11712 N SPROULE AVE 91331

Certificate Information: 11712 N SPROULE AVE 91331

Application / Permit
19010-20000-02294
Plan Check / Job No.
B19VN08988
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 41'--5" X 24'-2" IRREGULAR SHAPE ACCESSORY DWELLING UNIT WITH 5'-0" X 4'-0" COVERED PATIO PER AB 494 AND SB 229. ALL WORK DONE PERF WFPP.
Permit Issued
Issued on 6/25/2020
Issuing Office
Current Status
CofO Issued on 2/6/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/31/2019 APPLICANT
Green Plans Picked Up 7/15/2019 APPLICANT
Assigned to Plan Check Engineer 7/18/2019 ROSENDO MEDINA
Corrections Issued 7/22/2019 ROSENDO MEDINA
Quality Review Completed 7/22/2019 OMID HEDAYAT
Building Plans Picked Up 7/23/2019 APPLICANT
Applicant returned to address corrections 3/12/2020 ROSENDO MEDINA
Plan Check Approved 6/10/2020 ROSENDO MEDINA
Issued 6/25/2020 APPLICANT
CofO in Progress 11/17/2020 MICHEL ABAJAN
Permit Finaled 2/6/2021 MICHAEL SMITH
CofO Issued 2/6/2021 MICHAEL SMITH
Permit Finaled 2/6/2021 MICHAEL SMITH

Permit Application Clearance Information

Hydrant and Access approval Cleared 10/31/2019 GEORGE SUCHAND
Address approval Cleared 4/15/2020 GABRIEL ROBLES
Green Code Cleared 4/15/2020 MICHAEL AYERS
Low Impact Development Cleared 5/27/2020 JORGE MEJIA LEMUS
Eng Process Fee Ord 176,300 Cleared 5/28/2020 GABRIEL ROBLES
Roof/Waste drainage to street Cleared 5/28/2020 GABRIEL ROBLES
Sewer availability Cleared 5/28/2020 GABRIEL ROBLES
Clean Up Green Up Cleared 6/3/2020 LAUREN PADICK

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/30/2020 Partial Approval DANIEL ORRANTE
Sewer 6/30/2020 Approved DANIEL ORRANTE
Footing/Foundation/Slab 7/2/2020 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 7/16/2020 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 7/30/2020 Not Ready for Inspection JOHN HAYES
ELECTRICAL-Rough 7/30/2020 Not Ready for Inspection JOHN HAYES
Green Building Rough 7/30/2020 Not Ready for Inspection JOHN HAYES
HVAC-Rough 7/30/2020 Not Ready for Inspection JOHN HAYES
MERV13>=Rough 7/30/2020 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 7/30/2020 Not Ready for Inspection JOHN HAYES
Verify Sprinkler Sign Off 7/30/2020 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 8/3/2020 Approved MICHEL ABAJAN
Green Building Rough 8/3/2020 Approved MICHEL ABAJAN
Interior/Exterior Lathing 8/3/2020 Approved MICHEL ABAJAN
MERV13>=Rough 8/3/2020 Approved MICHEL ABAJAN
Rough-Elec/Plmb/HVAC 8/3/2020 Approved MICHEL ABAJAN
Verify Sprinkler Sign Off 8/3/2020 Approved MICHEL ABAJAN
Insulation 8/5/2020 Approved MICHEL ABAJAN
Interior/Exterior Lathing 8/5/2020 Approved MICHEL ABAJAN
Drywall Nailing 8/10/2020 Approved MICHEL ABAJAN
Insulation 8/10/2020 Approved MICHEL ABAJAN
Interior/Exterior Lathing 8/27/2020 Approved BEAU COLLINS
Shower Pan 8/27/2020 Not Ready for Inspection BEAU COLLINS
Interior/Exterior Lathing 9/1/2020 Approved MICHEL ABAJAN
Shower Pan 9/1/2020 Approved MICHEL ABAJAN
ELECTRICAL-Final 10/22/2020 Approved MICHEL ABAJAN
Final 10/22/2020 Corrections Issued MICHEL ABAJAN
Gas Test 10/22/2020 Approved MICHEL ABAJAN
Green Building Final 10/22/2020 Approved MICHEL ABAJAN
HVAC-Final 10/22/2020 Approved MICHEL ABAJAN
MERV13>=Final 10/22/2020 Approved MICHEL ABAJAN
PLUMBING-Final 10/22/2020 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 10/22/2020 SGSOV Not Ready MICHEL ABAJAN
Service/Power Release 10/22/2020 Approved MICHEL ABAJAN
Smoke Detectors 10/22/2020 Approved MICHEL ABAJAN
Final 10/28/2020 Not Ready for Inspection MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 10/28/2020 SGSOV Approved MICHEL ABAJAN
Final 11/17/2020 OK to Issue CofO MICHEL ABAJAN