12846 W HIGHWOOD ST 90049

Certificate Information: 12846 W HIGHWOOD ST 90049

Application / Permit
19010-20000-02291
Plan Check / Job No.
B19VN08970
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 124' X 84' (2) STORY SINGLE FAMILY DWELLING WITH BASEMENT AND ATTACHED GARAGE; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
Permit Issued
Issued on 12/9/2019
Issuing Office
Valley
Current Status
CofO Issued on 4/18/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/31/2019 APPLICANT
Assigned to Plan Check Engineer 7/11/2019 SELLA BENYAMIN
Green Plans Picked Up 7/15/2019 APPLICANT
Corrections Issued 7/16/2019 SELLA BENYAMIN
Quality Review Completed 7/18/2019 STEVEN KIM
Building Plans Picked Up 7/19/2019 APPLICANT
Applicant returned to address corrections 11/6/2019 SELLA BENYAMIN
Plan Check Approved 12/3/2019 SELLA BENYAMIN
Issued 12/9/2019 LADBS
CofO in Progress 4/17/2023 KEVIN SARGSYAN
Permit Finaled 4/18/2023 DANIEL ORRANTE
CofO Issued 4/18/2023 DANIEL ORRANTE
Permit Finaled 4/18/2023 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/8/2019 SAFA JAVANMARDI
Permit Cleared 8/8/2019 SAFA JAVANMARDI
Sewer availability Cleared 8/8/2019 GABRIEL ROBLES
Green Code Cleared 9/26/2019 MICHAEL AYERS
Low Impact Development Cleared 9/26/2019 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 9/26/2019 MARKOS PEREZ-BRAN
Hydrant and Access approval Cleared 10/8/2019 GEORGE SUCHAND
Miscellaneous Cleared 10/9/2019 HERMINIGILDO AGUSTIN
GPI Written Notices Cleared 11/6/2019 SELLA BENYAMIN
Grading Pre-Inspection Cleared 11/6/2019 SELLA BENYAMIN

Contact Information

Contractor Owner-Builder       ,
Engineer Pirbadian,, Amir; Lic. No.: C72413 5435 BALBOA BLVD 214      ENCINO, CA 91342

