12846 W HIGHWOOD ST 90049
Certificate Information: 12846 W HIGHWOOD ST 90049
- Application / Permit
- 19010-20000-02291
- Plan Check / Job No.
- B19VN08970
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 124' X 84' (2) STORY SINGLE FAMILY DWELLING WITH BASEMENT AND ATTACHED GARAGE; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 12/9/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/18/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/31/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 7/11/2019 | SELLA BENYAMIN |
| Green Plans Picked Up | 7/15/2019 | APPLICANT |
| Corrections Issued | 7/16/2019 | SELLA BENYAMIN |
| Quality Review Completed | 7/18/2019 | STEVEN KIM |
| Building Plans Picked Up | 7/19/2019 | APPLICANT |
| Applicant returned to address corrections | 11/6/2019 | SELLA BENYAMIN |
| Plan Check Approved | 12/3/2019 | SELLA BENYAMIN |
| Issued | 12/9/2019 | LADBS |
| CofO in Progress | 4/17/2023 | KEVIN SARGSYAN |
| Permit Finaled | 4/18/2023 | DANIEL ORRANTE |
| CofO Issued | 4/18/2023 | DANIEL ORRANTE |
| Permit Finaled | 4/18/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/8/2019 | SAFA JAVANMARDI |
| Permit | Cleared | 8/8/2019 | SAFA JAVANMARDI |
| Sewer availability | Cleared | 8/8/2019 | GABRIEL ROBLES |
| Green Code | Cleared | 9/26/2019 | MICHAEL AYERS |
| Low Impact Development | Cleared | 9/26/2019 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 9/26/2019 | MARKOS PEREZ-BRAN |
| Hydrant and Access approval | Cleared | 10/8/2019 | GEORGE SUCHAND |
| Miscellaneous | Cleared | 10/9/2019 | HERMINIGILDO AGUSTIN |
| GPI Written Notices | Cleared | 11/6/2019 | SELLA BENYAMIN |
| Grading Pre-Inspection | Cleared | 11/6/2019 | SELLA BENYAMIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Pirbadian,, Amir; Lic. No.: C72413 | 5435 BALBOA BLVD 214 ENCINO, CA 91342 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/19/2019 | No Access for Inspection | TIM CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 3/18/2020 | No Access for Inspection | TIM CHRISTENSEN |
| Gas Test | 4/27/2020 | Not Ready for Inspection | TIM CHRISTENSEN |
| Footing/Foundation/Slab | 10/1/2020 | Partial Approval | TIM CHRISTENSEN |
| Underground Mechanical | 10/2/2020 | Approved | TIM CHRISTENSEN |
| Reinforced Concrete Frame | 10/20/2020 | Partial Approval | TIM CHRISTENSEN |
| Deputy Shotcrete | 10/21/2020 | Conditional Approval | TIM CHRISTENSEN |
| Deputy Shotcrete | 10/22/2020 | Conditional Approval | TIM CHRISTENSEN |
| Deputy Shotcrete | 10/23/2020 | Conditional Approval | TIM CHRISTENSEN |
| PLUMBING-Rough | 11/19/2020 | Corrections Issued | KEVIN SARGSYAN |
| Underground Mechanical | 11/23/2020 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 12/16/2020 | Approved | MICHAEL PELHAM |
| Reinforced Concrete Frame | 2/3/2021 | Partial Approval | JUAN VALENZUELA |
| Masonry Wall/Backfill | 3/1/2021 | Not Ready for Inspection | JUAN VALENZUELA |
| Deputy Steel/Welding | 3/4/2021 | Approved | ROBERT SHELLY |
| Deputy Steel/Welding | 3/5/2021 | Approved | ROBERT SHELLY |
| Floor/Roof Diaphrgm/Shear Wall | 3/23/2021 | Partial Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 4/5/2021 | Partial Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 4/9/2021 | Partial Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 4/30/2021 | Partial Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 6/9/2021 | Corrections Issued | JUAN VALENZUELA |
