13717 W LOUVRE ST 91331
Certificate Information: 13717 W LOUVRE ST 91331
- Application / Permit
- 19010-20000-02348
- Plan Check / Job No.
- B19VN09171
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW FULLY SPRINKLERED 50'-0" X 30'-0" SINGLE FAMILY DWELLING PER WFPP. SEE COMMENTS.
- Permit Issued
- Issued on 11/6/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/27/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/5/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 6/27/2019 | JEROME MAGAT PALMA |
| Corrections Issued | 7/1/2019 | JEROME MAGAT PALMA |
| Quality Review Completed | 7/1/2019 | ABDUL CHEGENI |
| Building Plans Picked Up | 7/2/2019 | APPLICANT |
| Green Plans Picked Up | 8/2/2019 | APPLICANT |
| Plan Check Approved | 11/1/2019 | JEROME MAGAT PALMA |
| Issued | 11/6/2019 | LADBS |
| CofO in Progress | 9/26/2022 | MICHEL ABAJAN |
| CofO Issued | 9/27/2022 | RONALD MYRICK |
| Permit Finaled | 9/27/2022 | RONALD MYRICK |
Permit Application Clearance Information
| Address approval | Cleared | 7/12/2019 | JOHN LIN |
| Eng Process Fee Ord 176,300 | Cleared | 7/12/2019 | JOHN LIN |
| Permit | Cleared | 7/12/2019 | JOHN LIN |
| Sewer availability | Cleared | 7/12/2019 | JOHN LIN |
| Low Impact Development | Cleared | 10/2/2019 | ANDRES COVARRUBIAS |
| Green Code | Cleared | 10/10/2019 | DAVID MATSON |
| Hydrant and Access approval | Cleared | 10/23/2019 | GEORGE SUCHAND |
| Roof/Waste drainage to street | Cleared | 11/1/2019 | ADRIAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/6/2019 | Approved | MICHEL ABAJAN |
| METHANE-Barrier | 12/6/2019 | Approved | MICHEL ABAJAN |
| METHANE-Subgrade | 12/6/2019 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 1/3/2020 | Partial Approval | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/21/2020 | Partial Approval | MICHEL ABAJAN |
| Green Building Rough | 1/21/2020 | Not Ready for Inspection | MICHEL ABAJAN |
| METHANE-Rough | 1/21/2020 | Approved | MICHEL ABAJAN |
| Verify Sprinkler Sign Off | 1/21/2020 | Not Ready for Inspection | MICHEL ABAJAN |
| ELECTRICAL-Rough | 2/11/2020 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/11/2020 | Partial Approval | MICHEL ABAJAN |
| PLUMBING-Rough | 2/11/2020 | Approved | MICHEL ABAJAN |
| Shower Pan | 2/11/2020 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 2/20/2020 | Approved | MICHEL ABAJAN |
| Green Building Rough | 2/20/2020 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 2/20/2020 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 2/20/2020 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 2/20/2020 | Approved | MICHEL ABAJAN |
| Verify Sprinkler Sign Off | 2/20/2020 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 2/24/2020 | Approved | MICHEL ABAJAN |
| Final | 7/9/2021 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 7/9/2021 | Not Ready for Inspection | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 7/9/2021 | SGSOV Not Ready | MICHEL ABAJAN |
| Service/Power Release | 7/9/2021 | Partial Inspection | MICHEL ABAJAN |
| Smoke Detectors | 7/9/2021 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 8/2/2022 | Approved | MICHEL ABAJAN |
| Final | 8/2/2022 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 8/2/2022 | Approved | MICHEL ABAJAN |
| HVAC-Final | 8/2/2022 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 8/2/2022 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 8/2/2022 | SGSOV Approved | MICHEL ABAJAN |
| Service/Power Release | 8/2/2022 | Not Ready for Inspection | MICHEL ABAJAN |
| Final | 8/8/2022 | Not Ready for Inspection | MICHEL ABAJAN |
| Service/Power Release | 8/8/2022 | Not Ready for Inspection | MICHEL ABAJAN |
| Final | 9/21/2022 | Not Ready for Inspection | MICHEL ABAJAN |
| Service/Power Release | 9/21/2022 | Not Ready for Inspection | MICHEL ABAJAN |
| ELECTRICAL-Final | 9/26/2022 | Approved | MICHEL ABAJAN |
| Final | 9/26/2022 | OK to Issue CofO | MICHEL ABAJAN |
| HVAC-Final | 9/26/2022 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 9/26/2022 | Approved | MICHEL ABAJAN |
| Service/Power Release | 9/26/2022 | Approved | MICHEL ABAJAN |