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/19/2019 No Access for Inspection TIM CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 3/18/2020 No Access for Inspection TIM CHRISTENSEN
Gas Test 4/27/2020 Not Ready for Inspection TIM CHRISTENSEN
Footing/Foundation/Slab 10/1/2020 Partial Approval TIM CHRISTENSEN
Underground Mechanical 10/2/2020 Approved TIM CHRISTENSEN
Reinforced Concrete Frame 10/20/2020 Partial Approval TIM CHRISTENSEN
Deputy Shotcrete 10/21/2020 Conditional Approval TIM CHRISTENSEN
Deputy Shotcrete 10/22/2020 Conditional Approval TIM CHRISTENSEN
Deputy Shotcrete 10/23/2020 Conditional Approval TIM CHRISTENSEN
PLUMBING-Rough 11/19/2020 Corrections Issued KEVIN SARGSYAN
Underground Mechanical 11/23/2020 Not Ready for Inspection OGANES TARAKHCHYAN
Footing/Foundation/Slab 12/16/2020 Approved MICHAEL PELHAM
Reinforced Concrete Frame 2/3/2021 Partial Approval JUAN VALENZUELA
Masonry Wall/Backfill 3/1/2021 Not Ready for Inspection JUAN VALENZUELA
Deputy Steel/Welding 3/4/2021 Approved ROBERT SHELLY
Deputy Steel/Welding 3/5/2021 Approved ROBERT SHELLY
Floor/Roof Diaphrgm/Shear Wall 3/23/2021 Partial Approval JUAN VALENZUELA
Footing/Foundation/Slab 4/5/2021 Partial Approval JUAN VALENZUELA
Footing/Foundation/Slab 4/9/2021 Partial Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 4/30/2021 Partial Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 6/9/2021 Corrections Issued JUAN VALENZUELA
Deputy Steel/Welding 7/14/2021 Conditional Approval JUAN VALENZUELA
Deputy Wood Construction 9/10/2021 Conditional Approval JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 10/20/2021 Partial Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 11/15/2021 Partial Approval KENNETH NAGLE
PLUMBING-Rough 1/10/2022 Partial Inspection JUAN VALENZUELA
PLUMBING-Rough 1/19/2022 Partial Approval JUAN VALENZUELA
Underground Mechanical 2/9/2022 Partial Approval JUAN VALENZUELA
ELECTRICAL-Rough 2/11/2022 Partial Approval JUAN VALENZUELA
HVAC-Rough 2/18/2022 Partial Approval JUAN VALENZUELA
PLUMBING-Rough 2/23/2022 Partial Inspection JUAN VALENZUELA
Deputy Drilled-In Anchors 3/3/2022 Conditional Approval JUAN VALENZUELA
Deputy Wood Construction 3/3/2022 Conditional Approval JUAN VALENZUELA
Sewer 3/3/2022 Approved JUAN VALENZUELA
Underground Mechanical 3/3/2022 Partial Approval JUAN VALENZUELA
PLUMBING-Rough 3/10/2022 Conditional Approval MICHAEL PELHAM
ELECTRICAL-Rough 3/11/2022 Approved JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 3/11/2022 Partial Approval JOHN KIDWELL
HVAC-Rough 3/11/2022 Approved JOHN KIDWELL
BUILDING-Rough-Frame 3/14/2022 Not Ready for Inspection JUAN VALENZUELA
Green Building Rough 3/14/2022 Not Ready for Inspection JUAN VALENZUELA
PLUMBING-Rough 3/14/2022 Corrections Issued JUAN VALENZUELA
Shower Pan 3/14/2022 Partial Approval JUAN VALENZUELA
Verify Sprinkler Sign Off 3/14/2022 Approved JUAN VALENZUELA
Special/Order Compliance 3/15/2022 Partial Inspection PATRICK QUALEY
Wood Frame 3/15/2022 Partial Inspection ANDREW NAVE
BUILDING-Rough-Frame 3/25/2022 Approved JUAN VALENZUELA
Green Building Rough 3/25/2022 Approved JUAN VALENZUELA
Insulation 3/25/2022 Approved JUAN VALENZUELA
Interior/Exterior Lathing 3/25/2022 Partial Approval JUAN VALENZUELA
Shower Pan 3/25/2022 Partial Approval JUAN VALENZUELA
Interior/Exterior Lathing 4/5/2022 Partial Approval JOHN KIDWELL
Interior/Exterior Lathing 4/13/2022 Partial Approval JUAN VALENZUELA
Drywall Nailing 4/20/2022 Approved KRISTEN CAUSEY
Gas Test 10/26/2022 Approved JUAN VALENZUELA
ELECTRICAL-Final 11/29/2022 Partial Inspection JUAN VALENZUELA
PLUMBING-Final 1/10/2023 Corrections Issued CLAYTON GRAHAM
PLUMBING-Final 1/27/2023 Approved KEVIN SARGSYAN
ELECTRICAL-Final 1/31/2023 Corrections Issued KEVIN SARGSYAN
ELECTRICAL-Final 2/2/2023 Not Ready for Inspection KEVIN SARGSYAN
Footing/Foundation/Slab 2/2/2023 Approved KEVIN SARGSYAN
Green Building Final 2/2/2023 Corrections Issued KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 2/2/2023 SGSOV Approved KEVIN SARGSYAN
Smoke Detectors 2/2/2023 Approved KEVIN SARGSYAN
ELECTRICAL-Final 2/9/2023 Approved MICHAEL PELHAM
HVAC-Final 2/10/2023 Partial Approval OGANES TARAKHCHYAN
HVAC-Final 2/14/2023 Approved OGANES TARAKHCHYAN
Final 2/21/2023 Corrections Issued KEVIN SARGSYAN
Green Building Final 2/21/2023 Approved KEVIN SARGSYAN
Service/Power Release 3/9/2023 Approved KENNETH NAGLE
Final 4/17/2023 OK to Issue CofO KEVIN SARGSYAN