| Deputy Steel/Welding | 7/14/2021 | Conditional Approval | JUAN VALENZUELA |
| Deputy Wood Construction | 9/10/2021 | Conditional Approval | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 10/20/2021 | Partial Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 11/15/2021 | Partial Approval | KENNETH NAGLE |
| PLUMBING-Rough | 1/10/2022 | Partial Inspection | JUAN VALENZUELA |
| PLUMBING-Rough | 1/19/2022 | Partial Approval | JUAN VALENZUELA |
| Underground Mechanical | 2/9/2022 | Partial Approval | JUAN VALENZUELA |
| ELECTRICAL-Rough | 2/11/2022 | Partial Approval | JUAN VALENZUELA |
| HVAC-Rough | 2/18/2022 | Partial Approval | JUAN VALENZUELA |
| PLUMBING-Rough | 2/23/2022 | Partial Inspection | JUAN VALENZUELA |
| Deputy Drilled-In Anchors | 3/3/2022 | Conditional Approval | JUAN VALENZUELA |
| Deputy Wood Construction | 3/3/2022 | Conditional Approval | JUAN VALENZUELA |
| Sewer | 3/3/2022 | Approved | JUAN VALENZUELA |
| Underground Mechanical | 3/3/2022 | Partial Approval | JUAN VALENZUELA |
| PLUMBING-Rough | 3/10/2022 | Conditional Approval | MICHAEL PELHAM |
| ELECTRICAL-Rough | 3/11/2022 | Approved | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 3/11/2022 | Partial Approval | JOHN KIDWELL |
| HVAC-Rough | 3/11/2022 | Approved | JOHN KIDWELL |
| BUILDING-Rough-Frame | 3/14/2022 | Not Ready for Inspection | JUAN VALENZUELA |
| Green Building Rough | 3/14/2022 | Not Ready for Inspection | JUAN VALENZUELA |
| PLUMBING-Rough | 3/14/2022 | Corrections Issued | JUAN VALENZUELA |
| Shower Pan | 3/14/2022 | Partial Approval | JUAN VALENZUELA |
| Verify Sprinkler Sign Off | 3/14/2022 | Approved | JUAN VALENZUELA |
| Special/Order Compliance | 3/15/2022 | Partial Inspection | PATRICK QUALEY |
| Wood Frame | 3/15/2022 | Partial Inspection | ANDREW NAVE |
| BUILDING-Rough-Frame | 3/25/2022 | Approved | JUAN VALENZUELA |
| Green Building Rough | 3/25/2022 | Approved | JUAN VALENZUELA |
| Insulation | 3/25/2022 | Approved | JUAN VALENZUELA |
| Interior/Exterior Lathing | 3/25/2022 | Partial Approval | JUAN VALENZUELA |
| Shower Pan | 3/25/2022 | Partial Approval | JUAN VALENZUELA |
| Interior/Exterior Lathing | 4/5/2022 | Partial Approval | JOHN KIDWELL |
| Interior/Exterior Lathing | 4/13/2022 | Partial Approval | JUAN VALENZUELA |
| Drywall Nailing | 4/20/2022 | Approved | KRISTEN CAUSEY |
| Gas Test | 10/26/2022 | Approved | JUAN VALENZUELA |
| ELECTRICAL-Final | 11/29/2022 | Partial Inspection | JUAN VALENZUELA |
| PLUMBING-Final | 1/10/2023 | Corrections Issued | CLAYTON GRAHAM |
| PLUMBING-Final | 1/27/2023 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Final | 1/31/2023 | Corrections Issued | KEVIN SARGSYAN |
| ELECTRICAL-Final | 2/2/2023 | Not Ready for Inspection | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 2/2/2023 | Approved | KEVIN SARGSYAN |
| Green Building Final | 2/2/2023 | Corrections Issued | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 2/2/2023 | SGSOV Approved | KEVIN SARGSYAN |
| Smoke Detectors | 2/2/2023 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Final | 2/9/2023 | Approved | MICHAEL PELHAM |
| HVAC-Final | 2/10/2023 | Partial Approval | OGANES TARAKHCHYAN |
| HVAC-Final | 2/14/2023 | Approved | OGANES TARAKHCHYAN |
| Final | 2/21/2023 | Corrections Issued | KEVIN SARGSYAN |
| Green Building Final | 2/21/2023 | Approved | KEVIN SARGSYAN |
| Service/Power Release | 3/9/2023 | Approved | KENNETH NAGLE |
| Final | 4/17/2023 | OK to Issue CofO | KEVIN SARGSYAN |