/23/2022 Partial Inspection RUSSELL BONVOULOIR
Verify Sprinkler Sign Off 3/23/2022 Partial Inspection RUSSELL BONVOULOIR
Wood Frame 3/23/2022 Partial Inspection RUSSELL BONVOULOIR
Insulation 4/7/2022 Partial Approval RUSSELL BONVOULOIR
Drywall Nailing 4/20/2022 Partial Approval RUSSELL BONVOULOIR
Drywall Nailing 4/21/2022 Not Ready for Inspection DARRYL ARNOLD
Insulation 5/6/2022 Not Ready for Inspection RUSSELL BONVOULOIR
Interior/Exterior Lathing 5/12/2022 Approved RUSSELL BONVOULOIR
Drywall Nailing 6/29/2022 Partial Approval RUSSELL BONVOULOIR
Insulation 8/30/2022 Approved RUSSELL BONVOULOIR
Drywall Nailing 9/20/2022 Approved RUSSELL BONVOULOIR
Interior/Exterior Lathing 11/14/2022 Approved RUSSELL BONVOULOIR
Final 3/4/2024 Partial Inspection EDWIN GREGORYONA
Green Building Final 3/4/2024 Approved EDWIN GREGORYONA
Green Building Rough 3/4/2024 Approved EDWIN GREGORYONA
SGSOV-Seismic Gas S/O Valve 3/4/2024 SGSOV Approved EDWIN GREGORYONA
Smoke Detectors 3/4/2024 Approved EDWIN GREGORYONA
Verify Sprinkler Sign Off 3/4/2024 Approved EDWIN GREGORYONA
Wood Frame 3/4/2024 Approved EDWIN GREGORYONA
Final 4/25/2024 Partial Inspection EDWIN GREGORYONA
Final 6/3/2024 OK to Issue CofO EDWIN GREGORYONA