11361 N CLYBOURN AVE 91342
Certificate Information: 11361 N CLYBOURN AVE 91342
- Application / Permit
- 19010-20000-02289
- Plan Check / Job No.
- B19VN08941
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New irr. 22'-6" x 44'-2" two-story Accessory Dwelling Unit per AB 494 and SB 229
- Permit Issued
- Issued on 3/31/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 5/14/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/31/2019 | APPLICANT |
| Green Plans Picked Up | 6/17/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 6/20/2019 | ANGELICA DAVE |
| Corrections Issued | 6/24/2019 | ANGELICA DAVE |
| Quality Review Completed | 6/25/2019 | CHON CHIO KUO |
| Building Plans Picked Up | 6/27/2019 | APPLICANT |
| Applicant returned to address corrections | 3/19/2020 | ANGELICA DAVE |
| Plan Check Approved | 3/24/2020 | ANGELICA MARTINEZ |
| Issued | 3/31/2020 | LADBS |
| CofO in Progress | 2/17/2022 | MICHEL ABAJAN |
| No Progress | 2/23/2022 | MICHAEL TEMPLE |
| CofO in Progress | 4/28/2022 | MICHAEL TEMPLE |
| Permit Finaled | 5/14/2022 | MICHAEL SMITH |
| CofO Issued | 5/14/2022 | MICHAEL SMITH |
| Permit Finaled | 5/14/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| GPI Written Notices | Cleared | 6/21/2019 | ANGELICA MARTINEZ |
| Grading Pre-Inspection | Cleared | 6/21/2019 | ANGELICA MARTINEZ |
| Address approval | Cleared | 7/29/2019 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 7/29/2019 | CELINA MORENO |
| Sewer availability | Cleared | 8/21/2019 | ELAINE LEI |
| Green Code | Cleared | 8/30/2019 | MICHAEL AYERS |
| Low Impact Development | Cleared | 9/18/2019 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 9/19/2019 | GUILLERMO PETRA |
| Specific Plan | Cleared | 9/19/2019 | PEGGY MALONE-BROWN |
| Flood clearance | Cleared | 11/14/2019 | TUYEN LE |
| Hydrant and Access approval | Cleared | 3/18/2020 | JEREMY CARTER |
Contact Information
| Contractor | Williams Christopher; Lic. No.: 711380-B | P O BOX 8652 LA CRESCENTA, CA 91224 |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| FLOOD-Elevation Certificate | 11/5/2020 | Not Ready for Inspection | MICHEL ABAJAN |
| Footing/Foundation/Slab | 11/5/2020 | Corrections Issued | MICHEL ABAJAN |
| Footing/Foundation/Slab | 11/13/2020 | Partial Approval | MICHEL ABAJAN |
| Pre-Inspection | 11/13/2020 | Partial Inspection | MICHEL ABAJAN |
| Special/Order Compliance | 11/13/2020 | Partial Inspection | MICHAEL TEMPLE |
| FLOOD-Elevation Certificate | 11/18/2020 | Approved | MICHEL ABAJAN |
| Footing/Foundation/Slab | 11/18/2020 | Approved | MICHEL ABAJAN |
| Pre-Inspection | 12/10/2020 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/19/2021 | Partial Approval | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/29/2021 | Partial Approval | MICHEL ABAJAN |
| Deck | 2/5/2021 | Partial Approval | MICHEL ABAJAN |
| ELECTRICAL-Rough | 3/24/2021 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 3/24/2021 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 4/7/2021 | Approved | MICHEL ABAJAN |
| FLOOD-Proofing Certificate | 4/7/2021 | Approved | MICHEL ABAJAN |
| Green Building Rough | 4/7/2021 | Approved | MICHEL ABAJAN |
| MERV13>=Rough | 4/7/2021 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 4/7/2021 | Approved | MICHEL ABAJAN |
| Verify Sprinkler Sign Off | 4/7/2021 | Approved | MICHEL ABAJAN |
| Shower Pan | 4/21/2021 | Approved | MICHEL ABAJAN |
| Insulation | 4/27/2021 | Partial Inspection | MORRIS JACKSON |
| Pre-Inspection | 4/27/2021 | Partial Inspection | ALIZAH MAYAGOITIA |
| Wood Frame | 5/3/2021 | Approved | MICHEL ABAJAN |
| Insulation | 5/12/2021 | Approved | KRISTEN CAUSEY |
| Interior/Exterior Lathing | 5/12/2021 | Partial Approval | KRISTEN CAUSEY |
| Pre-Inspection | 5/12/2021 | Partial Inspection | JAVIER RAMOS JR |
| Drywall Nailing | 5/24/2021 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 12/17/2021 | Approved | MICHEL ABAJAN |
| Final | 12/17/2021 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 12/17/2021 | Not Ready for Inspection | MICHEL ABAJAN |
| HVAC-Final | 12/17/2021 | Approved | MICHEL ABAJAN |
| MERV13>=Final | 12/17/2021 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 12/17/2021 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 12/17/2021 | SGSOV Approved | MICHEL ABAJAN |
| Service/Power Release | 12/17/2021 | Not Ready for Inspection | MICHEL ABAJAN |
| Smoke Detectors | 12/17/2021 | Approved | MICHEL ABAJAN |
| Final | 2/17/2022 | OK to Issue CofO | MICHEL ABAJAN |
| Green Building Final | 2/17/2022 | Approved | MICHEL ABAJAN |
| Service/Power Release | 2/17/2022 | Approved | MICHEL ABAJAN |
| Pre-Inspection | 2/23/2022 | Corrections Issued | MICHAEL TEMPLE |
| Pre-Inspection | 4/28/2022 | Approved | MICHAEL TEMPLE |