1905 N GRACE AVE 90068

Certificate Information: 1905 N GRACE AVE 90068

Application / Permit
19010-20000-02346
Plan Check / Job No.
B19VN09166
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
RELOCATE EXISTING GARAGE
Permit Issued
Issued on 3/17/2020
Issuing Office
Valley
Current Status
Permit Finaled on 8/31/2022

Permit Application Status History

Submitted 6/4/2019 APPLICANT
Assigned to Plan Check Engineer 7/11/2019 SELLA BENYAMIN
Green Plans Picked Up 7/15/2019 APPLICANT
Corrections Issued 7/18/2019 SELLA BENYAMIN
Quality Review Completed 7/23/2019 STEVEN KIM
Building Plans Picked Up 7/25/2019 APPLICANT
Plan Check Approved 1/15/2020 SELLA BENYAMIN
Issued 3/17/2020 LADBS
Permit Finaled 8/30/2022 STUART CHAPMAN

Permit Application Clearance Information

Green Code Cleared 1/10/2020 MICHAEL AYERS
"Q" conditions Cleared 1/14/2020 DAISY BENICIA
Eng Process Fee Ord 176,300 Cleared 1/14/2020 GABRIEL ROBLES
HPOZ Cleared 1/14/2020 LAMBERT GIESSINGER
Miscellaneous Cleared 1/14/2020 DAISY BENICIA
Roof/Waste drainage to street Cleared 1/14/2020 GABRIEL ROBLES
Tract Map conditions Cleared 1/14/2020 DAISY BENICIA

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 6/15/2020 Partial Inspection BRIAN SULLIVAN
Footing/Foundation/Slab 8/19/2020 Corrections Issued BRIAN SULLIVAN
Footing/Foundation/Slab 8/25/2020 Approved BRIAN SULLIVAN
ELECTRICAL-Rough 6/2/2021 Corrections Issued SCOTT FINNILA
PLUMBING-Rough 6/2/2021 Corrections Issued SCOTT FINNILA
ELECTRICAL-Rough 6/8/2021 Approved SCOTT FINNILA
Green Building Rough 6/8/2021 Corrections Issued SCOTT FINNILA
HVAC-Rough 6/8/2021 Corrections Issued SCOTT FINNILA
PLUMBING-Rough 6/8/2021 Approved SCOTT FINNILA
ELECTRICAL-Rough 6/11/2021 Partial Inspection SCOTT FINNILA
Interior/Exterior Lathing 11/16/2021 Partial Approval SCOTT FINNILA
Shower Pan 11/16/2021 Approved SCOTT FINNILA
BUILDING-Rough-Frame 8/30/2022 Approved STUART CHAPMAN
Final 8/30/2022 Permit Finaled STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 8/30/2022 SGSOV Approved STUART CHAPMAN
Smoke Detectors 8/30/2022 Approved STUART CHAPMAN